The purpose of this process is the review and execution contracts and/or Purchase Orders. The process enables external vendors and external executors to electronically route and approve all PO's and contracts.
The process generates an e-Builder Purchase Order following issuance of the SAP PO, and automatically triggers the Contract Approval process whenever the PO data meets the thresholds for a formal contract document.
Note that in e-Builder a purchase order Purchase Order is referred to as a Commitment.
Process Details
Composition Setup
Deck of Cards
id
Issue
Card
label
Summary
This process can be started by the Project Coordinator, Project Manager, Administrative AssistantAdministrative Assistant, CC Director, CC Planner, CC Planning Director, CC Planning Manager, Director of Finance and Administration, eB Admin, Furniture Designer, OCP Planner, SPT Commissioning Lead, SPT Lead, VPF Strategic Sourcing.This process is also started when Send and Initialize is used as the notification option in the 4.0 Bidding StepProgram Manager, Project Coordinator, Project Manager, SPT Commissioning Lead, SPT Lead, and VPF Strategic Sourcing.
Card
label
Process Map
Image RemovedImage Added
Card
label
Step Descriptions
Note that these step descriptions are in the process of being updated.
Toggle Cloak
Start
Cloak
The Project Coordinator or Project ManagerProcess Initiatorfills out the required fields and executes the Submit actionchooses to submit.
The next step is PM Initiate ProcessTotal $ <= 0?
When asked to identify the type of contract being requested this document may be helpful.
Toggle Cloak
Total $ <= 0?Conditional
Cloak
The PM Initiate Process? conditional step determines the path the process will take based on if the Data Field “Did the PM Initiate the Process?” has a value of “Yes”.
If the value is Yes the next step is Contract Required?
Total $ <=0? conditional checks if the amount for all commitment items entered is less than or equal to $ 0.
If True (Yes) the next step is Initiator Revise.
If False (No) the next step is PjFnAmt < ComAmtIf the value is False the next step is PM Review?
Toggle Cloak
Initiator RevisePRJCT Status CHK
Cloak
The PMThis conditional reviews the process and verifies the Contract or PO being added to the project and chooses the Submit action.if the Project is in a status that allows for the submission of a Purchase Order request. All Active status are allowed to create new POs.
If True (Yes) the next step is PM Fixes Project Status
If False (No) the next step is Total $<= 0The next step is Contract Required?
Toggle Cloak
PM Initiate Process? ConditionalFixes Project Status
Cloak
The Process Initiator reviews the Contract Document.
If Submit is chosen the next step is CA Manager Reviews.
If Revise is chosen the next step is Contract Admin Assembles Contract
Multiple fields are evaluated to determine the path that the process will take.
If True the next step is Construction?
If False the next step is Purch Req MM.
Toggle Cloak
Contract Required? Conditional
Cloak
Multiple fields are evaluated to determine the path the process will take.
If True the next step is eB Admin Updates CSI Codes.
If False the next step is DoF Procurement Reviews.
Toggle Cloak
Contract >$10k? Conditional
Cloak
eB Admin runs the bid tabulation report and combines it with the process import template to do a quick upload into the processes to get the CSI and GL information on the commitment line item custom fields. Through the import the following Submit action is taken.
The next step is DoF Procurement Review.
Toggle Cloak
PM Review
Cloak
DoF Procurement reviews the process and executes the Submit action.
The next step is Contract Admin Assembles Contract.
Toggle Cloak
Vendor Manager Review of SoS
Cloak
The Contract Admin reviews the process and uploads the assembled contract to be executed and has the option to take an acton to Submit or Revise.
As part of this step the Contract Admin associates a bid process to this PO/Contract process by using the Contract Number Lookup. (Instructions are in included on the process page)
If Submit is chosen the next step is Initiator Reviews Contract.
If Revise is chosen the next step is DoF Procurement Reviews.
Checking for contract choice discrepancies with 3 conditionals - CR=Y/CT=N, CR=N/CT!=N, and No Contrct?
