Deck of Cards
idBid
Card
labelSummary

The Bidding process and the Bidding module are both used to complete a bid and issue an award.

Card
labelProcess Map

Card
labelStep Descriptions

To make the Step descriptions for Bidding easier to read they have been separated into the three parts (tabs). 

Deck of Cards
idSDBid
historyfalse
Card
labelBid List Approval

Toggle Cloak
Start Process

Cloak
  • The Bidding process is usually initiated by the Project Manager.
  • Depending on the project the initiator completes the required sections of the page.
    • Contract Management
    • Pre-Priced Agreement for Office/CR/Lab
    • Sole Source
    • Potential Bidders - When adding potential bidders you should add contact information for each bidder prior to submitting for Vendor Manager review. If that information is not provided the process will be returned to your court for the Initiator Revise step
  • When finished, take the Submit action.
  • The next step is Furniture or AV Bid?

Toggle Cloak
Furniture?

Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Bid Doc Preparation
  • If False (No) the next step is AV?

Toggle Cloak
AV?

Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Vendor Mgr Reviews A/V Bid
  • If False (No) the next step is Sole Source?

Toggle Cloak
Vendor Mgr Reviews A/V Bid

  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Bid Doc Preparation
  • If False (No) the next step is
    Cloak
    • In this step the Vendor Manager reviews the Bid information. The process reaches this step for A/V Bids.
    • If the Submit action is taken the next step is Program Manager Reviews.
    • If the Revise action is taken he next step is Initiator Review.

    Toggle Cloak
    Vendor Mgr Reviews Prop Bid List

    .

     

     

    Cloak
    • The Vendor Manager reviews the proposed bid list.
    • If approved the Vendor Manager takes the Submit action. The next step is Prepriced Agmt?
    • If the Revise action is taken he next step is Initiator Review.

    Toggle Cloak
    Furniture or AV Bid? (Conditional)Prepriced Agmt?

    Cloak
    • The system evaluates this conditional to determine if this is a Pre-priced agreement. Using a pre-priced agreement bypasses the process steps which generate an Approved Bid List.
    • If the use of a pre-priced agreement is approved, the work is awarded to a vendor who has previously bid for for work of a certain scope/complexity in order to be considered for that work in the future.
    • If Pre-priced Agreement is True (Yes) the next step is CA Approved Contract Type.
    • If it is
    • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
    • If True (Yes) the next step is Bid Doc Preparation
    • If False (No) the next step is Vendor Mgr Reviews Prop Bid ListProgram Manager Review.

    Toggle Cloak
    Vendor Mgr Reviews Prop Bid ListSole Source?

    Cloak
    Cloak
    The
    • The Vendor Manager reviews the proposed bid list.
    • If approved the Vendor Manager takes the Submit action.
    • If requesting revisions the Vendor Manager takes the Revise action.

    Toggle Cloak
    Pre-priced Agreement

    • system evaluates this conditional to determine if this is a
    Pre-priced
    • Sole Sourced agreement. Using a
    pre-priced
    • Sole Sourced agreement bypasses the process steps which generate an Approved Bid List.
    • If the use of a
    pre-priced
    • Sole Source agreement is approved,
    the work is awarded to a vendor who has previously bid for for work of a certain scope/complexity in order to be considered for that work in the future.
    • an explanation must be provided.
    • If this conditional evaluates toIf Pre-priced Agreement is True (Yes) the next step is CA Approved Contract Type Vendor Reccomendation.
    • If it is this conditional evaluates to False (No) the next step is Program Manager Review Vendor Mgr Reviews Prop Bid List.

    Toggle Cloak
    Initiator Revise

    Cloak
    • Initiator Revise is used to request that the initiator correct an error or add more information to a prior step.
    • The Initiator reviews the process and the comments made by the reviewer and makes adjustments as required. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
    • If To Vendor Manager is chosen the next step is Vendor Mgr Reviews Prop Bid List.
    • If To Program Manager is chosen the next step is Program Manager Review.
    • If Void is chosen the next step is Finish.

    Toggle Cloak
    Program Manager ReviewReviews

    Cloak
    • The Program Manager reads the comments and reviews the process fields and has the option to take an Action to Submit or Revise.
    • If Submit is chosen the next step is Campus Construction?
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Campus Construction? (Conditional)

    Cloak
    • e-Builder uses information previously entered about the project to determine if this is a Campus Construction project.
    • If Yes the next step is SP&T Program?
    • If No the next step is OCP?

