This process can be started by the CC Planner, Contractor, OCP Planner, Project Manager, and SPT Lead.

The process routes the GCCO for approval and signature by the appropriate parties based on dollar amount and program.

Card
labelProcess Map
Image RemovedImage Added
  • The Proj Budget Change? conditional checks if an answer was given that was not None for the Project Budget Change Type? field.
  • Card
    labelStep Descriptions

    Toggle Cloak
    Spawn $0 Budget Change

    Cloak
    • The process $0 Budget Change is started and placed in the project manager's Court.
    • The Projet Manager must complete the $0 Budget Change process.
    • Following the Spawn $0 Budget Change step the process moves to the Fin. Analyst Hold for Completion step is started.

    Toggle Cloak
    Spawn Additional Funding

    Cloak
    • The 03.03 - Contingency Request/True-Up Form/Additional Funding Request process is started and placed in the project manager's Court.
    • The next step is Fin. Analyst Holds for Completion.

    Toggle Cloak
    Time Only? (Decisional Step)

    Cloak
    • The "Is this a Time Only request" field is evaluated to determine if this is a Time Only request.
    • If True (Yes) the next step is GC Change Order M.M
    • If False (No) the next step is Sum of Attached CORs.

    Toggle Cloak
    Fin. Analyst Holds for Completion

    Cloak
    • The Financial Analyst holds the process until budget changes or additonal funding is resolved.
    • When resolved the Financial Analyst takes the Submit action.
    • The next step is Time Only?

    Toggle Cloak
    GC Change Order M.M

    Cloak
    • This is a e-Builder Mail Merge step that produces the Change Order document from the Change Order template.
    • The next step is PM Review Mail Merge.

    Toggle Cloak
    Sum of Attached CORs

    Cloak
    • This is an e-Builder step in which custom code sums the attached PCOs.
    • The next step is Success?

    Toggle Cloak
    Success? (Decisional Step)

    Cloak
    • The Success field is evaluated to determine successful execution of Step 4.
    • If True (Yes) the next step is Commitment Value CO..
    • If False (No) the next step is Initiator Resubmit.

    Toggle Cloak
    Commitment Value CO

    Cloak

    This is a code step that processes the Change Orders.

    Toggle Cloak
    Success?

    Cloak
    • This is a code step that evaluates the success of the Commitment Value CO step.
    • If successful the next step is GC Change Order MM. (Mail Merge)
    • If unsuccessful the next step is Initiator Resubmit.

    Toggle Cloak
    GC Change Order M.M. (Mail Merge)

    Cloak
    • The GC Change Order mail merge generates the General Change Order document.
    • The next step is PM Review Mail Merge.

    Toggle Cloak
    Initiator Resubmit

    Cloak
    • The Process Initiator reads the comments and reviews the process fields, updates as necessary and takes the Resubmit action.
    • The next step is Sum of Attached PCOs.

    Toggle Cloak
    PM Review Mail Merge

    Cloak
    • The Project Manager reviews the process fields and the auto generated mail merge document and has the option to select either the Submit or Redo Mail Merge actions.
    • If Submit is chosen the next step is Vendor Signature.
    • If Redo Mail Merge is chosen the next step is Time Only?

    Toggle Cloak
    Vendor Signature

    Cloak
    • The Vendor reads the comments, reviews the process fields and takes the Approve action.
    • The next step is Vendor Signature.

    Toggle Cloak
    Vendor Signature St

    Cloak
    • The Vendor Signature St is an e-Signature file download/automated step to download final signed e-Signature files.
    • The next step is A/E Review Required?

    Toggle Cloak
    A/E Review Required? (Decisional)

    Cloak
    • If Yes (A/E Signature Required) the next step is A/E Signature.
    • If No (no A/E Signature Required) the next step is PM Review.

    Toggle Cloak
    A/E Signature

    Cloak
    • The A/E Signature step is an e-Signature file download/automated step to download final signed e-Signature files.
    • The next step is PM Review.

    Toggle Cloak
    PM Review

    Cloak
    • The PM reads the comments, reviews the process and takes the Approve action.
    • The next step is Program Manager Review.

