Result or Product of this Process

Round Rectangle
bgcolor#e6f2ff

This process is used to request a Journal Voucher.

Deck of Cards
idCardsJV
Card
labelSummary

Project Managers should use this process to:

  • Move costs from one GL to another within a project
  • Move costs from one project to another project

DoF Accounting will use this process to:

  • Convert the project from a Capital to an Expense project
  • Move asbestos/moving to a separate cost object
  • Convert non-billable time to billable
  • Split the project into multiple projects after project completion
Card
labelProcess Map

Card
labelStep Descriptions

Toggle Cloak
Initiation

Cloak
  • Started by the Accounting Manager or the Project Manager who fills out the required fields and attaches the associated documents before using the Submit option
  • The next step is Capital Expense

Toggle Cloak
Final Invoice?

Cloak
  • Multiple fields are evaluated to determine the reason for the Journal Voucher
  • If True the next step is Acct Change eB Info and Create JV
  • If False the next step is Correct Project GL?

Toggle Cloak
Acct Change eB Info and Create JV

Cloak
  • The Accounting Manager reads the comments and reviews the process fields and executes the Complete option
  • The next step is Finish

Toggle Cloak
Correct Project GL?

Cloak
  • The Reason for JV Request field is evaluated to determine if this JV request is "To correct the cost element to which a cost was changed within a project"
  • If True (Yes) the next step is PC Creates Budget Change Process
  • If False (No) the next step is Asbestos Move?

Toggle Cloak
PM Creates Budget Change Process

Cloak
  • The project manager reads the comments and reviews the process fields and takes the Complete action
  • The next step is POs on Project?

Toggle Cloak
POs on Project?

Cloak
  • The data field "Are there any purchase orders on the project" is evalulated
  • If True (Yes) the next step is PM Creates Commitment Change Process
  • If False (No) the next step is Account Creates GL Change JV

Toggle Cloak
PM Creates Commitment Change Process

Cloak
  • The project manager  reads the comments and reviews the process fields and takes the Complete action
  • The next step is POs on Project?

Toggle Cloak
Account Creates GL Change JV

Cloak
  • The accounting manager reads the comments, reviews the process and takes the Complete action
  • The next step is Finish

Toggle Cloak
Asbestos Move?

Cloak
  • The data field "Asbestos moving to separate cost object?" is evaluated
  • If True (Yes) the next step is Acct Updates eB & Creates Asbestos JV
  • If False (No) the next step is Nonbillable/Billable.

Toggle Cloak
Acct Updates eB & Creates Asbestos JV

Cloak
  • The accounting manager reads the comments, reviews the process fields and takes the Complete action.
    The next step is Finish.

Toggle Cloak
Billable/Non-Billable

Cloak
  • The data field Reason for JV Request is evaluated to determine if it is equal to "Previously non-billable time is being determined as billable".
  • If True the next step is eB Admin Changes Project Number.
  • If False the next step is Wrong Project Cost?

Toggle Cloak
eB Admin Changes Project Number

Cloak
  • The eB admin reads the comments and reviews the process fields and takes the Complete action
  • The next step is Previous Time Bill?

Toggle Cloak
Previous Time Bill?

Cloak
  • The data field Reason for JV Request is evaluated to determine if it is equal to Previously non-billable time is being determined as billable
  • If True the next step is Accounting Creates Billable Time JV
  • If False the next step is Finish

Toggle Cloak
Accounting Creates Billable Time JV

Cloak
  • The accounting manager reads the comments, reviews the process fields and takes the Complete action
  • The next step is Finish

Toggle Cloak
Wrong Project Cost?

Cloak
  • The data field Reason for JV Request is evaluated to determine if it is equal to Costs were charged to the wrong project
  • If True the next step is Acct Creates Transfer JV
  • If False the next step is eB Admin Creates/Joins Projects

Toggle Cloak
Acct Creates Transfer JV

Cloak
  • The accounting manager reads the comments, reviews the process fields and takes the Complete action
  • The next step is Finish

Toggle Cloak
eB Admin Creates/Joins Projects

Cloak
  • The eB admin reads the comments and reviews the process fields and takes the Complete action
  • The next step is Acct Creates Cost Object IO

Toggle Cloak
Acct Creates Cost Object IO

Cloak
  • The accounting manager reads the comments, reviews the process fields and takes the Complete action
  • The next step is PM Determines/Triggers Reallocation

Toggle Cloak
PM Determines/Triggers Reallocation

Cloak
  • The project manager reads the comments and reviews the process fields and takes the Complete action
  • The next step is Finance Reallocates Cost

Toggle Cloak
Finance Reallocates Cost

Cloak
  • The financial analyst reads the comments and reviews the process fields and takes the Complete action
  • The next step is Accounting Creates Reallocation JV

Toggle Cloak
Accounting Creates Reallocation JV

Cloak
  • The accounting manager read the comments, reviews the process fields and takes the Complete action
  • The next step is Finish

Toggle Cloak
Finish

Cloak

Card
idPFIJV
labelProcess Form Instructions

Instructions for Project Managers

  1. Complete Section A

  2. To move costs from one GL to another on this project complete Sections B and C

  3. To move costs from this project to another project (or vice versa) complete Sections B and C.
    If you are not the PM on the other project you should attach documentation (email) indicating that the PM of the other project accepts the charges.
  4. If "other" provide as much information as possible.

Note: By using this process you are requesting a JV. The request is reviewed by accounting resources prior to any processing. If you do not have complete information fill in only the required fields and the information you have and accounting will guide you on any other information that is needed.

DoF Accounting Instructions

  1. Complete Section A
  2. To convert this project from a Capital to Expense project (or vice versa) complete Section E.
  3. To move Asbestos/Moving to a separate cost object , complete Section E.
  4. To convert non-billable time to billable, complete Section F.
  5. To split this project into multiple projects after completion, complete Sections D and E.