Milestones

Status

Project Planning

      

Project Kickoff

      

Community Communications

   √

Windows Selection

 

    IS Forefront Evaluation

complete by late January   √

    IS ESET Evaluation

complete by late January   √

    Vendor Demo

scheduling schedule by late January

    Analyze Recommendation and Solution

February

    Sponsor Approval

February

    Pilot Rollout

End of February

   Sponsor Approval

March

    Procurement

March

    Early Adopters

April

    Final Review and Approval

May

    Full Rollout

June

MAC Selection

 

   IS Sophos Evaluation

  √

   IS ESET Evaluation

complete by late January

    Vendor Demo

schedule by late January

    Analyze Recommendation and Solution

February

   Sponsor Approval

February

    Pilot Rollout

End of February

  Sponsor Approval

March

    Procurement

March

    Early Adopters

April

    Final Review and Approval

May

    Full Rollout

June

Project Wrap up

June 2013