- The Project Manager fills out the required fields and clicks Submit.
- The next step is Systems Renwal?
| Systems Renewal Cloak |
---|
- The system determines if this process is for Systems Renewal based on the project manager's response to the question "Requesting Add'l Capital Renewal funds?"
- If it is for Systems Renewal the next step is CC Planner Review
- If it is not for Systems Renewal the next step is Return Funds?
|
CC Planner Review Cloak |
---|
- The CC Planner reviews the process, completes any required fields and chooses one of these actions;
- To CC Planning Manager
- To PM for Revision
- If To CC Planning Manager is chosen the next step is CC Planning Manager Review.
- If To PM is chosen the next step is Initiator Revise.
| CC Planning Manager Review Cloak |
---|
- The Planning Manager reviews and may edit the process When finished the only option is to send the process back to the CC Planner
|
CC Planning Dir Review Cloak |
---|
- The CC Planning Director reviews the request and has the option to Submit if approved or ask the CC Planning Mgr for revisions.
|
Initiator Revises Cloak |
---|
- From the CC planner Review step the CC Planner can request that the project manager revise the request. Once revised, the PM can resubmit the request to the CC planner.
|
Return Funds? Cloak |
---|
- Return funds is a decision step.
- If funds are being returned to the program the next step is Program Manager Review A
- If funds are not being returned to the program the next step is Program Manager Review B
| Program Manager Review A Cloak |
---|
- The Program Manager reviews the process, adds comments if necessary and when finished chooses to Submit or to Revise.
- If Submit is chosen the next step isCC Director Review.
- If Revise is chosen the next step is Initiator Revise and Submit.
| CC Director Review Cloak |
---|
- The CC Director reviews the form and has the option to Submit or Revise.
- If Submit is chosen the next step is Financial Analyst Adjusts Funding.
- If Revise is chosen the next step is Initiator Revise and Resubmit.
|
Initiator Revise and Submit Cloak |
---|
- The Project Manager reads the comments, reviews process fields and updates as necessary and when finished chooses to Resubmit or to Void.
- Resubmit is chosen the next step is Return Funds
- If Void is chosen the next step is Finish
|
Governance Review
Cloak |
---|
- The Budget Planning Manager reviews process fields and updates the funding data as necessary and when finished chooses Submit.
|
Financial Analyst Adjusts Funding Cloak |
---|
- The Financial Analyst reads the comments, adjusts the funding and then clicks Submit.
- The next step is True-Up Form/Addl, a mail merge step that creates the True-Up form.
- Once the mail merge is completed the process is Code Complete and goes to the Finish step.
| True Up Form Cloak |
---|
- Automatic Step to generate the True Up form document
- The next step is Finish
| Program Manager Review B Cloak |
---|
- The Program Manager reads the comments, reviews the process fields and chooses to Submit or Revise.
- If Submit is chosen the next step is CC Project?
- If Revise is chosen the next step is PM Reviews Com Initiator Revise and Resubmit
| CC Project? Cloak |
---|
- This is a decision step. e-Builder evaluates the Project Type to determine if the value is "Capital Renewal"
- If True the next step isProject Director Review
- If Falsethe next step is M&U Project?
| M&U Project? Cloak |
---|
- This is a decision step. e-Builder evaluates the Project Type to determine if the value is "Utilities".
- If True the next step is M&U Director Review
- If False the next step is OCP Project?
| OCP? Cloak |
---|
- This step is a decision step. e-Builder evaluates the Project Type to determine if the value is "OCP"
- If True the next step is OCP Director Review
- If False the next step is Director of Housing Review
| Campus Services? Cloak |
---|
- This step is a decision step. e-Builder evaluates the Project Type to determine if the value is "Campus Services"
- If True the next step is Campus Services Director.
- If False the next step is Dir of Fin & Adm Review
| Dir of Fin & Adm Review Cloak |
---|
- The Director of Finance and Administration reads the comments and review the process fields and has the option to Submit, Revise, or Send to CC Director.
- If Submit is chosen the next step is VP, CSS Executes.
- If Revise is chosen the next step is Initiator Revise and Resubmit.
- If Send to CC Director is chosen the next step is CC Director Review.
|
VP, CSS Executes Cloak |
---|
- The IBO Director reads the comments and review the process fields and has the option to Submit, Revise, or Send to CC Director.
- If Submit is chosen the next step is DoF Dept Funding?
- If Revise is chosen the next step is Initiator Revise and Resubmit
- If Send to CC Director is chosen the next step is CC Director Review.
| CC Director Review Cloak |
---|
- The CC Director reads the comments and review the process fields and has the option to Submit or Revise.
- If Submit is chosen the next step is CC Director Review.
- If Send to Dir of Fin and Adm is chosen the next step is Dir of Fin & Adm Review.
- If Send to Utilities Director is chosen the next step is Utilities Director Review.
- If Send to O&M Director is chosen the next step is O&M Director Review.
- If Send to FEG Director is chosen the next step is SEG Director Review.
- If Send to M&U Director is chosen the next step is M&U Director Review.
- If Send to OCP Director is chosen the next step is OCP Director Review.
- If Send to Campus Services Director is chosen the next step is Campus Services Director.
| M&U Director Review Cloak |
---|
- The M&U Director reads the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
| OCP Director Review Cloak |
---|
- The OCP Director reads the the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
| DoF Department Funding? Cloak |
---|
- This is a decision step. e-Builder evaluates the value of the Department Funding field.
- If Yes the next step is Governance Review_2
- If False the next step is DoF Contingency?
| Governance Review_2 Cloak |
---|
- Governance Review reads the comments and reviews the process fields and clicks Approve.
- The next step is True Up Form / Addi
- If the To PM -> Revise action is taken the next step is Initiator Revise & Resubmit.
| DoF Contingency Cloak |
---|
- This is a decision step. e-Builder evaluates the value of the Funding Source field.
- If True the next step is Financial Analyst Adds Funding
- If False the next step is EVPT Contingency?
| EVPT Contingency Cloak |
---|
- This is a decision step. e-Builder evaluates the value of the Funding Source field.
- If True the next step is Deputy EVPT Review
- If False the next step is Governance Review_1
| Deputy EVPT Review Cloak |
---|
- The EVPT Office reads the comments and reviews the process fields and then clicks Submit.
- The next step is Financial Analyst Adds Funding
| Governance Review_1 Cloak |
---|
- Governance Review reads the comments and reviews the process fields and clicks Approve.
- The next step is True Up Form / Addi
| True Up Form Cloak |
---|
- Automatic step to generate the true up form document.
- The Next Step is Financial Analyst Adds Funding
|
Financial Analyst Adds Funding Cloak |
---|
- The financial analyst adds the funding to the project and will compete the required process fields clicks to add funds.
- The next step is Finish
| Finish |