Cloak
If the Process Initiator selects "No" for the question "Contract Required?" but then chooses a contract type th process moves to the Initiator Revise step.
If the Process Initiator selects Yes" for the question "Contract Required?" but then chooses one of the "No Contract" types the process moves to the Initiator Revise step.
If the Process Initiator selects "No" for the question "Contract Required?" and then chooses one of the "No Contract" types the process moves to a MM and then the Procurement review step.
If the Process Initiator selects "Yes" for the question "Contract Required?" and then chooses a contract type the process moves to the Vendor Manager Review step.
Toggle Cloak
PjFnAmt < ComAmt?
Cloak
The PjFnAmt < ComAmt? conditional checks if the Projected Final Contract Amount is less than the amount of the Commitment you are trying to establish.
If True (Yes) the next step is Initiator Revise.
If False (No) the next step is PjFnAmt < ComAmt?
Toggle Cloak
Initiator Revise
Cloak
The Initiator Revise step shares a page layout with the Start step and allows the Process Initiator to make changes and resubmit the process.
If Resubmit is chosen the next step is PM Initiate Process?
If Void is chosen the next step is Finish.
Toggle Cloak
PM Initiate Process?
Cloak
The PM Initiate Process? conditional step determines the path the process will take based on if the data field “Did the PM Initiate the Process?” has been marked “Yes” or "No" in the previous step.
If True (Yes) the next step is Contract Required?
If False (No) the next step is PM Revise.
Toggle Cloak
Contract >$10K?
Cloak
TheContract >$10K? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$10K) the next step is Vendor Manager Review of SoS.
If False (<=$10K) the next step isPurch Req M.M.
Toggle Cloak
PM Review
Cloak
The PM reviews the process and verifies the Contract or PO being added to the project and chooses the Submit action.
The next step is Contract Required?
Toggle Cloak
Vendor Manager Review of SoS
Cloak
The Vendor Manager reviews the Selection of Source information and confirms the vendor exists in SAP.
Toggle Cloak
Contract Admin Assembles Contract
Cloak
The initiator reviews the contract and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Releases Contract.
If Revise is chosen the next step is Contract Admin Assembles Contract.
Toggle Cloak
Initiator Reviews Contract
Cloak
DoF Procurement reviews the contract and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Vendor Executes Contract.
If Revise is chosen the next step is Contact Admin Assembles Contract.
Toggle Cloak
CA Manager Reviews & Initials
Cloak
The Vendor reviews, signs and uploads the contract. The Vendor has the option to Submit or Revise. (Request Revision)
If Submit is chosen the next step is Vendor Signature StepContract Admin Assembles Contract.
If Revise is chosen the next step is DoF Procurement Releases Contract.
Toggle Cloak
OGC Counsel Review
Cloak
The Vendor Signature Step finalizes the vendor's electronic signature with DocuSign allowing for the next person to sign the document. A Code Complete action is automatically taken.
The next step is DoF Procurement Approves Contract.
Toggle Cloak
Contract Admin Releases Contract
Cloak
DoF Procurement reviews the process and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Campus Construction.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
Initiator Revise 1
Cloak
The Campus Construction step determines the path the process will take based on the Program Type and if the contract is managed by a different program.
If True (Yes) the next step is SP&T Program?
If False (No) the next step is OCP?
Toggle Cloak
Hold for Vendor Contract Execution
Cloak
The SP&T Program? Step determines the path the process will take based on the Program Type or if the project is managed by a different program.
If True (Yes) the next step is VPF Strategic Sourcing Review.
If False (No) the next step is Projects Director Review.
Toggle Cloak
Contract Admin Final Review
Cloak
The VPF Strategic Sourcing Director reviews the process and contract, then takes the Submit action.
The next step is Contract<10M
Toggle Cloak
Campus Construction? Conditional
Cloak
The Projects Director reviews the process and contract, then takes the Submit action.
The next step is Contract <$10M
Toggle Cloak
SPT Program?
Cloak
The Contract <$10M conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $10M.