    Toggle Cloak
    Program Manager Review

    Cloak
    • The Program Manager reads the comments, reviews the process fields and has the option to take the Approve or Modify CO actions.
    • If Approve is chosen the next step is Program Director Review.
    • If Modify CO is chosen the next step is Initiator Review.

    Toggle Cloak
    Program Director Review

    Cloak
    • A series of decisional steps determines which program director approves.
    • The appropriate Program Director reads the comments, reviews the process fields and takes the Approve action.
    • The next step is Campus Construction Review.

    Toggle Cloak
    <10m? (Decisional Step)

    Cloak
    • This is a decison step to determine signature authority and proper routing.
    • If <10 million the next step is CC Director Executes.
    • If >10 million the next step is CC Director Reviews.

    Toggle Cloak
    CC Director Executes

    Cloak
    • The Campus Construction Director reads the comments, reviews the process fields and has the option to take either the Submit or Revise action.
    • If Submit is chosen the next step is CC Director Signs.
    • If the Revise action is taken the next step is PM Revise.

    Toggle Cloak
    CC DIrector Signs

    Cloak
    • The CC DIrector Signs step is an e-Signature file download step the allows documents to be signed and attached to the process.
    • The next step is <100M?

    Toggle Cloak
    <$100 (Decisional Step)

    Cloak
    • The data field Change Amount is evaluated to determine if the change is less than 100 million dollars.
    • If True (Yes) the next step is Dputy EVPT Executes
    • If False (No) the next step is Deputy EVPT Review.

    Toggle Cloak
    Deputy EVPT Review

    Cloak
    • The Deputy EVPT reads the comments, reviews the process fields and has the option to take the Approve or Modify CO action.
    • If Approve is chosen the next step is EVPT Executes.
    • If Modify is chosen the next step is PM Revise.

    Toggle Cloak
    EVPT Executes

    Start

    Cloak
    • Started by the Project Manager, CC Planner, OCP Planner, SPT Lead, or Contractor who fills in the required fields and attaches the associated Change Order Requests that are to be combined into a single General Contract Change Order.
    • Be sure to add the Change Order Request properly. You must access the Filter Processes screen to select COR's to be processed. On screen instructions are provided in the process.
    • When finished the initiator takes the Submit action.
    • The next step is PM Review?

    Toggle Cloak
    PM Review

    Cloak
    • This step is in the process so that a GCCO submitted by a contractor is immediately reviewed by the project manager before being forwarded to others. (If the project manager started the process this may seem like a duplicate step.)
    • The Project Manager reviews the submission.
    • As part of this step project managers must update the Schedule module to reflect any changes including the substantial completion date.
    • The Project Manger takes the Submit action to advance the process.
    • If revisions are needed, the project manager has the option to take the Revise action to return this process to the initiator for changes.
    • If the action NTP Rev/Appv is chosen the process moves to the Contracts Reviews, Drafts, Ex. a New NTP step.
    • Following the Submit action the next step is Project Budget Change?.

    Toggle Cloak
    Contracts Reviews, Drafts,, Ex a New NTP

    Cloak
    • This step is contains all of the fields that the Start step contains plus 2 additional fields; New NTP and New Fully Executed NTP which contracts uses to engage with the PM and the vendor.
    • The Send to PM for Review Action is chosen then the contracts team has loaded a new NTP and is requesting that the project manager review, make edits or approve it.  
    • If the action Fully Exec NTP action is chosen the process moves to the Project Budget Change? step.
    • If the action Revise action is chosen the process moves to the Initiator Revise step.

    Toggle Cloak
    Proj Budget Change?

    Cloak
    • The Proj Budget Change? conditional checks if an answer was given that was not None for the Project Budget Change Type? field.
    • If True (YesBudget Change) the next step is $0 Budget Change?.
    • If False (NoNot a Budget Change) the next step is Commitment Value Co

    Toggle Cloak
    $0 Change?

    Cloak
    • The $0 Change? conditional checks if $0 Reallocation was selected for the Project Budget Change Type? field.
    • If True (Yes) the next step is Commitment Value Co
    • If False (No) the next step is Spawn PBAP.

    Toggle Cloak
    Conting or Reallo?

