Start Cloak |
---|
- Started by the Project Manager, CC Planner, OCP Planner, SPT Lead, or Contractor who fills in the required fields and attaches the associated Change Order Requests that are to be combined into a single General Contract Change Order.
- Be sure to add the Change Order Request properly. You must access the Filter Processes screen to select COR's to be processed. On screen instructions are provided in the process.
- When finished the initiator takes the Submit action.
- The next step is PM Review?
| PM Review Cloak |
---|
- This step is in the process so that a GCCO submitted by a contractor is immediately reviewed by the project manager before being forwarded to others. (If the project manager started the process this may seem like a duplicate step.)
- The Project Manager reviews the submission.
- As part of this step project managers must update the Schedule module to reflect any changes including the substantial completion date.
- The Project Manger takes the Submit action to advance the process.
- If revisions are needed, the project manager has the option to take the Revise action to return this process to the initiator for changes.
- If the action NTP Rev/Appv is chosen the process moves to the Contracts Reviews, Drafts, Ex. a New NTP step.
- Following the Submit action the next step is Project Budget Change?.
| Proj Budget Change?Contracts Reviews, Drafts,, Ex a New NTP Cloak |
---|
- This step is contains all of the fields that the Start step contains plus 2 additional fields; New NTP and New Fully Executed NTP which contracts uses to engage with the PM and the vendor.
- The Send to PM for Review Action is chosen then the contracts team has loaded a new NTP and is requesting that the project manager review, make edits or approve it.
- If the action Fully Exec NTP action is chosen the process moves to the Project Budget Change? step.
- If the action Revise action is chosen the process moves to the Initiator Revise step
| Cloak |
---|
- The Proj Budget Change? conditional checks if an answer was given that was not None for the Project Budget Change Type? field.
- If True (YesBudget Change) the next step is $0 Budget Change?.If False (NoNot a Budget Change) the next step is Sum of Attached CORs.
| $0 Proj Budget Change? Cloak |
---|
- The $0 Proj Budget Change? conditional checks if $0 Reallocation was selected an answer was given that was not None for the Project Budget Change Type? field.
- If True (YesBudget Change) the next step is Spawn $0 $0 Budget Change?.
- If False (NoNot a Budget Change) the next step is Spawn PBAP. Commitment Value Co
| Spawn $0 Budget Change? Cloak |
---|
- The process $0 Budget Change is started and placed in the project manager's Court.
- The Projet Manager must complete the $0 Budget Change process.
- Change? conditional checks if $0 Reallocation was selected for the Project Budget Change Type? field.
- If True (Yes) the next step is Commitment Value Co
- If False (No) the next step is Spawn PBAPFollowing the Spawn $0 Budget Change step the process moves to the Sum of Attached CORs step.
| Spawn PBAPConting or Reallo? Cloak |
---|
- The process 03.01.a - Budget Approval Process is started and placed in the Project Managers Court.
- The Project Manager must complete the 03.01.a - Budget Approval Process.
- Conting or Reallo? conditional checks if $0 Reallocation or Reallocation was selected for the Project Budget Change Type? field.
- If True (Yes) the next step is Commitment Value Co
- If False (No) the next step is Spawn PBAPFollowing the Spawn PBAP step the process moves to the CRSP Admin Mgr. Hold step.
| CRSP Admin Mgr. HoldCustom GCCO Number? Cloak |
---|
- The Custom GCCO Number? Conditional checks if the GC-CO No. field has a value.
- If True (Yes) the next step is Success?
- If False (No) the next step is Custom GCCO Number Contract Admin Manager reviews the process details and holds the process in this step until funding is applied.If Submit is chosen the next step is Sum of Attached CORs
| Sum of Attached CORsCustom GCCO Number Cloak |
---|
- This is an Automation code step in which custom code sums the attached CORsThe Custom GCCO Number automation step generates a Mail Merge document with the GCCO number entered by the initiator.