If True (Yes) the next step is CC Director Executes Contract.
If False (No) the next step is CC Director Review.
Toggle Cloak
SPT Director Review
Cloak
The CC Director reviews the process and executes the contact, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Proj. Contract>$10m? Conditional
Cloak
The CC Director reviews the process and the contract, then takes the Submit action.
The next step is Contract <$100M.
Toggle Cloak
CC Director Review
Cloak
The OCP? conditional step determines the path the takes based on Program Type or if the contract is managed by a different program.
If True (Yes) the next step is Contract <$500K.
If False (No) the next step is M&U?
Toggle Cloak
CC Director Executes Contract
Cloak
The Contract <$500K conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $500K.
If True (Yes) (<) the next step is OCP Director Executes.
If False (No) (>) the next step is OCP Director Review.
Toggle Cloak
CA Mgr & Dir. Finance
Cloak
The OCP Director reviews the process and executes the contract then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
OCP? Conditional
Cloak
The OCP Director reviews the process and contract then takes the Submit action.
The next step is Contract <$100m.
Toggle Cloak
Proj. Contract> $500k? Conditional
Cloak
The M & U? Conditional step will determine the path the process takes based on the Program Type or if the contract is managed by a different program
If True (Yes) the next step is Utilities Program.
If False (No) the next steep is Campus Services.
Toggle Cloak
OCP Director Review
Cloak
The Utilities Program? Conditional step will determine the path process takes based on the Program Type or if the contract is managed by a different program.
If True (Yes) the next step is Contract <$100K.
If False (No) the next step is SEG Program.
Toggle Cloak
OCP Director Execute
Cloak
The Contract < $100k conditional step determines the path process takes based on the Current Commitment Value being greater than or less than $100k.
If True (Yes) the next step is Utilities Director Execute.
If False (No) the next step is Utilities Director Review.
Toggle Cloak
CSM? Conditional
Cloak
The Utilities Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Proj. Contract>$5m? Conditional
Cloak
The Utilities Director reviews the process and contract, then takes the Submit action.
The next step is Contract <$5m.
Toggle Cloak
CSM Director Executes
Cloak
The SEG Program?conditionalstep determines the path the process takes based on the Program Type or if the contract is managed by a different program, Contract Program Type = SEG.
If True (Yes) the next step is Contract <$100k.
If False (No) the next step is Contract <$100k.
Toggle Cloak
CSM Director Review
Cloak
The Contract < $100k conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $100k.
If True (Yes) the next step is O&M Director Execute.
If False (No) the next step is O&M Director Review.
Toggle Cloak
Utilities Program? Conditional
Cloak
The O&M Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Contract> $1M Conditional
Cloak
tThe O&M Director reviews the process and contract, then takes the Submit action.
The next step is Contract <$5m
Toggle Cloak
Utilities Director Execute
Cloak
The Contract < $100k conditional step determines the path process takes based on the Current Commitment Value being greater than or less than $100k.
If True (Yes) the next step is SEG Director Execute.
If False (No) the next step is SEG Director Review.
Toggle Cloak
Utilities Director Review
Cloak
The SEG Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
FEG Program? Conditional
Cloak
The SEG Director reviews the process and the contract, then takes the Submit action.
The next step is Contract <$100m.
Toggle Cloak
FEG Director Review
Cloak
The Contract < $5m conditional step will determine the path process takes based on the Current Commitment Value being greater than or less than $5m.
If True (Yes) the next step is M&U Director Executes Contract.
If False (No) the next step is M&U Director Review.
Toggle Cloak
Prj Contract > 10mil? Conditional
Cloak
The M&U Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
VP, CSS Reviews
Cloak
The M&U Director reviews the process and the contract, then takes the Submit action.
The next step is Contract <$100m.
Toggle Cloak
CP, CSS Executes
Cloak
The Campus Services? Conditional step determines the path the process takes based on the Program Type or if the contract is managed by a different program, Contract Program Type = Campus Services..