    Cloak
    • The Conting or Reallo? conditional checks if $0 Reallocation or Reallocation was selected for the Project Budget Change Type? field.
    • If True (Yes) the next step is Commitment Value Co
    • If False (No) the next step is Spawn PBAP.

    Toggle Cloak
    Custom GCCO Number?

    Cloak
    • The Custom GCCO Number? Conditional checks if the GC-CO No. field has a value.
    • If True (Yes) the next step is Success?
    • If False (No) the next step is Custom GCCO Number

    Toggle Cloak
    Custom GCCO Number

    Cloak
    • The Custom GCCO Number automation step generates a Mail Merge document with the GCCO number entered by the initiator.
    • The next step is PM Review Mail Merge.

    Toggle Cloak
    Spawn PBAP

    Cloak
    • The process 03.01.a - Budget Approval Process is started and placed in the Project Managers Court.
    • The Project Manager must complete the 03.01.a - Budget Approval Process.
    • Following the Spawn PBAP step the process moves to the CRSP Admin Mgr. Hold step.

    Toggle Cloak
    CRSP Admin Mgr. Hold

    Cloak
    • The Contract Admin Manager reviews the process details and holds the process in this step until funding is applied.
    • If Submit is chosen the next step is Sum of Attached CORs

    Toggle Cloak
    Sum of Attached CORs

    Cloak
    • This is an Automation code step in which custom code sums the attached CORs.
    • The next step is Success?

    Toggle Cloak
    Success?

    Cloak
    • The Success? conditional checks if true was entered for the Success? field as a part of the Sum of Attached CORs code step.
    • If True (Yes) the next step is PM?
    • If False (No) the next step is PM Review

    Toggle Cloak
    PM?

    Cloak
    • The PM? conditional checks if the process was submitted by someone with the Primary Role of Project Manager.
    • If True (Yes) the next step is Proj Budget Change?
    • If False (No) the next step is PM Review

    Toggle Cloak
    Attach CORS

    Cloak
    • The Project Manager is responsible attaching the missing CORs to the CORs tab of the process.
    • If Submit is chosen the next step is Sum of Attached CORs
    • If Redo Sum is chosen the next step is Initiator Revise.
    • If Void is chosen the next step is Finish and the process is set to a Void status.

    Toggle Cloak
    Commitment Value Co

    Cloak
    • This is an Automation code step that processes the Change Orders.
    • The next step is Success?

    Toggle Cloak
    Success?

    Cloak
    • The Success? conditional checks if true was entered for the Passed Approval? field as a part of the Commitment Value Co code step.
    • If True (Yes) the next step is GC Change Order M.M.
    • If False (No) the next step is Initiator Revise.

    Toggle Cloak
    GC Change Order M.M.

    Cloak
    • This is an Automation code step that generates the General Contract Change Order document.
    • The next step is PM Review Mail Merge.

    Toggle Cloak
    PM Review Mail Merge

    Cloak
    • The Project Manager reviews the process details and the file in the Change Order Document field.
    • If DocuSign Submit is chosen the next step is Vendor Signature.
    • If Revise is chosen the next step is Initiator Revise.
    • If Take Offline is chosen the next step is Attach Vendor Signed CO.

    Toggle Cloak
    Vendor Signature

    Cloak
    • The Contractor reviews the process details and the file in the Change Order Document field.
    • If DocuSign Submit is chosen the next step is Vendor Signature.
    • If Approve is chosen the step actor will be prompted to electronically sign the document, the next step is A/E Review Required?
    Cloak
    • The EVPT reads the comments, reviews the process fields and has the option to take the Submit or Revise action.
    • If Submit is chosen the next step is CO Signature Finalized.
    • If Revise is chosen the next step is PM Initiator Revise.

    Toggle Cloak
    CO Signature FinalizeSend a MM to a Vend

    Cloak
    • The CO Signature Final step is an e-Signature file download step that allows documents to be signed and attached to the processThis automation step sends the Mail Merge file to the contact of the Purchase Order that is being modified.
    • The next step is Comp CORs on Hold.

