This process results in the assignment of team members (Project Coordinator, Construction Safety Officer and SEG lead) to a project. The process is reviewed by the eB Admin and the selected team members are added to the project and notified.
|
...
Deck of Cards |
---|
|
Card |
---|
| This process is spawned by the 02.03.05 CRSP Screening Kickoff ( CRSPKCRSPS) or initiated by the e-B admin for non-CRSP projects. A project manager may initiate this process. The process can be reviewed by Note |
---|
Escalation rules apply to this process. - Three days after the Start step the e-B admin
| , Project Manager, and the Program Manager.No other processes are spawned by Team Assignment- is notified.
- If a PM has been identified, the e-B Admin will put that person in the role and add a note to the PM that the TA process has been in the “Team Assignment” step for 3 days but is still incomplete.
- If the PM has not yet been assigned, the eB Admin will send an Action Item to the Program Manager requesting that the PM be assigned. Once the Action Item response is received, the PM will be put in the role and a note added to the PM that TA process has been in the “Team Assignment” step for 3 days but is still incomplete.
- Seven days after the Start step the eB admin is notified.
- The eB Admin will move the process to the next step, putting only identified team members in roles (and notifying them).
- If additional team members are required, process "01.03-Add a Resource to a Project" should be used.
|
|
Card |
---|
| Image Removed Image Added |
Card |
---|
label | Training: Actors and ActionsStep Descriptions |
---|
| 1. Initiation Cloak |
---|
The process is usually started by a Spawn step, but can be started by the eB Admin , or Project Manager or automatically spawned by the CRSP Screening Process. The initiator fills out the required fields take the following action: Submit . In this step a Program Manager. Project Manager and CC Planner can be assigned. The Program Manager is required. When complete the Submit action is taken. - If a Project Manager assignment has not been assigned the process moves to Team Assignments - Including PM.
- If a Project Manager has been assigned the
- Status of Process: Submitted
- If Project Manager has already been assigned, process moves to Team Assignments w/o Program Manager
- If Project Manager has not been assigned, process moves to Team Assignments - PM previously assigned.
| 2.Team Assignments w/o Program Manager- PM Previously Assigned Cloak |
---|
Each actor assignor in this step assigns their respective team members and takes the following Submit action: Submit Status of Process: Pending. Note that some roles are required before the process moves forward.
The next step is eB Admin. Next Step: eB Admin | 3.Team Assignments - Including PM actor assignor in this step assigns their respective team members and takes the | following action:Submit Status of Process: PendingNext Step: Submit action. Note that Project Manager is a required field for this step.
The next step is |
4. eB Admin Cloak |
---|
An eB Admin reviews the assignments and automation assigns all team members selected to the project front end and backend at the project role level and | takes the following action:Complete
- Status of Process: Approved
- Next Step: Finished
Finished Cloak |
---|
The process is complete |
|
|
e-Builder Instructions
The names of eligible individuals, as determined by their e-Builder role(s), are displayed in a dropdown menu for each position being filled.
This process is considered complete when a Project Coordinator, Construction Safety Officer and SEG Lead have all been assigned to the project.
completes the process. The next step is Finish. |
Finish |
|
...