If True (Yes) the next step is Contract <$5m.
If False (No) the next step is Contract <$10m.
Toggle Cloak
>$10mil <$100mil? Conditional
Cloak
The Contract < $5m conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $5m.
If True (Yes) the next step is CS Director Execute.
If False (No) the next step is CS Director Review.
Toggle Cloak
VP Finance Executes
Cloak
The CS Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
EVPT Executes
Cloak
The CS Director reviews the process and the contract, then takes the Submit action.
The next step is Contract < $100m .
Toggle Cloak
Initiator Revise 3
Cloak
The Contract <$10m conditional step determines the path the process takes based on the Current Commitment value being greater than or less than $10m.
If True (Yes) the next step is IBO Director Executes Contract.
If False (No) the next step is IBO Director Reviews Contract.
Toggle Cloak
Contract Signature
Cloak
The IBO Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Purch Req M.M.
Cloak
The IBO Director reviews the process and the contract, then takes the Submit action.
The next step is Contract <100m.
Toggle Cloak
CRSP Admin & Procurement Review
Cloak
The Contract <$100m conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $100m.
If True (Yes) the next step is Deputy EVP Executes Contract.
If False (No) the next step is Deputy EVPT Review.
Toggle Cloak
>$25K? Conditional
Cloak
The Deputy EVPT reviews the process, signs the contract and takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Initiator Revise 2
Initiator Revise 1.
If Resubmit Cntrcts is chosen the next step is Contract Admin Assembles Contract.
If Resubmit Vndr Mgr is chosen the next step is Vendor Manager review of SoS.
If Resub to CA Mgr is chosen the next step is CA Manager Reviews.
Toggle Cloak
Contract Admin Assembles Contract
Cloak
The Contract Admin reviews the process and uploads the assembled Contract Document to be executed.
As part of this step the Contract Admin associates a bid process to this PO/Contract process by using the Contract Number Lookup. (Instructions are in included on the process page)
If Submit is chosen the next step is Initiator Reviews Contract.
If Revise is chosen the next step is Initiator Revise 1.
Toggle Cloak
Initiator Reviews Contract
Cloak
The Process Initiator reviews the Contract Document.
If Submit is chosen the next step is CA Manager Reviews.
If Revise is chosen the next step is Contract Admin Assembles Contract.
Toggle Cloak
CA Manager Reviews
Cloak
The DoF Procurement Manager and the Contract Admin Manager reviews the Contract Document and determine whether or not it meets the requirements for OGC Counsel Review.
If Submit is chosen the next step is Contract Admin Releases Contract.
If Revise is chosen the next step is Initiator Revise 1.
If To DOF Counsel is chosen the next step is OGC Counsel Review.
Toggle Cloak
OGC Counsel Review
Cloak
The DOF General Counsel reviews the Contract Document.
If Submit is chosen the next step is Contract Admin Releases Contract.
If Revise is chosen the next step is Initiator Revise 1.
Toggle Cloak
Contract Admin Releases Contract
Cloak
The Contract Admin sends the contract to the vendor for review and signature, and records the date the contract was sent.
If Submit is chosen the Contract Document has been sent to the vendor. The next step is Vendor Executes Contract.
If Revise is chosen the next step is Contact Admin Assembles Contract.
Toggle Cloak
Initiator Revise 1
Cloak
The Initiator Revise 1 step allows the Process Initiator to make changes and resubmit the process.
If Resubmit is chosen the next step is Vendor Manager review of SoS.
If Cnt Ambl Cntr is chosen the next step is Contract Admin Assembles Contract.
If Resub CA Mgr Rv is chosen the next step is CA Manager Reviews.
If Resub CA Rel Ct is chosen the next step is Contract Admin Releases Contract.
If Void is chosen the next step is Finish.
If No Contract Reqd the next step is Procurement Review.
Toggle Cloak
Hold for Vendor Contract Execution
Cloak
The Contract Admin reviews the signed contract received from the vendor, records the date they received the signed contract and then removes and replaces the unsigned contract with the received vendor signed contract into the Contract Document field.