     

    ----------------------------------------------------------------------------------

    Toggle Cloak
    Start

    Cloak
    • Started by the Project Manager, CC Planner, OCP Planner, SPT Lead, or Contractor who fills in the required fields and attaches the associated Change Order Requests that are to be combined into a single General Contract Change Order.
    • Be sure to add the Change Order Request properly. You must access the Filter Processes screen to select COR's to be processed. On screen instructions are provided in the process.
    • When finished the initiator takes the Submit action.
    • The next step is PM Review?

    Toggle Cloak
    PM Review

    Cloak
    • This step is in the process so that a GCCO submitted by a contractor is immediately reviewed by the project manager before being forwarded to others. (If the project manager started the process this may seem like a duplicate step.)
    • The Project Manager reviews the submission.
    • As part of this step project managers must update the Schedule module to reflect any changes including the substantial completion date.
    • The Project Manger takes the Submit action to advance the process.
    • If revisions are needed, the project manager has the option to take the Revise action to return this process to the initiator for changes.
    • Following the Submit action the next step is Project Budget Change?.

    Toggle Cloak
    Proj Budget Change?

    Cloak
    • is Attach Vendor Signed CO

    Toggle Cloak
    Attach Vendor Signed CO

    Cloak
    • The process is in this step because the vendor is not in e-Builder. It is the responsibility of the
    If True (YesBudget Change) the next step is $0 Budget Change?.If False (NoNot a Budget Change) the next step is Sum of Attached CORs.

    Toggle Cloak
    $0 Change?

    Cloak
    • The $0 Change? conditional checks if $0 Reallocation was selected for the Project Budget Change Type? field.
    • If True (Yes) the next step is Spawn $0 Budget Change
    • If False (No) the next step is Spawn PBAP.

    Toggle Cloak
    Spawn $0 Budget Change

    Cloak
    • The process $0 Budget Change is started and placed in the project manager's Court.
    • The Projet Manager must complete the $0 Budget Change process.
    • Following the Spawn $0 Budget Change step the process moves to the Fin. Analyst Hold for Completion step is started.

    Toggle Cloak
    Spawn PBAP

    Cloak
    • The process $0 Budget Change is started and placed in the project manager's Court.
    • The Projet Manager must complete the $0 Budget Change process.
    • Following the Spawn $0 Budget Change step the process moves to the Fin. Analyst Hold for Completion step is started.

    Toggle Cloak
    CRSP Admin Mgr. Hold

    Cloak
    • The Contract Admin Manager reviews the process details and holds the process in this step until funding is applied.
    • If Submit is chosen the next step is Sum of Attached CORs

    Toggle Cloak
    Sum of Attached CORs

    Cloak
    • This is an Automation code step in which custom code sums the attached CORs.
    • The next step is Success?

    Toggle Cloak
    Success?

    Cloak
    • The Success? conditional checks if true was entered for the Success? field as a part of the Sum of Attached CORs code step.
    • If True (Yes) the next step is Commitment Value Co
    • If False (No) the next step is Attach CORS.

    Toggle Cloak
    Attach CORS

    Cloak
    • The Project Manager is responsible attaching the missing CORs to the CORs tab of the process.
    • If Submit is chosen the next step is Sum of Attached CORs
    • If Void is chosen the next step is Finish and the process is set to a Void status.

    Toggle Cloak
    Commitment Value Co

    Cloak
    • This is an Automation code step that processes the Change Orders.
    • The next step is Success?

    Toggle Cloak
    Success?

    Cloak
    • The Success? conditional checks if true was entered for the Passed Approval? field as a part of the Commitment Value Co code step.
    • If True (Yes) the next step is GC Change Order M.M.
    • If False (No) the next step is Initiator Revise.

    Toggle Cloak
    GC Change Order M.M.

    Cloak
    • This is an Automation code step that generates the General Contract Change Order document.
    • The next step is PM Review Mail Merge.

    Toggle Cloak
    PM Review Mail Merge

    Cloak
    • The Project Manager reviews the process details and the file in the Change Order Document field.
    • If DocuSign Submit is chosen the next step is Vendor Signature.
    • If Revise is chosen the next step is Initiator Revise.
    • If Take Offline is chosen the next step is Attach Vendor Signed CO.