    Toggle Cloak
    SP&T Program? (Conditional)

    Cloak
    • e-Builder uses information previously entered about the project to determine if this is an SP&T Program.
    • If True (Yes) the next step is SPT Director Review.
    • If False (No) the next step is CC Director Review.

    Toggle Cloak
    SPT Director Review

    Cloak
    • The SPT Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
    • If Submit is chosen the next step is CC Director Review.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    CC Director Review

    Cloak
    • The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
    • If Submit is chosen the next step is Approved Bid List
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    OCP? (Conditional)

    Cloak
    • e-Builder evaluates information previously entered about the project to determine if this is an OCP Program.
    • If True (Yes) the next step is OCP Director Review.
    • If False (No) the next step is M&U?

    Toggle Cloak
    OCP Director Review

    Cloak
    • The OCP Director reads the comments and reviews the process fields. The OCP Director has the option to take an Action to Submit or Revise.
    • If Submit is chosen the next step is Approved Bid List
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    M&U? (Conditional)

    Cloak
    • e-Builder evaluates information previously entered about the project to determine if this is an M&U program?
    • If Yes the next step is Utilities Program?
    • If No the next step is Campus Services?

    Toggle Cloak
    Utilities Program? (Conditional)

    Cloak
    • e-Builder evaluates information previously entered about the project to determine if this is a Utilities Program.
    • If True (Yes) the next step is Utilities Director Review.
    • If False (No) the next step is SEG Program?

    Toggle Cloak
    Utilities Director Review

    Cloak
    • The Utilities Director reads the comments and reviews the process fields. The Utilities Director has the option to take an Action to Submit or Revise.
    • If Submit is chosen the next step is M&U Director Review.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    SEG Program? (Conditional)

    Cloak
    • e-Builder evaluates information previously entered about the project  to determine if this is an SEG Program.
    • If True (Yes) the next step is SEG Director Review.
    • If False (No) the next step is O&M Director Review?

    Toggle Cloak
    SEG Director Review

    Cloak
    • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
    • If Submit is chosen the next step is M&U Director Review.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    O&M Director Review

    Cloak
    • The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
    • If Submit is chosen the next step is M&U Director Review.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    M&U Director Review

    Cloak
    • The M&U Director reads the comments and reviews the process fields. The M&U Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Approved Bid List
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Campus Services? (Conditional)

    Cloak
    • e-Builder evaluates information previously entered about the project to determine if this is an Campus Services Program.
    • If True (Yes) the next step is CS Director Review.
    • If False (No) the next step is IBO Director Review

    Toggle Cloak
    CS Director Review

    Cloak
    • The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Approved Bid List
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    IBO Director Review

    Cloak
    • The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Approved Bid List.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Initiator Revise

    Cloak
    • The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
    • The If the Submit action is taken the next step is Sole Source?
    • If Void is chosen the next step is Finish.

    Toggle Cloak
    Approved Bid List (Automation)

    Cloak
    • This step generates the Approved Bid List document from a template
    • The bid list document is placed into the Documents\05 Procurement\0505 Bid Lists (I) folder
    • The next step is Initiator Prepares Bid DocumentsCA Apprv Contract Type.
    • The Contract Admin assembles the bid package and when finished takes the Submit action.
    • As part of this process the Contract Admin adds a contract sample and assigns a contract number.
    • The next step is Hold for Bids/Proposals Received.

    Card
    labelDocuments, Contract Approval, Release Bid

    Toggle Cloak
    CA Apprv Contract Type

    Cloak
    • The Contract Admin either approves or changes the contract type or approves the Pre-priced agreement and adds the contract number for that agreement to the process.
    • The Contract Admin takes the Approved action to approve. The next step is Approved Pre-Price.
    • The Contract Admin takes the Changed action when changing the contract type, and adds comments to indicate to the PM that the contract has been changed and the reasons for the change.
    • The next step is Bid Doc Preparation.

    Toggle Cloak
    Approved Pre-Price Agreement

    Cloak
    • This is a conditional step. If True (a Pre-priced agreement) the next step is the Merge/Code step that creates the Selection of Source form document.
    • If False the next step is Bid Document Preparation.

    Toggle Cloak
    Pre-Priced SOS Code/Merge CreationPrePriced SoS

    Cloak
    • e-Builder generates the Selection of Source for Pre-priced agreements.
    • The next step is Vendor Manager Review of SoS.

