  • Provision systems, VMs, based on initial architecture plan.
    • New raft-test and raft-prod systems in place. To replace existing RAFT I servers.
    • Await decision on budget for online help systems. bi-help-dev installed on temporary system so documenation staff can begin work.
  • Update datacenter SLAs with technical, financial, business contact information.
  • Developing blanket SLA between business-support and Business Intelligence team.
  • Training curriculum, work with Training to ramp-up Help Desk (business-support).
  • Stakeholder engagement: Trying to move design documents to wiki for better collaboration, resources limited.
  • Develop RAFT escalation scripts from Tier 2 (business-support) and Tier 3 (raft-support). Service-Delivery Plan Support Escalations Outline
  • Phased usability test plan underway with phased rollout of RAFT functionalitY: Usability & Accessibility.

...