If Submit is chosen the next step is Contract Admin Final Review.
If BackToInitiator is chosen the next step is the Initiator Revise 1 step.
Toggle Cloak
Contract Admin Final Review
Cloak
The Contract Admin Manager reviews the vendor signed contract for final review before going to directors steps.
If Submit is chosen the next step is Campus Construction?
If Revise is chosen the next step is Hold for Vendor Contract Execution.
Toggle Cloak
Campus Construction?
Cloak
The Campus Construction? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal.
If True (Yes) the next step is SP&T Program?
If False (No) the next step is OCP?
Toggle Cloak
SPT Program?
Cloak
The SPT Program? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is System Performance & Turn-over.
If True (Yes) the next step is SPT Director Review
If False (No) the next step isProj. Contract>$10m?
Toggle Cloak
SPT Director Review
Cloak
The SPT Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Proj. Contract>$10m?
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Proj. Contract>$10m?
Cloak
TheProj. Contract>$10m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$10m) the next step is Vendor Manager Review of SoS.
If False (<=$10m) the next step isPurch Req M.M.
Toggle Cloak
CC Director Review
Cloak
The CC Director reviews the Contract Document attached to the process and if required attaches the CC Director Memo.
If Submit is chosen the next step is CA Mgr & Dir. Finance.
If Revise is chosen the next step is Initiator Revise 3.
If Send To OGC is chosen the next step is OGC Counsel Review.
Toggle Cloak
CC Director Executes Contract
Cloak
By taking the Submit action at this step the CC Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
CA Mgr & Dir. Finance
Cloak
The Contract Admin Manager and the Director of Finance and Administration review the attached CC Director Memo and upload the Executed Memo to the process.
If Submit is chosen the next step is VP, CSS Reviews
If Revise is chosen the next step is CC Director Review
Toggle Cloak
OCP?
Cloak
The OCP? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is OCP.
If True (Yes) the next step is Proj. Contract> $500k?
If False (No) the next step isCSM?
Toggle Cloak
Utilities Program Manager Reviews Cntrct
Cloak
By taking the Submit action at this step the Utilities Program Manager is Reviewing the contract.
If Submit is chosen the next step is Contract> $1M.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Proj. Contract> $500k?
Cloak
TheProj. Contract> $500k? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$500K) the next step is CSM Director Executes
If False (<=$500K) the next step is CSM Director Reviews
Toggle Cloak
OCP Director Review
Cloak
The OCP Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Prj Contract > $10mil?
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
OCP Director Execute
Cloak
By taking the Submit action at this step the OCP Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
CSM?
Cloak
The CSM? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is CSG or R&M.
If True (Yes) the next step is Proj. Contract>$5m?
If False (No) the next step isUtilities Program?
Toggle Cloak
Proj. Contract>$5m?
Cloak
TheProj. Contract>$5m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$5m) the next step is CSM Director Review.
If False (<=$5m) the next step isCSM Director Executes.
Toggle Cloak
Facilities Operations Execute
Cloak
By taking the Submit action at this step the Facilities Operations Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Facilities Operations Review
Cloak
By taking the Submit action at this step the Facilities Operations Director is Reviewing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
CSM Director Executes
Cloak
By taking the Submit action at this step the O&M Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
CSM Director Review
Cloak
The SPT Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Prj Contract > 10mil?
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Utilities Program?
Cloak
The Utilities Program? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is CUP - OPS, or Utilities.
If True (Yes) the next step is Contract> $1M.
If False (No) the next step isFEG Program?
Toggle Cloak
Contract> $1M
Cloak
TheProj. Contract>$10m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$1m) the next step is Utilities Director Review.
If False (<=$1m) the next step is Utilities Director Executes.
Toggle Cloak
Utilities Director Execute
Cloak
By taking the Submit action at this step the Utilities Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Utilities Director Review
Cloak
The SPT Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Proj. Contract>$10mil?
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
FEG Program?
Cloak
The FEG Program? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is Energy, or SEG.
