Malware Protection Overhaul Aug28.mpp
Malware Protection Overhaul May09.mpp
Malware Protection Overhaul May09.pdf
Malware Protection Overhaul Feb04.mpp
Malware Protection Overhaul Feb04.pdf
Malware Protection Overhaul Jan02.mpp
Malware Protection Overhaul Jan02.pdf
Milestones | Status | ||||
---|---|---|---|---|---|
Project Planning | √ | ||||
Project Kickoff | √ | ||||
Community Communications | ongoing | ||||
Windows Selection |
| ||||
IS Forefront Evaluation | ongoing | ||||
IS ESET Evaluation | ongoing | ||||
√ | |||||
Sophos ISST Evaluation | √ | ||||
System Center ISST Evaluation | √ | ||||
ESET ISST Evaluation | √ | ||||
Vendor Demo | √ | ||||
Analyze Recommendation and Solution | √ |
|
| ||
Sponsor Approval | √ |
| |||
Pilot Rollout |
| ||||
Procurement |
| ||||
Early Adopters |
| ||||
Final Review and Approval |
| ||||
Full Rollout |
| ||||
MAC Selection |
| ||||
IS Sophos Evaluation | √ | ||||
IS ESET Evaluation | ongoing | ||||
Vendor Demo |
| ||||
Analyze Recommendation and Solution |
| ||||
Sponsor Approval |
| ||||
Pilot Rollout |
| ||||
Procurement |
| ||||
Early Adopters |
| ||||
| |||||
IS&T planning and communications | √ |
|
|
| |
Full Integration Testing | √ |
|
| ||
Sponsor Checkpoint | √ |
|
| ||
Purchasing and Contracts | √ |
|
| ||
Final Communications | √ |
| Final Review and Approval |
| |
Full Rollout | √ |
|
| ||
Project Wrap up UP | √ |
|
|