If you go to AMPS page,its randomized by refresh of the page. Can be randomzies randomizes between anything, it can be TechTv, the videos can come from AMPS video server, DVD, anywhere. Very cool!THi
4.) Implementation Questions.
a.) Prepare for usability testing. Basic html. For the test, how much content needs to be written and required. Kate: for usability, build the first one, and then build a complete path.
b.)Where do we host this? We agreed that we don't want it to be hosted at IS&T. If we want it to look like Teaching with Technology. We agree we want to host it there.
c.) Black out periods for the team:
Kate: May 17-31; Ann: 1st week in July; Molly: June 20-Jul5; Peter: May 15-June 6; Kris: May 1-15; Elaine May 13th, June 1- 11th.
5.) Milestones:
Wireframe/html: front page, 1 or more completed paths. (1-3 weeks) Ranjani, Peter, Molly
Content creation (3 weeks) Kate, Kris, Elaine
Usability Testing (1.5 weeks) IS&T Micheal and Christine
Process UT fixes (2 weeks) Ranjani, Peter, Molly
Build out site (4 weeks) everybody
6.) Timeline:
April1 - May 15 | May 15 - June1 | June 1 - 21 | June 21 - July 21 | July 21 - Aug 1 |
---|---|---|---|---|
Wireframe/html | Usability Testing | process fixes from | Build out the site | Final tweaks, |