We are working on the release of RAFT II. This is a major release. This checklist tracks is the current release path of RAFT II to the service operations, primarily from the Business Intelligence development team to Customer Support, Training, and Server & System Administration. Change Management - Enter release date, and other significant dates, on Change Communications Calendar.
- Exchange resource name: IS&T: Change Communications
- When these dates change, communicate to ist-pipeline list.
- This has not been done in a while, dates have changed a lot.
- Planned major milestones recorded on wiki home page.
- Send announcement and change log to ist-pipeline@mit.edu, stakeholder list once release is complete.
- Update any known open issues (Jira, Request Tracker) affected by release and close.
- Search http://ist.mit.edu.ezproxyberklee.flo.org and http://kb.mit.edufor any articles that would be invalidated by release and update as needed. Contact istweb@mit.edu if you are not sure how to update this documentation.
- Contact IS&T Communications for public release announcement.
- If sending outside of IS&T, send draft release announcement to IS&T communications team at least 2 business days prior to release.
- Inform ist-pipeline@mit.edu, pipeline of release at least 1 business day prior to release.
- Consider how to support early adopters or pilot users, phase out current version?
- Pilot release in May, community release in June. Still no hard transition plan for RAFT I users?
- Review need to de-support of previous version(s), communications to current users.
- Create communication plan, based on stakeholders identified in prior steps.
Configuration Management - Critical Path: Need stable test environment!
- Migrating from RAFT I environments to new, clean VMs for RAFT II
- raft-test in place, needs PHP downgrade?
- raft-r1, new raft production, does not exist yet.
- Await decision on budget for drupal-based online help systems. bi-help-dev installed on temporary system so documenation staff can begin work.
- Update datacenter SLAs with technical, financial, business contact information.
Release and Deployment Management - OLA: business-support team engagement, OLA in development: Service Levels Development
- Developing blanket OLA between business-support and Business Intelligence team.
- Code management/versioning and continuous integration plan with release engineer. Deploy from Bamboo or directly from SVN.
Evaluation and Testing - See "evaluators" list at right. Responsible parties for internal evaluation. Must sign off. Second architecture review still required by this group.
- Input and sign-off by Usability Team: Usability & Accessibility Reports.
- Stakeholder committee schedule in place, core business users signed up for rolling usability-test plan.
- BI Team to provide smoke-test/system health page for Customer Support?
- business-help and business-intelligence teams to perform smoke tests for every patch or update during burn-in period (six week from go-live).
Knowledge Management - Training Plan
- Training mutual venture of SE Training team and COUES Training team.
- Training curriculum, work with Training to ramp-up Help Desk (business-support).
- Online Help: SE Training, Mark Wiklund.
- Develop RAFT escalation scripts from Tier 2 (business-support) and Tier 3 (raft-support). Support Escalations Outline
|
Column |
---|
Panel |
---|
borderColor | blue |
---|
borderWidth | 1 |
---|
title | Transition Teams |
---|
borderStyle | solid |
---|
| When in doubt, raft-support@mit.edu. Release Team Technical Lead, Amon Horne Release Coordination, Steve Landry Systems Operations, Nathan Thaler COEUS Integration: Carol Wood Evaluation, Internal Acceptance Accessibility and Usability: Katherine Wahl Database Administration Team: Rob Grenier Service Desk: Jessica Donnelly Reed Server and Systems Administration: Garry Zacheiss Business-user testing team, mitbi-test@mit.edu Knowledge Management Jessica Donnelly Reed: Service Desk Mark Wiklund: Training Peggy McGrath: Business Intelligence Carole Trainor: COUES Training |
|
|
This documentation is for planning the release of RAFT PhII to the support areas of IS&T. Other parts of the project plan and implementation details that are not relevant to support teams should go elsewhere.
Checklist
Not in order of priority or chronology yet.
Notes
We used IS&T's product-release checklist as a base for this plan though it was developed for distributed/desktop release. You might not have authorizations to view the release-core wiki.
Product-Release Checklist
Based on this system's criteria, RAFT is Resources: High, Community Impact: Moderate, and Risk to IS&T: High.
...