If True (Yes) the next step is FEG Director Review.
If False (No) the next step isPrj Contract > 10mil?.
Toggle Cloak
FEG Director Review
Cloak
The FEG Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Proj. Contract>$10mil?
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Prj Contract > 10mil?
Cloak
ThePrj. Contract > 10mil? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount
If True (>$10m) the next step is Dir of Fin & Adm Review 1.
If False (<=$10m) the next step isDir of Fin & Adm Review 2.
Toggle Cloak
Dir of Fin & Adm Review 1
Cloak
The Director of Finance and Administration reviews the Contract Document attached to the process.
If Submit is chosen the next step is VP, CSS Reviews.
If Revise is chosen the next step is Initiator Revise 3.
IfSend CC Director is chosen the next step is CC Director Review.
Toggle Cloak
Dir of Fin & Adm Review 2
Cloak
The Director of Finance and Administration reviews the Contract Document attached to the process.
If Submit is chosen the next step is VP, CSS Executes.
If Revise is chosen the next step is Initiator Revise 3.
If Send CC Director is chosen the next step is CC Director Executes Contract.
Toggle Cloak
VP, CSS Reviews
Cloak
The VP for Campus Services and Stewardship reviews the Contract Document attached to the process.
If Submit is chosen the next step is >$10mil <$100mil?
If Revise is chosen the next step is CA Mgr & Dir. Finance.
Toggle Cloak
VP, CSS Executes
Cloak
By taking the Submit action at this step the VP for Campus Services and Stewardship is executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
>$10mil <$100mil?
Cloak
The>$10mil <$100mil? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$10m and <$100mil) the next step is VP Finance Executes.
If False (>=$100mil) the next step is EVPT Executes.
Toggle Cloak
VP Finance Executes
Cloak
By taking the Submit action at this step the VP for Finance is executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
EVPT Executes
Cloak
By taking the Submit action at this step the EVP&T Office is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Initiator Revise 3
Cloak
The Initiator Revise3step allows the Process Initiator to make changes and resubmit the process.
If Resubmit is chosen the next step is Campus Construction?
If Void is chosen the next step is Finish.
Toggle Cloak
Contract Signature
Cloak
Contract Signature will finalize the director's electronic signatures using DocuSign. Once complete it will automatically take the Code Complete action. (Signifies that e-Builder has completed a task}
The next step is SAP PO Hold Step
Toggle Cloak
Purch Req M.M.
Cloak
The Purch Req M.M. step is a mail merge automation step that completes the purchase requisition from the purchase requisition template.
The next step is CRSP Admin & Procurement Review.
Toggle Cloak
Procurement Review
Cloak
The DoF Procurement Manager and the Contract Admin Manager review the process and confirms that the vendor exists in SAP and an SAP issued vendor number is correctly entered in the "Company Number" field in the Contacts Module.
If Submit is chosen the next step is >$25K?
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
>$25K?
Cloak
The>$25K? conditional step determines the path the process will take based on the amount entered for the Commitment you are trying to establish.
If True (>$25K) the next step is Campus Construction?
If False (<=$25K) the next step is SAP PO Hold Step
Cloak
The Deputy EVPT reviews the process and the contract and takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
SAP PO Hold Step
Cloak
Hold step for SAP Processing.
Once processed the next step is the PO M.M. step
The EVPT Office reviews the process and the contract and takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
PO M.M
Cloak
The PO M.M step is a mail merge automation step that completes the Purchase Order mail merge document.
The next step is AA sends Exec. PO\Contract to vendor
Contract Signature will finalize the director's electronic signatures using DocuSign. Once complete it will automatically take the Code Complete action. (Signifies that e-Builder has completed a task}
The next step is SAP PO/Contract Hold Step.
Toggle Cloak
AA sends Exec. PO\Contract to vendor
Cloak
The Purchase req MM step is a mail merge automation that completes the purchase requisition from the purchase requisition templateAdministrative Assistant should review the documents attached to the process, send the executed documents to the vendor and record the date that the executed documents were sent.
