Project Timelines and Milestones:

  • Orginal goal was to complete the new online component by the end of FY08 (was this correct?)Goal is to roll out HR Staffing Services web site by early fall

Revised timeline and major milestones for the NEO web site project:

  • 4/11 RFP distributed
  • 4/23 Vendors Selected
  • 5/1 Kickoff Meeting
  • 9/3 Target Release Date

Consolidated Design and Writing Schedule (updated 6/09/08)

Development Schedule (updated 7/01/08)

Multimedia Development Schedule (updated 6/09/08)TBD