Hourly Student Appointment Automation Project

Reporting Period: May 9, 2011 - May 13, 2011

Overall Status:   (warning)     

Please note that the overall status continues to appear yellow due to resource issues, not actual project work/schedule. We are slightly ahead of schedule on non webdynpro development and on target for all other work.

...

Type

Description

Owner

Current Status

Mitigation Strategy (for risk only)

Due Date

Risk

Originally the QA resource was scheduled to work 50% on the EL project and 50% on the Hourly Student Appointment (HSA) project for the entire project.  EL now requires 100% QA resource effective in July. May result in project delays to HSA project if QA resource is not available when we need him

Karon

Resource started on 5/2 and gave his notice on 5/6/2011. New risk - delays could result if replacement is not found in a timely manner; new search in progress

Reassess once we finalize the project schedule

04/30/2011
new due date TBD