    Toggle Cloak
    Vendor Signature

    Cloak
    • The Contractor reviews the process details and the file in the Change Order Document field.
    • If DocuSign Submit is chosen the next step is Vendor Signature.
    • If Approve is chosen the step actor will be prompted to electronically sign the document, the next step is A/E Review Required?
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Attach Vendor Signed CO

    Cloak
    • The process is in this step because the vendor is not in e-Builder. It is the responsibility of the Project Manager to send the file in the Change Order Document field to the vendor.
    • After you receive this signed document back from the vendor, remove the original document and attached this signed copy to the attach the Change Order Document field.
    • Once the file is Downloaded and Removed reattach the signed file file.
    • When submit is chosen the next step is A/E Review Required?

    Toggle Cloak
    A/E Review Required?

    Cloak
    • The A/E Review Required? conditional checks if Yes was selected for the A/E Review Required? field.
    • If True (Yes) the next step is A/E Signature.
    • If False (No) (No) the next step is Program Manager Review.

    Toggle Cloak
    A/E Signature

    Cloak
    • The A/E Lead reviews the process details and the file in the Change Order Document field.
    • If Submit is chosen the step actor will be prompted to electronically sign the document, the next step is is Program Manager Review.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    A/E PM Review Contract Signature

    Cloak
    • The A/E Lead The Project Manager reviews the process details contract signature and the file in the Change Order Document field.
    • If Submit is chosen the next step is Contracts Group Review.
    • If Initiator Revis is chosen the step actor will be prompted to electronically sign the document, the next step is next step is Initiator Revise
    • If Submit is chosen the next step is A/E Signature.
    • If Vndrs Mnually SignedProgram Manager Review.If Revise is chosen the next step is PM ReviseProgram Manager Review.

    Toggle Cloak
    Program Manager Review

    Cloak
    • The Program Manager reviews the process details and the file in the Change Order Document field.
    • If Submit is chosen the next step is Contracts Group Review.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Contracts Group Review

    Cloak
    • The Contract Admin reviews the process details and the file in the Change Order Document field.
    • If Submit is chosen the next step is Contracts Group Review.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Initiator Revise

    Cloak
    • The Initiator Revise step allows the Process Initiator to make changes and resubmit the process.
    • If Resubmit is chosen the next step is PM Review
    • If Void is chosen the next step is Finish and the process is set to a Void status.

    Toggle Cloak
    Time Only?

    Cloak
    • The Time Only? conditional checks if Yes was selected for the Is this a Time Only request? field.
    • If True (Yes) the next step is CC Director Execute TO.
    • If False (No) the next step is prjConstr>10mil?

    Toggle Cloak
    CC Director Execute TO

    Cloak
    • The CC Director reviews the process details and the file in the Change Order Document field.
    • If Approved is chosen If True (Yes) the next step is All Signatures Step.If Revise to PM is chosen is CC Director Execute TO.
    • If False (No) the next step is PM Review Mail Merge. prjConstr>10mil?

    Toggle Cloak
    prjConstr > 10milContin or Reallo?

    Cloak
    • The prjConstr>10mil? conditional checks if the value of the Revised Value field is greater than $ 10,000,000The Revised Value field is a sum of the Original Contract Value field, the Sum of Changes by Prior Change Orders field and the amount of the GCCO Contin or Reallo? conditional checks if Contingency or Reallocation was selected for the Change Order Type field of the COR process.
    • If True (Yes) the next step is PM Enters Bridge Doc Info. CC Dir Reviews Conting or Realloc
    • If False (No) the next step is Campus Construction. prjConstr>10mil?

    Toggle Cloak
    PM Enters Bridge Doc InfoCC Dir Reviews Conting or Realloc

    Cloak
    • The Project Manager The CC Director reviews the process details and places a the file into the Bridge Documents file in the Change Order Document field.
    • When Submit If Send CSM is chosen the next step is Program Manager Review DOCS.

    Toggle Cloak
    Program Manager Review DOCS

    Cloak
    • The Program Manager reviews the process details and the file in the Bridge Documents field.
    • If Submit is chosen the next step is Contract>$10m?
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    Campus Construction?

    Cloak
    • The Campus Construction? Conditional checks if the Program Type of the project is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
    • If True (Yes) the next step is SP&T Program?
    • If False (No) the next step is OCP?

