- Remedy 8 Prototype update
- negotiations ongoing
- start date moved out to 4/29
- stakeholder commitments in process
- Data Management: Sherene, Peggy and Rob Campanella confirmed
- DITR: Sar, Rashard, Greg, Bill Furtado, Joe Pitha confirmed
- HD: Jake, Bill, Jozsef, Cynthia, Lisa, Jennifer, Stuart and Fred status?
- Website: Alison status?
- NetOps: Chris, Rich and Deb status?
- need Training resource as Kate is leaving MIT
- ServiceNow prototype proposal
- free of charge
- Pat has con call with them 3/28
- move forward
- Change Management update
- NetOps needs to choose service offeringswants to move forward with Exchange
- sketch out the environment and resources at next Steering Committee meeting 4/17
- invite Rich Edelson to attend
- PCI is moving into business analysis phase for April
- RAFT still in a sprint but on target for demo in April
- Revisit Altiris, Casper and Lite Touch need some advocacythis summer
- NetOps needs to choose service offeringswants to move forward with Exchange