- The next step is Success? PM Review Mail Merge.
| Success?Spawn PBAP Cloak |
---|
- The Success? conditional checks if true was entered for the Success? field as a part of the Sum of Attached CORs code step.
- If True (Yes) the next step is Commitment Value Co
- process 03.01.a - Budget Approval Process is started and placed in the Project Managers Court.
- The Project Manager must complete the 03.01.a - Budget Approval Process.
- Following the Spawn PBAP step the process moves to the CRSP Admin Mgr. Hold stepIf False (No) the next step is Attach CORS.
| Attach CORSCRSP Admin Mgr. Hold Cloak |
---|
- The Project Manager is responsible attaching the missing CORs to the CORs tab of the process Contract Admin Manager reviews the process details and holds the process in this step until funding is applied.
- If Submit is chosen the next step is Sum of Attached CORs
- If Void is chosen the next step is Finish and the process is set to a Void status.
| Commitment Value CoSum of Attached CORs Cloak |
---|
- This is an Automation code step that processes the Change Ordersin which custom code sums the attached CORs.
- The next step is Success?
| Success? Cloak |
---|
- The Success? conditional checks if true was entered for the Passed Approval Success? field as a part of the Commitment Value Co Sum of Attached CORs code step.
- If True (Yes) the next step is GC Change Order M.M.PM?
- If False (No) the next step is Initiator Revise.
|
GC Change Order M.M. Cloak |
---|
- This is an Automation code step that generates the General Contract Change Order document.The next step is PM Review Mail Merge.
|
PM Review Mail Merge? Cloak |
---|
- The Project Manager reviews the process details and the file in the Change Order Document field.
- If DocuSign Submit is chosen the next step is Vendor Signature.
- If Revise is chosen the next step is Initiator Revise.
- If Take Offline is chosen the next step is Attach Vendor Signed CO.
|
Vendor Signature - PM? conditional checks if the process was submitted by someone with the Primary Role of Project Manager.
- If True (Yes) the next step is Proj Budget Change?
- If False (No) the next step is PM Review
|
Attach CORS Cloak |
---|
- The Project Manager is responsible attaching the missing CORs to the CORs tab of the process.
- If
| Cloak |
---|
- The Contractor reviews the process details and the file in the Change Order Document field.
- If DocuSign Submit is chosen the next step is Vendor Signature. Sum of Attached CORs
- If Redo Sum If Approve is chosen the step actor will be prompted to electronically sign the document, the next step is A/E Review Required?next step is Initiator Revise.
- If VoidIf Revise is chosen the next step is Initiator Revise.Finish and the process is set to a Void status.
|
Attach Vendor Signed COCommitment Value Co Cloak | The process is in this step because the vendor is not in e-Builder. It is the responsibility of the Project Manager to send the file in the Change Order Document field to the vendor.After you receive this signed document back from the vendor, remove the original document and attached this signed copy to the attach the Change Order Document field.Once the file is Downloaded and Removed reattach the signed file file.When submit is chosen the next step is A/E Review Required?
A/E Review Required? Cloak |
---|
- The A/E Review Required? conditional checks if Yes was selected for the A/E Review Required? field.
- If True (Yes) the next step is A/E Signature.
- If False (No) the next step is Program Manager Review.
|
A/E Signature - This is an Automation code step that processes the Change Orders.
- The next step is Success?
|
Success? Cloak |
---|
- The Success? conditional checks if true was entered for the Passed Approval? field as a part of the Commitment Value Co code step.
- If True (Yes) the next step is GC Change Order M.M.
- If False (No) the next step is Initiator Revise.
|
GC Change Order M.M. Cloak |
---|
- This is an Automation code step that generates the General Contract Change Order document.
- The next step is PM Review Mail Merge.
|
PM Review Mail Merge Cloak |
---|
- The Project Manager reviews the process details and the file in the Change Order Document field.
- If DocuSign Submit is chosen the next step is Vendor Signature.
- If Revise is chosen the next step is Initiator Revise.