    Toggle Cloak
    SP&T Program?

    Cloak
    • The SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
    • If True (Yes) the next step is SPT Director Review
    • If False (No) the next step is Contract>$10m?

    Toggle Cloak
    SP&T Director Review

    • is CSM Director Execute.
    • If Send Utilities is chosen the next step is Utilities Director Execute.
    • If Send FEG is chosen the next step is FEG Director Review.
    • If Send Finance is chosen the next step is Dir Finance Execute.
    • If Send OCP is chosen the next step is OCP Director Execute.
    • If Revise is chosen the next step is PM Revise.
    • If Submit is chosen the next step is Compl CORs on Hold

    Toggle Cloak
    CC Director Execute TO

    Cloak
    • The CC Director reviews the process details and the file in the Change Order Document field.
    • If Approved is chosen the next step is All Signatures Step.
    • If Revise to PM is chosen the next step is PM Review Mail Merge.

    Toggle Cloak
    prjConstr > 10mil?

    Cloak
    • The prjConstr>10mil? conditional checks if the value of the Revised Value field is greater than $ 10,000,000
    • The Revised Value field is a sum of the Original Contract Value field, the Sum of Changes by Prior Change Orders field and the amount of the GCCO.
    • If True (Yes) the next step is PM Enters Bridge Doc Info.
    • If False (No) the next step is Campus Construction.

    Toggle Cloak
    PM Enters Bridge Doc Info

    Cloak
    • The Project Manager reviews the process details and places a file into the Bridge Documents file field.
    • When Submit is chosen the next step is Program Manager Review DOCS.

    Toggle Cloak
    Program Manager Review DOCS

    Cloak
    • The Program Manager reviews the process details and the file in the Bridge Documents field.
    • If Submit is chosen the next step is Contract>$10m?
    Cloak
    • The SPT Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the next step is EstFinCon>$10M
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    Contract>$10mCampus Construction?

    Cloak
    • The Contract>$10mCampus Constructionconditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.Conditional checks if the Program Type of the project is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
    • If True (Yes) the next step is CC Director ReviewSP&T Program?
    • If False (No) the next step is CC Director ExecuteOCP?

    Toggle Cloak
    CC Director ReviewSP&T Program?

    Cloak
    • The CC Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the next step is Contract>$10m<$100m?
    • SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
    • If True (Yes) the next step is SPT Director Review
    • If False (No) the next step is Contract>$10m?If Revise is chosen the next step is PM Revise

    Toggle Cloak
    CC SP&T Director ExecuteReview

    Cloak
    • The CC SPT Director reviews the the process details and details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the Submit is chosen the next step is All Signatures Step.EstFinCon>$10M
    • If Revise is chosen the next step is PM Revise.
    • If Send Dir F&A is chosen the next step is Contract > $1mil.
    • If Send to OCP is chosen the next step is OCP Director Execute.

    Toggle Cloak
    Contract>$10m<$100mContract>$10m?

    Cloak
    • The Contract>$10m<$100mContract>$10m? conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000was  was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is VP Finance ExecuteCC Director Review
    • If False (No) the next step is EVPT Execute) the next step is CC Director Execute

    Toggle Cloak
    CC Director Review

    Cloak
    • The CC Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the next step is Contract>$10m<$100m?
    • If Revise is chosen the next step is PM Revise

    Toggle Cloak
    VP Finance CC Director Execute

    Cloak
    • The VP for Finance reviews the process details and CC Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    OCP?

    • If Send Dir F&A is chosen the next step is Contract > $1mil.
    • If Send to OCP is chosen the next step is OCP Director Execute.
    Cloak
    • The OCP? Conditional checks if the Program Type of the project is OCP
    • If True (Yes) the next step is Contract> $500k?
    • If False (No) the next step is CSM?

    Toggle Cloak
    Contract> $500kContract>$10m<$100m?