    Toggle Cloak
    Bid Document Preparation

    Cloak
    • The process initiator, usually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit action is taken when finished.
    • The next step is Contract Admin Assembles Bid Package

    Toggle Cloak
    Contract Admin Assembles Bid Package

    Cloak
    Toggle Cloak
    Hold for Bids/Proposals Received

    Cloak

    The bid should be released in the Bid module when the process reaches this step.

    • Hold the process in this step from bid release until all bids are received and the bid tab has been opened and analyzed. This may be held for one to several weeks while the bid is open.
    • Once the bids have been analyzed and a vendor recommendation is ready the Project Manager takes the Submit actionusually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit action is taken when finished.
    • The next step is Vendor Recommendation. Contract Admin Assembles Bid Package

    Toggle Cloak
    Program Manager Reviews Contract Admin Assembles Bid Package

    Cloak
    • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
    • If Submit is chosen the next step is Initiator Releases Bid.
    • Contract Admin assembles the bid package and when finished takes the Submit action.
    • As part of this process the Contract Admin adds a contract sample and assigns a contract number.

    • The next step is Hold for Bids/Proposals ReceivedIf Revise is chosen the next step is Initiator Prepares Bid Documents.

    Toggle Cloak
    Hold for Bids/Proposals ReceivedInitiator Releases Bid

    Cloak

    The bid should be released in the Bid module when the process reaches this step.

    • Hold the process in this step from bid release until all bids are received and the bid tab has been opened and analyzed. This may be held for one to several weeks while the bid is open.
    • Once the bids have been analyzed and a vendor recommendation is ready the Project Manager takes the Submit action initiator (usually the Project Manager) works within the Bidding module to complete the steps that enable the Bidding portal for the bid package.Once the bid has been released the Initiator completes the required process fields, takes the Submit Action.
    • The next step is Initiator Recommend Vendor Recommendation.
    Card
    labelBid Award Recommendation

    Toggle Cloak
    Vendor Recommendation

    Cloak
    • The Project Manager, having received all the bids and supporting documents, performs the analysis and selects a vendor.
    • The process step form is completed and the Submit action is taken.
    • The next step is Selection of Source.

    Toggle Cloak
    Selection of Source (Automatic Step)

    Cloak
    • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
    • The next step is Vendor Manager Review of SoS.

    Toggle Cloak
    Vendor Manager Review of SoS

    Cloak
    • The Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
    • If Submit is chosen the next step is Program Manager Review
    • If Revise is chosen the next step is Vendor Recommendation.

    Toggle Cloak
    Program Manager Review

    Cloak
    • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
    • If Submit is chosen the next step is Campus Construction.
    • If Revise is chosen the next step is Initiator Revise Recommendation.

    Toggle Cloak
    Initiator Revise Recommendation

    Cloak
    • The Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
    • If Submit is chosen the next step is Selection of Source.
    • If Void is chosen the next step is Finish.

    Toggle Cloak
    Campus Construction (Decisional Step)?

    Cloak
    • e-Builder uses information previously entered to to determine "ownership" of the program.
    • If True (Yes) the next step is SP&T Program.
    • If False (No) the next step is M&U.

    Toggle Cloak
    SP&T Program? (Decisional Step)

    Cloak
    • The "Contract managed by a different program" field is evaluated.
    • If True (Yes) the next step is SPT Director Review.
    • If False (No) the next step is Vendor Manager Review of SoS

    Toggle Cloak
    SPT Director Review

    Cloak
    • The SPT Director reads the comments and reviews the process fields. The SPT Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Vendor Manager Review of SoS.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    M&U (Decisional Step)U2?

    Cloak
    • e-Builder uses information previously entered to determine "ownership" of the program.
    • If True (Yes) the next step is Utilities Program?
    • If False (No) the next step is Vendor Manager Review of SoS. Campus Services?

    Toggle Cloak
    Utilities Program (Decisional Step)?

    Cloak
    • e-Builder uses information previously entered to determine "ownership" of the program.
    • If True (Yes) the next step is Utilities Director Review.
    • If False (No) the next step is SEG Program?.

    Toggle Cloak
    Utilities Director Review Rec

    Cloak
    • The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
      If Submit is chosen the next step is Vendor Manager Review of SoS M&U Director Review Rec.
    • If Revise is chosen the next step is Initiator ReviewRevise Recommendation.

    Toggle Cloak
    SEG Program?