- If Take Offline is chosen the next step is Attach Vendor Signed CO.
|
Vendor Signature Cloak |
---|
| Cloak |
---|
- The A/E Lead reviews the process details and the file in the Change Order Document field.
- If DocuSign Submit is chosen the next step is Vendor Signature.
- If Approve If Submit is chosen the step actor will be prompted to electronically sign the document, the next step is Program Manager Review.A/E Review Required?
- If Revise is chosen the next step is PM Initiator Revise.
|
Program Manager ReviewSend a MM to a Vend Cloak |
---|
- The Program Manager reviews the process details and the file in the Change Order Document field.
- If Submit is chosen the next step is Contracts Group Review.
- If Revise is chosen the next step is Initiator Revise.
|
Contracts Group Review Cloak |
---|
- The Contract Admin reviews the process details and the file in the Change Order Document field.
- If Submit is chosen the next step is Contracts Group Review.
- If Revise is chosen the next step is Initiator Revise.
| Initiator Revise Cloak |
---|
- The Initiator Revise step allows the Process Initiator to make changes and resubmit the process.
- If Resubmit is chosen the next step is PM Review
- If Void is chosen the next step is Finish and the process is set to a Void status.
|
Time Only? Cloak |
---|
- The Time Only? conditional checks if Yes was selected for the Is this a Time Only request? field.
- If True (Yes) the next step is CC Director Execute TO.
- If False (No) the next step is prjConstr>10mil?
|
CC Director Execute TO - This automation step sends the Mail Merge file to the contact of the Purchase Order that is being modified.
- The next step is Attach Vendor Signed CO
|
Attach Vendor Signed CO Cloak |
---|
- The process is in this step because the vendor is not in e-Builder. It is the responsibility of the Project Manager to send the file in the Change Order Document field to the vendor.
- After you receive this signed document back from the vendor, remove the original document and attached this signed copy to the attach the Change Order Document field.
- Once the file is Downloaded and Removed reattach the signed file file.
- When submit is chosen the next step is A/E Review Required?
|
A/E Review Required? Cloak |
---|
- The A/E Review Required? conditional checks if Yes was selected for the A/E Review Required? field.
- If True (Yes) the next step is A/E Signature.
- If False (No) the next step is Program Manager Review.
|
A/E Signature Cloak |
---|
- The A/E Lead reviews the process details and the file in the Change Order Document field.
- If Submit is chosen the step actor will be prompted to electronically sign the document, the next step is Program Manager Review.
- If Revise is chosen the next step is PM Revise.
|
PM Review Contract Signature Cloak |
---|
- The Project Manager reviews the contract signature
| Cloak |
---|
- The CC Director reviews the process details and the file in the Change Order Document field.
- If ApprovedSubmit is chosen the next step is All Signatures Step.Contracts Group Review.
- If Initiator Revis If Revise to PM is chosen the next step is Initiator Revise
- If Submit is chosen the next step is A/E Signature.
- If Vndrs Mnually Signed is chosen the next step is Program Manager ReviewPM Review Mail Merge.
|
prjConstr > 10mil?Program Manager Review Cloak |
---|
- The Program Manager reviews the process details and the file in the Change Order Document field.
- If Submit is chosen the next step is Contracts Group Review.
- If Revise is chosen the next step is Initiator Revise
- The prjConstr>10mil? conditional checks if the value of the Revised Value field is greater than $ 10,000,000
- The Revised Value field is a sum of the Original Contract Value field, the Sum of Changes by Prior Change Orders field and the amount of the GCCO.
- If True (Yes) the next step is PM Enters Bridge Doc Info.
- If False (No) the next step is Campus Construction.
|
PM Enters Bridge Doc InfoContracts Group Review Cloak |
---|
- The Project Manager The Contract Admin reviews the process details and places a the file into the Bridge Documents file in the Change Order Document field.
- When If Submitis is chosen the next step is Program Manager Contracts Group Review DOCS.