The next step is DoF Procurement ReviewFinish.
Toggle Cloak
Finish
Cloak
Card
label
Commitment Line IntructionsInstructions
Enter information for each commitment item.
Item Number - a sequential number denoting each line.
Budget Line Item - Associate each entry with a Budget Line Item.
Current Budget - Displays the current budget.
Description - editable field for a description.Description of the Budget Line Item
Retainage Percent - enter the retainage percent when applicable.
Amount - the amount of the the commitment line
Allowance Item - Check if it is an allowance item.
Custom Fields - used to enter the cost object.
Pay particulate attention to the Retainage percentage as that determines how retainage is calculated when invoices are submitted.
A Retainage of five percent should be expressed as 5.00 (as in the example)
The following list of items, though part of the budget template, cannot be used to generate a commitment. You cannot place internal charges on a PO.
If you are issuing a PO to cover vendor expenses use the reimbursable line item for that vendor type. For example, for A/E expenses use B-30-125 A/E Reimbursables.
Do Not Use list is below:
A15-005
A15-005 DoF Project Administration
A15-010
A15-010 OCP Project Administration
A15-015
A15-015 Utilities Project Administration
A15-020
A15-020 SEG Project Administration
A15-025
A15-025 EHS Project Administration
A15-035
A15-035 Service and Support-Staff
A15-045
A15-045 Employee Benefit Charges (EB) - General
A20-050
A20-050 Travel Expenses
C50-685
C50-685 Other MIT Internal Charges
C55-730
C55-730 Steam
C55-745
C55-745 Chilled Water
F95-835
F95-835 EVPT Contingency
F96-840
F96-840 DoF Contingency
Card
label
Output - The Purchase Order Document
This process will print a Purchase Order document that can be sent to the vendor.
Purchase Order
This process is used for both signed contracts and purchase orders and it will display the desired document in the AA Sends Exec. PO/Contract to Vendor ... step.
When a contract is displayed the supporting purchase order is still generated. To print the purchase order:
Click the Print button.
Click the Merge Templates radio button.
Choose Purchase Order from the drop down menu.
Click the Print Button on the Mail Merge Templates menu.
Sample Purchase Order Document
PO Mail Merge Field
Notes/Description
Purchase Order Number
The Purchase Order Number in the top right hand corner of the PO (highlighted in yellow on this example) will only appear when the process has progressed through the SAP PO/Contract Hold step. Prior to that step it is possible to preview the Purchase Order, but the PO number will not appear on the form.
Date
The date field is the date that the purchase order mail merge is generated. If you reprint the purchase order the date will update.
Vendor and Vendor Address
The Vendor and vendor addresss information is derived from the Contacts module in e-Builder. If address information is missing from that module the PO fields for this information will be blank. If you update the Contacts information in e-Builder you may reprint the PO and the information will appear as updated.
Ship To
This information is derived from the building information that is part of the e-Builder project information. If room information has been added to e-Builder the room information will also print on the purchase order.
Delivery Date
This information is hardcoded. Each purchase order will have "Per Previous Agreement" in this field. Changing this field requires the assistance of an e-B admin.
Shipping Method
This information is hardcoded. Each purchase order will have "N/A" in this field. Changing this field requires the assistance of an e-B admin.
Shipping Terms
This information is hardcoded. Each purchase order will have "N/A" in this field. Changing this field requires the assistance of an e-B admin.
Payment Terms
This information is hardcoded. Each purchase order will have "Net 30" in this field. Changing this field requires the assistance of an e-B admin.
Items
Each commitment line will use the dollar figure and commitment description for the corresponding commitment in e-Builder. Each line will be sequentially numbered beginning with 001.
Project Number
The project number from e-Builder.
Project Name
The project name from e-Builder. The project name may contain the room number.
Project Contact
The proect contact is derived from Project Manager 1 in e-Builder. The phone number is hard coded and is the general switchboard number for MIT DoF.