    Cloak
    • e-Builder uses information previously entered to determine if this is an SEG Program.
    • If True (Yes) the nest step is SEG Director Review Rec
    • If False (No) the next step is O&M Director Review .Rec

    Toggle Cloak
    SEG Director Review Rec

    Cloak
    • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to take an Action to Submit or Revise.
    • If Submit is chosen the next step is Vendor Manager Review of SoS.
    • If Revise is chosen the next step is Initiator Revise Recommendation.

    Toggle Cloak
    O&M Director Review Rec

    Cloak
    Cloak
    • The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
    • If Submit is chosen the next step is Vendor Manager Review of SoS.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Vendor Manager Review of SoS

    • Vendor Manager reads the comments and reviews the process fields. Vendor Manager Procurement has the option to Submit or Revise.
    • If Submit is chosen the next step is Campus Construction Vendor Manager Review of SoS.
    • If Revise is chosen the next step is Initiator Revise .

    Toggle Cloak
    Campus Construction (Decisional Step)

    Cloak
    • Multiple fields are evaluated to determine if this is a Campus Construction program.
    • If True (Yes) the next step is CC Director Review.
    • If False (No) the next step is OCP?Recommendation.

    Toggle Cloak
    CC Director Review

    Cloak
    • The CC Director reads the comments and reviews the process fields. CC Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Initiator Awards Bid.
    • If Revise is chosen the next step is Initiator Revise Recommendation.

    Toggle Cloak
    OCP? (Decisional Step)

    Cloak
    • Multiple fields are evaluated to determine if this is an OCP Program.
    • If True (Yes) the next step is OCP Director Review.
    • If False (No) the next step is M&U?.

    Toggle Cloak
    OCP Director Review

    Cloak
    • The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Initiator Awards Bid.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    M&U? (Decisional Step)

    Cloak
    • Multiple fields are evaluated to determine if this is an M&U program
    • If True (Yes) the next step is M&U Director Review
    • If False (No) the next step is Campus Services? Initiator Revise Recommendation.

    Toggle Cloak
    M&U Director Review Rec

    Cloak
    • The M&U Director reads the comments and reviews the process fields and has the option to Submit or Revise
    • If Submit is chosen the next step is Initiator Awards Bid
    • If Revise is chosen the next step is Initiator Revise Recommendation.

    Toggle Cloak
    Campus Services? (Decisional Field)

    Cloak
    • Multiple fields are evaluated to determine if this is an Campus Services program?
    • If True (Yes) the next step is CS Director Review.
    • If False (No) the next step is IBO Director Review.

    Toggle Cloak
    CS Director Review

    Cloak
    • The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Initiator Awards Bid.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    IBO Director Review

    Cloak
    • The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
    • If Submit is chosen the next step is Initiator Awards Bid.
    • If Revise is chosen the next step is Initiator Revise.

    Toggle Cloak
    Initiator Award Bid

    Cloak
    • The Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
    • The next step is Vendor Manager Checks Company Info.

    Toggle Cloak
    Pre-Priced #33?

    Cloak
    • This conditional determines if this process contains a Pre-priced agreement.
    • If True the process moves to Finish.
    • If False the process moves to Vendor Manager Checks Company Info

    Toggle Cloak
    Vendor Manager Mgr Checks Company Info

    Cloak
    • The Vendor Managerchecks and fills out form fields to ensure that:
      • The awarded bidder exists in SAP
      • The company information is correct and current in the Contacts module.
      • If the company is not in SAP that the New Company process has been started.
    • When finished the Vendor Manager takes the Submit action.
    • The next step is Vendor Exists in SAP?

    Toggle Cloak
    Vendor Exists in SAP (Decisional)?

    Cloak
    • This step routes the process to the Finish step if the Vendor exists in SAP.
    • If the Vendor does not exist in SAP the next step is AA Adds New Company.

    Toggle Cloak
    AA Adds New Company

    Cloak
    • If the company does not exist in SAP the AA completes the 01.01 Add New Company/
    Contact process and holds the process in this step until that has been completed.

    When completed the AA takes the Vendor Added action.

    The next step is Vendor Manager Checks Company Info.

    Finish
    • Contact process and holds the process in this step until that has been completed.
    • When completed the AA takes the Vendor Added action.
    • The next step is Vendor Manager Checks Company Info.

    Toggle Cloak
    Hold for SAP Vendor #

    Cloak
    • In this step the Administrative Assistant waits until the Vendor has been assigned a SAP Vendor Number from VPF.
    • If the Submit action is taken the next step is Finish.
    • If the Revise action is taken the next step is AA Adds New Company.

    Toggle Cloak
    Finish

    Cloak