- If Revise is chosen the next step is Initiator Revise.
| Initiator ReviseProgram Manager Review DOCS Cloak |
---|
- The Program Manager reviews the process details and the file in the Bridge Documents fieldInitiator Revise step allows the Process Initiator to make changes and resubmit the process.
- If SubmitResubmit is chosen the next step is Contract>$10m?PM Review
- If ReviseVoid is chosen the next step is PM ReviseFinish and the process is set to a Void status.
|
Campus ConstructionTime Only? Cloak |
---|
- The Time Only? conditional checks if Yes was selected for the Is this a Time Only request? field.
- If True
- The Campus Construction? Conditional checks if the Program Type of the project is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
- If True (Yes) the next step is SP&T Program?is CC Director Execute TO.
- If False If False (No) the next step is OCPis prjConstr>10mil?
|
SP&T ProgramContin or Reallo? Cloak |
---|
- The Contin or Reallo? conditional checks if Contingency or Reallocation was selected for the Change Order Type field of the COR process.
- If True
- The SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
- If True (Yes) the next step is SPT Director Reviewis CC Dir Reviews Conting or Realloc
- If False If False (No) the next step is Contract>$10mis prjConstr>10mil?
|
SP&T Director ReviewCC Dir Reviews Conting or Realloc Cloak |
---|
- The SPT CC Director reviews the process details and details and the appropriate file in the the Change Order Document field.
- If Submit If Send CSM is chosen the next step is EstFinCon>$10MIf Revise is is CSM Director Execute.
- If Send Utilities is chosen the next step is PM Revise
|
Contract>$10m?
- is Utilities Director Execute.
- If Send FEG is chosen the next step is FEG Director Review.
- If Send Finance is chosen the next step is Dir Finance Execute.
- If Send OCP is chosen the next step is OCP Director Execute.
- If Revise is chosen the next step is PM Revise.
- If Submit is chosen the next step is Compl CORs on Hold
| Cloak |
---|
- The Contract>$10m? conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is CC Director Review
- If False (No) the next step is CC Director Execute
|
CC Director ReviewExecute TO Cloak |
---|
- The CC Director reviews the the process details and and the appropriate file in the the Change Order Document field.
- If Submit is Approved is chosen the next step is Contract>$10m<$100m?All Signatures Step.
- If Revise is to PM is chosen the next step is PM Reviseis PM Review Mail Merge.
|
CC Director ExecuteprjConstr > 10mil? Cloak |
---|
- The prjConstr>10mil? conditional checks if the value of the Revised Value field is greater than $ 10,000,000
- The Revised Value field is a sum of the Original Contract Value field, the Sum of Changes by Prior Change Orders field and the amount of the GCCO.
- If True (Yes) the next step is PM Enters Bridge Doc Info.
- If False (No) the next step is Campus Construction
| Cloak |
---|
- The CC Director reviews the process details and the appropriate file in the Change Order Document field.
- If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
- If Send Dir F&A is chosen the next step is Contract > $1mil.
- If Send to OCP is chosen the next step is OCP Director Execute.
|
Contract>$10m<$100m? Cloak |
---|
- The Contract>$10m<$100m? conditional checks if >$10,000,000<=$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is VP Finance Execute
- If False (No) the next step is EVPT Execute
|
VP Finance Execute PM Enters Bridge Doc Info Cloak |
---|
- The Project Manager reviews the process details and places a file into the Bridge Documents file field.
- When Submit is chosen the next step is Program Manager Review DOCS.
|
Program Manager Review DOCS Cloak |
---|
- The Program Manager reviews the process details and the file in the Bridge Documents field.
- If Submit is chosen the next step is Contract>$10m?
| Cloak |
---|
- The VP for Finance reviews the process details and the appropriate file in the Change Order Document field.
- If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
|
OCPCampus Construction? Cloak |
---|
- The OCPCampus Construction? Conditional checks if the Program Type of the project is OCPAcademic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
- If True (Yes) the next step is Contract> $500kSP&T Program?