    Cloak
    • The Contract> $500kContract>$10m<$100m? Conditional checks if >$500,000<=$1,000,000, >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000,  conditional checks if >$10,000,000<=$100,000,000, or >$100=$100,000,000  was was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is VP Finance Execute
    • If False (No) the next step is EVPT Execute

    Toggle Cloak
    VP Finance Execute

    Cloak
    • The VP for Finance reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is OCP Director ReviewAll Signatures Step.
    • If False (No) Revise is chosen the next step is OCP Director ExecutePM Revise.

    Toggle Cloak
    OCP Director Review?

    Cloak
    • The OCP Director? reviews the process details and the appropriate file in the Change Order Document field.Conditional checks if the Program Type of the project is OCP
    • If True (Yes) If Submit is chosen the next step is Contract>$10m<$100mContract> $500k?
    • If Revise is chosen the next step is PM Revise.If Send CC Director is chosen False (No) the next step is Contract>$10mis CSM?

    Toggle Cloak
    OCP Director ExecuteContract> $500k?

    Cloak
    • The Contract> $500k? Conditional checks if >$500,000<=$1,000,000, >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is OCP Director Review.
    • If False (No) the next step is OCP Director Execute
    Cloak
    • The OCP Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    CSM?OCP Director Review

    Cloak
    • The CSM? Conditional checks if the Program Type of the project is CSG or R&MOCP Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen If True (Yes) the next step is Contract>$5MContract>$10m<$100m?
    • If False (No) Revise is chosen the next step is PM Revise.
    • If Send CC Director is chosen the next step is Contract>$10mUtilities Program?

    Toggle Cloak
    Contract>$5M?OCP Director Execute

    Cloak
    • The Contract>$5M? conditional checks if >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is CSM Director Review.
    • OCP Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • If Revise is chosen the next step is PM ReviseIf False (No) the next step is CSM Director Execute.

    Toggle Cloak
    CSM Director Review?

    Cloak
    • The CSM Director reviews the process details and the appropriate file in the Change Order Document field.Conditional checks if the Program Type of the project is CSG or R&M
    • If True (Yes) If Submit is chosen the next step is Contract>$10MContract>$5M?
    • If Revise is chosen False (No) the next step is PM Revise.Utilities Program?

    Toggle Cloak
    CSM Director ExecuteContract>$5M?

    Cloak
    • The CSM Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • Contract>$5M? conditional checks if >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is Facilities Operations Review.
    • If False (No) the next step is Facilities Operations ExecuteIf Revise is chosen the next step is PM Revise.

    Toggle Cloak
    Utilities Program?Facilities Operations Review

    Cloak
    • The Utilities Program? Conditional checks if the Program Type of the project is CUP - OPS Facilities Operations Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen or UtilitiesIf True (Yes) the next step is Contract >$1MContract>$10M?
    • If False (No) the next step is FEG Program

    Toggle Cloak
    Contract >$1M?

    • Revise is chosen the next step is PM Revise.

    Toggle Cloak
    Facilities Operations Execute

    Cloak
    • The Facilities Operations Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • If Revise is chosen the next step is PM Revise
    Cloak
    • The Contract >$1M? conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is Utilities Director Review.
    • If False (No) the next step is Utilities Director Execute.

    Toggle Cloak
    Utilities Director ReviewProgram?

    Cloak
    • The Utilities Director reviews the process details and the appropriate file in the Change Order Document field.Program? Conditional checks if the Program Type of the project is CUP - OPS or Utilities
    • If True (Yes) If Submit is chosen the next step is Contract>$10MContract >$1M?
    • If Revise is chosen False (No) the next step is PM Revise.FEG Program

    Toggle Cloak
    Utilities Director ExecuteContract >$1M?

    Cloak
    • The Contract >$1M? conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is Utilities Director Review.
    • If False (No) the next step is Utilities Director Execute
    Cloak
    • The Utilities Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    FEG Program?Utilities Director Review

    Cloak
    • The FEG Program? Conditional checks if the Program Type of the project is Energy orUtilities Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen  SEGIf True (Yes) the next step is FEG Director ReviewContract>$10M?
    • If False (No) Revise is chosen the next step is Contract > $1milPM Revise.

    Toggle Cloak
    FEG Utilities Director ReviewExecute

    Cloak
    • The SEG Utilities Director  reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen Approved is chosen the step actor will be prompted to electronically sign the document, the next step is Contract>$10M?All Signatures Step.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    Contract > $1milFEG Program?

