- Small Scope (i.e. Acrobat Reader)
- Single or multi-platform
- Time to complete - 40 person hours or less
- Decision can be made and managed mostly within SWRT Team
- Mediums Scope (i.e. VirusScan)
- Project, multiple people
- Multiple platforms involved - 1 month of calendar time
- Resources from CSS
- May have to use a few resources outside of SWRT
- Large Scope (i.e. TSM, Apple Mail, MS Office)
- Large project with multiple people
- Resources outside of CSS are critical
- Very Large Scope (i.e. Operating System)
- IS&T as a department is involved
| Scope
| Decision Maker
| Examples
| Time
|Small
Platform Coordinator
Acrobat Reader
~40 hours
Medium
SWRT Leader/Team
Virus Scan
~1 month
Large
CSS Director
TSM, Filemaker Pro
1+ months
Very Large
IS&T VP Staff
Operating System
2+ months
- IS&T as a department is involved