- If False (No) the next step is CSMOCP?
|
Contract> $500kSP&T Program? Cloak |
---|
- The SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
- If True (Yes) the next step is SPT Director Review
- If False (No) the next step is Contract>$10m?
|
SP&T Director Review Cloak |
---|
- The SPT Director reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is EstFinCon>$10M
- If Revise is chosen the next step is PM Revise
|
Contract>$10m?
Cloak |
---|
- The Contract>$10m? conditional checks if >$10Contract> $500k? Conditional checks if >$500,000<=$1,000,000, >$1,000,000<=$5,000,000, >$5,000,000<=$10$100,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is OCP Director Review.
- or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is CC Director Review
- If False (No) the next step is CC Director Execute
|
CC Director Review
Cloak |
---|
- The CC Director reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is Contract>$10m<$100m?
- If Revise is chosen the next step is PM Revise
|
CC Director Execute Cloak |
---|
- The CC Director reviews the process details and the appropriate file in the Change Order Document field.
- If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
- If Send Dir F&A is chosen the next step is Contract > $1mil.
- If Send to OCP is chosen If False (No) the next step is the next step is OCP Director Execute.
|
OCP Director ReviewContract>$10m<$100m? Cloak |
---|
- The OCP Director reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is Contract>$10m<$100m?
- If Revise is chosen the next step is PM Revise.
- Contract>$10m<$100m? conditional checks if >$10,000,000<=$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is VP Finance Execute
- If False (No) the next step is EVPT ExecuteIf Send CC Director is chosen the next step is Contract>$10m?
|
OCP Director VP Finance Execute Cloak |
---|
- The OCP Director VP for Finance reviews the process details and the appropriate file in the Change Order Document field.
- If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
|
CSMOCP? Cloak |
---|
- The CSMOCP? Conditional checks if the Program Type of the project is CSG or R&MOCP
- If True (Yes) the next step is Contract>$5MContract> $500k?
- If False (No) the next step is Utilities ProgramCSM?
|
Contract>$5MContract> $500k? Cloak |
---|
- The Contract>$5MContract> $500k?conditional Conditional checks if >$500,000<=$1,000,000, >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is CSM OCP Director Review.
- If False (No) the next step is CSM OCP Director Execute.
|
CSM OCP Director Review Cloak |
---|
- The CSM OCP Director reviews the process details and the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is Contract>$10MContract>$10m<$100m?
- If Revise is Revise is chosen the next step is PM Revise.
- If Send CC Director is chosen the next step is PM Revise.is Contract>$10m?
|
CSM OCP Director Execute Cloak |
---|
- The CSM OCP Director reviews the process details and the appropriate file in the Change Order Document field.
- If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
|
Utilities ProgramCSM? Cloak |
---|
- The Utilities ProgramCSM? Conditional checks if the Program Type of the project is CUP - OPS or UtilitiesCSG or R&M
- If True (Yes) the next step is Contract >$1MContract>$5M?
- If False (No) the next step is FEG Utilities Program?
|
Contract >$1MContract>$5M? Cloak |
---|
- The Contract >$1MContract>$5M? conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is Utilities Director Facilities Operations Review.
- If False (No) the next step is Utilities Director is Facilities Operations Execute.
|
Utilities Director Facilities Operations Review Cloak |
---|
- The Utilities Facilities Operations Director reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is Contract>$10M?
- If Revise is chosen the next step is PM Revise.
|
Utilities Director Facilities Operations Execute Cloak |
---|
- The Utilities Facilities Operations Director reviews the process details and the appropriate file in the Change Order Document field.
- If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
|
Utilities Program? Cloak |
---|
- The Utilities Program? Conditional checks if the Program Type of the project is CUP - OPS or Utilities
- If True (Yes) the next step is Contract >$1M?
- If False (No) the next step is FEG Program
|
Contract >$1M? Cloak |
---|
- The FEG Program? Conditional checks if the Program Type of the project is Energy or SEGContract >$1M? conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is FEG Utilities Director Review.
