- The Vendor Manager reviews the Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
- If Submit is chosen the next step is Program Manager Review
- If Revise is chosen the next step is Vendor Recommendation.
| Program Manager Review Cloak |
---|
- The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
- If Submit is chosen the next step is Campus Construction.
- If Revise is chosen the next step is Initiator Revise Recommendation.
| Initiator Revise Recommendation Cloak |
---|
- The Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
- If Submit is chosen the next step is Selection of Source.
- If Void is chosen the next step is Finish.
| Campus Construction? Cloak |
---|
- e-Builder uses information previously entered to to determine "ownership" of the program.
- If True (Yes) the next step is SP&T Program.
- If False (No) the next step is M&U.
| SP&T Program? Cloak |
---|
- The "Contract managed by a different program" field is evaluated.
- If True (Yes) the next step is SPT Director Review.
- If False (No) the next step is Vendor Manager Review of SoS
| SPT Director Review Cloak |
---|
- The SPT Director reads the comments and reviews the process fields. The SPT Director has the option to Submit or Revise.
- If Submit is chosen the next step is Vendor Manager Review of SoS.
- If Revise is chosen the next step is Initiator Revise.
| M&U2? Cloak |
---|
- e-Builder uses information previously entered to determine "ownership" of the program.
- If True (Yes) the next step is Utilities Program?
- If False (No) the next step is Campus Services?
| Utilities Program? Cloak |
---|
- e-Builder uses information previously entered to determine "ownership" of the program.
- If True (Yes) the next step is Utilities Director Review.
- If False (No) the next step is SEG Program?.
| Utilities Director Review Rec Cloak |
---|
- The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
If Submit is chosen the next step is M&U Director Review Rec. - If Revise is chosen the next step is Initiator Revise Recommendation.
| SEG Program? Cloak |
---|
- e-Builder uses information previously entered to determine if this is an SEG Program.
- If True (Yes) the nest step is SEG Director Review Rec
- If False (No) the next step is O&M Director Review Rec
| SEG Director Review Rec Cloak |
---|
- The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to take an Action to Submit or Revise.
- If Submit is chosen the next step is Vendor Manager Review of SoS.
- If Revise is chosen the next step is Initiator Revise Recommendation.
| O&M Director Review Rec Cloak |
---|
Cloak |
---|
- The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
- If Submit is chosen the next step is Vendor Manager Review of SoS.
- If Revise is chosen the next step is Initiator Revise.
| Vendor Manager Review of SoS
- Vendor Manager reads the comments and reviews the process fields. Vendor Manager has the option to Submit or Revise.
- If Submit is chosen the next step is Campus Construction Vendor Manager Review of SoS.
- If Revise is chosen the next step is Initiator Revise.
| Campus Construction (Decisional Step) Cloak |
---|
- Multiple fields are evaluated to determine if this is a Campus Construction program.
- If True (Yes) the next step is CC Director Review.
- If False (No) the next step is OCP? Initiator Revise Recommendation.
| CC Director Review Cloak |
---|
- The CC Director reads the comments and reviews the process fields. CC Director has the option to Submit or Revise.
- If Submit is chosen the next step is Initiator Awards Bid.
- If Revise is chosen the next step is Initiator Revise Recommendation.
| OCP? (Decisional Step) Cloak |
---|
- Multiple fields are evaluated to determine if this is an OCP Program.
- If True (Yes) the next step is OCP Director Review.
- If False (No) the next step is M&U?.
| OCP Director Review Cloak |
---|
- The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
- If Submit is chosen the next step is Initiator Awards Bid.
- If Revise is chosen the next step is Initiator Revise.
| M&U? (Decisional Step) Cloak |
---|
- Multiple fields are evaluated to determine if this is an M&U program
- If True (Yes) the next step is M&U Director Review
- If False (No) the next step is Campus Services? Initiator Revise Recommendation.
| M&U Director Review Rec Cloak |
---|
- The M&U Director reads the comments and reviews the process fields and has the option to Submit or Revise
- If Submit is chosen the next step is Initiator Awards Bid
- If Revise is chosen the next step is Initiator Revise Recommendation.
| Campus Services? (Decisional Field) Cloak |
---|
- Multiple fields are evaluated to determine if this is an Campus Services program?
- If True (Yes) the next step is CS Director Review.
- If False (No) the next step is IBO Director Review.
| CS Director Review Cloak |
---|
- The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
- If Submit is chosen the next step is Initiator Awards Bid.
- If Revise is chosen the next step is Initiator Revise.
| IBO Director Review Cloak |
---|
- The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
- If Submit is chosen the next step is Initiator Awards Bid.
- If Revise is chosen the next step is Initiator Revise.
| Initiator Award Bid Cloak |
---|
- The Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
- The next step is Vendor Manager Checks Company Info.
|
Pre-Priced #33? Cloak |
---|
- This conditional determines if this process contains a Pre-priced agreement.
- If True the process moves to Finish.
- If False the process moves to Vendor Manager Checks Company Info
|
Vendor Manager Mgr Checks Company Info Cloak |
---|
- The Vendor Managerchecks and fills out form fields to ensure that:
- The awarded bidder exists in SAP
- The company information is correct and current in the Contacts module.
- If the company is not in SAP that the New Company process has been started.
- When finished the Vendor Manager takes the Submit action.
- The next step is Vendor Exists in SAP?
|
Vendor Exists in SAP (Decisional)? Cloak |
---|
- This step routes the process to the Finish step if the Vendor exists in SAP.
- If the Vendor does not exist in SAP the next step is AA Adds New Company.
|
AA Adds New Company Cloak |
---|
- If the company does not exist in SAP the AA completes the 01.01 Add New Company/Contact
process and holds the process in this step until that has been completed.When completed the AA takes the Vendor Added action. The next step is Vendor Manager Checks Company Info. | Finish- process and holds the process in this step until that has been completed.
- When completed the AA takes the Vendor Added action.
- The next step is Vendor Manager Checks Company Info.
|
Hold for SAP Vendor # Cloak |
---|
- In this step the Administrative Assistant waits until the Vendor has been assigned a SAP Vendor Number from VPF.
- If the Submit action is taken the next step is Finish.
- If the Revise action is taken the next step is AA Adds New Company.
| Finish |