    Cloak
    • The Contract > $1mil? conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.FEG Program? Conditional checks if the Program Type of the project is Energy or SEG
    • If True (Yes) the next step is Contract>$10M?FEG Director Review
    • If False (No) the next step is Dir. Finance Executeis Contract > $1mil

    Toggle Cloak
    Dir. Finance ExecuteFEG Director Review

    Cloak
    • The Director of Finance and Administration SEG Director reviews the process details and the appropriate file in the Change Order Document field.
    • If Approved is chosen the step actor will be prompted to electronically sign the document, the Submit is chosen the next step is All Signatures Step.Contract>$10M?
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    Contract > $10M?$1mil

    Cloak
    • The Contract > $10M$1mil?  conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is Dir of F&A Review.is Contract>$10M?
    • If False (No) the next step is is Dir F&A Review. Finance Execute

    Toggle Cloak
    Dir F&A Review. Finance Execute

    Cloak
    • The Director of Finance and Administration  reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the Approved is chosen the step actor will be prompted to electronically sign the document, the next step is VP, CSS ExecuteAll Signatures Step.
    • If Revise is chosen the next step is PM Revise.If Send to CC Dir is chosen the next step is CC Director Execute.

    Toggle Cloak
    Dir of F&A ReviewContract > $10M?

    Cloak
    • The Director of Finance and Administration reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the next step is VP, CSS Review.
    • If Revise is chosen the next step is PM Revise.
    • Contract > $10M? conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
    • If True (Yes) the next step is Dir of F&A Review.
    • If False (No) the next step is Dir F&A If Send CC Director is chosen the next step is CC Director Review.

    Toggle Cloak
    VP, CSS Review

    Cloak
    • The Deputy EVP reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the next step is EVPT Execute.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    VP, CSS Execute

    Cloak
    • The Deputy EVP reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    EVPT Execute

    Cloak
    • The EVP&T Office reviews the process details and the appropriate file in the Change Order Document field.
    • If Submit is chosen the step actor will be prompted to electronically sign the document, the next step is All Signatures Step.
    • If Revise is chosen the next step is PM Revise.

    Toggle Cloak
    PM Revise

    Cloak
    • The PM Revise step allows the Project Manager to make changes and resubmit the process.
    • If Resubmit to Vendor is chosen the next step is Time Only?
    • If Resubmit to A/E is chosen the next step is A/E Signature.
    • If Resubmit to Program Manager is chosen the next step is Program Manager Review.

    Toggle Cloak
    All Signatures Step

    Cloak
    • This is an e-Signature File Download Automation step that completes the DocuSign process.
    • The next step is Compl CORs on Hold.

    Toggle Cloak
    Compl CORs on Hold

    Cloak
    • This is an Automation code step that runs custom code to complete the COR's.
    • All CORs attached to the GCCO need to be in the COR Hold for GC-CO step.
    • The next step is Success?

    Toggle Cloak
    eB Admin Resubmit

    Cloak
    • The eB Admin reads the comments, reviews the process fields and and takes the Resubmit action when all attached CORs are in the COR Hold for GC-CO step.
    • The next step is Compl CORs on Hold.

    Toggle Cloak
    Success?

    Cloak
    • The Success? conditional checks if true was entered for the Passed Approval? field as a part of the Compl CORs on Hold code step.
    • If True (Yes) the next step is AA/Contracts send to Vendor.
    • If False (No) the next step is eB Admin Resubmit.

    Toggle Cloak
    AA/Contracts send to Vendor

    Cloak
    • The Administrative Assistant and Contract Admin should review the documents attached to the process, and send the executed documents to the vendor.
    • The next step is Finish.

    Toggle Cloak
    Finish

    Cloak

     

    Card
    labelChange Log
    DateChangeeB Admin
    4/3/2018Process updated to enable signaure step for CC Director when value of GCCO is <10 milion. (Workflow v4.1)RB/SA
    4/3/2018WIKI documention (Step Descriptions and Process map updated)RB
    12/11/2020Wiki updated to 06.02.3 - General Contract Change Order workflow.JM
       

    ...

    10/31/2022Wiki updated to current workflow.JM