- If False (No) the next step is Contract > $1milis Utilities Director Execute.
|
Utilities Director Review Cloak |
---|
- The Utilities Director reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is Contract>$10M?
- If Revise is chosen the next step is PM Revise.
|
FEG Utilities Director ReviewExecute Cloak |
---|
- The SEG Utilities Director reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the Approved is chosen the step actor will be prompted to electronically sign the document, the next step is Contract>$10M?All Signatures Step.
- If Revise is chosen the next step is PM Revise.
|
Contract > $1milFEG Program? Cloak |
---|
- The FEG Program? Conditional checks if the Program Type of the project is Energy or SEG
| Cloak |
---|
- The Contract > $1mil? conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is Contract>$10M?FEG Director Review
- If False (No) the next step is Dir. Finance Executeis Contract > $1mil
|
Dir. Finance ExecuteFEG Director Review Cloak |
---|
- The Director of Finance and Administration SEG Director reviews the process details and the appropriate file in the Change Order Document field.
- If Approved is Submit is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.Contract>$10M?
- If Revise is chosen the next step is PM Revise.
|
Contract > $10M?$1mil Cloak |
---|
- The Contract > $10M? conditional checks if $1mil? conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is Dir of F&A Review.is Contract>$10M?
- If False (No) the next step is is Dir F&A Review. Finance Execute
|
Dir F&A Review. Finance Execute Cloak |
---|
- The Director of Finance and Administration reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is Approved is chosen the next step is VP, CSS Execute.If Revise is chosen step actor will be prompted to electronically sign the document, the next step is PM Revise.All Signatures Step.
- If Revise is If Send to CC Dir is chosen the next step is CC Director Executeis PM Revise.
|
Dir of F&A ReviewContract > $10M? Cloak |
---|
- The Director of Finance and Administration reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is VP, CSS Review.
- If Revise is chosen the next step is PM Revise.
- Contract > $10M? conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is Dir of F&A Review.
- If False (No) the next step is Dir F&A If Send CC Director is chosen the next step is CC Director Review.
|
VP, CSS Review Cloak |
---|
- The Deputy EVP reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the next step is EVPT Execute.
- If Revise is chosen the next step is PM Revise.
|
VP, CSS Execute Cloak |
---|
- The Deputy EVP reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
|
EVPT Execute Cloak |
---|
- The EVP&T Office reviews the process details and the appropriate file in the Change Order Document field.
- If Submit is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
- If Revise is chosen the next step is PM Revise.
|
PM Revise Cloak |
---|
- The PM Revise step allows the Project Manager to make changes and resubmit the process.
- If Resubmit to Vendor is chosen the next step is Time Only?
- If Resubmit to A/E is chosen the next step is A/E Signature.
- If Resubmit to Program Manager is chosen the next step is Program Manager Review.
|
All Signatures Step Cloak |
---|
- This is an e-Signature File Download Automation step that completes the DocuSign process.
- The next step is Compl CORs on Hold.
|
Compl CORs on Hold Cloak |
---|
- This is an Automation code step that runs custom code to complete the COR's.
- All CORs attached to the GCCO need to be in the COR Hold for GC-CO step.
- The next step is Success?
|
eB Admin Resubmit Cloak |
---|
- The eB Admin reads the comments, reviews the process fields and and takes the Resubmit action when all attached CORs are in the COR Hold for GC-CO step.
- The next step is Compl CORs on Hold.
|
Success? Cloak |
---|
- The Success? conditional checks if true was entered for the Passed Approval? field as a part of the Compl CORs on Hold code step.
- If True (Yes) the next step is AA/Contracts send to Vendor.
- If False (No) the next step is eB Admin Resubmit.
|
AA/Contracts send to Vendor Cloak |
---|
- The Administrative Assistant and Contract Admin should review the documents attached to the process, and send the executed documents to the vendor.
- The next step is Finish.
|
Finish |