| This process can be started by the A/E Lead, Administrative Assistant, CC Planner, Consultant, Contractor, OCP Planner, Project Manager and SPT Lead. This process is used to submit, review and approve the following: Amendments to Commitments (Contracts) & Purchase Orders issues to Professional Services vendors (A/E, Designers, Consultants), Master Design Agreement Release Change Orders, and Phased Purchase Order Releases (under and executed design contract). |
Card |
---|
|  |
Card |
---|
| Start Cloak |
---|
- The Process Initiator fills out the required fields and chooses to submit.
- The next step is MDA Release?
| MDA Release? Cloak |
---|
- The MDA Release? Conditionalchecks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
- If True (Yes) the next step is PM Enters Release
- If False (No) the next step is PO Release?
| PO Release? Cloak |
---|
- The PO Release? Conditional checks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
- If True (Yes) the next step is PO CO MM
- If False (No) the next step is A/E Initiated?
| A/E Initiated? Cloak |
---|
- The A/E Initiated? Conditional checks if the role of the Process Initiator was A/E Lead or Consultant.
- If True (Yes) the next step is PSA Mail Merge
- If False (No) the next step is PSA MM (for A/E man
| PM Enters Release Cloak |
---|
- The Project Manager adds the appropriate release from the 05.02.05 MDA Release(s) folder of project 11112, and fills out any required fields.
- If Submit is chosen the next step is Program Manager Review MDA
- If Revise is chosen the next step is Initiator Revise MDA
- If Void is chosen the next step is Finish and the process is set to a Void status.
| Program Manager Review MDA Cloak |
---|
- The Program Manager reviews the Master Design Agreement Release details
- If Submit is chosen the next step is Vendor Signature
- If Revise is chosen the next step is Initiator Revise MDA
| Contracts Group Cloak |
---|
- The Contract Admin reviews the Master Design Agreement Release details, makes any changes and if necessary re-uploads the document in the PSA/MDA for Signature field.
- If Submit is chosen the next step is Program Manager Review MDA
- If Revise is chosen the next step is Initiator Revise MDA
- If Void is chosen the next step is Finish and the process is set to a Void status.
| Initiator Revise MDA Cloak |
---|
- The Initiator Revise MDA step allows the Process Initiator to make changes and resubmit the process.
- If Resubmit is chosen the next step is MDA Release
- If Void is chosen the next step is Finish and the process is set to a Void status.
| Vendor Signature Cloak |
---|
- The Consultant, A/E Lead and/or the Project Manager takes the appropriate action to sign the document.
- If Submit is chosen the next step is Program Manager Review MDA
- If Revise is chosen the next step is Initiator Revise MDA
| PO CO MM Cloak |
---|
- The PO CO MM step is a mail merge automation step that completes the Phased Purchase Order Release mail merge document.
- The next step is PM Attaches Contract
| PM Attaches Contract Cloak |
---|
- The Project Manager attaches a copy of the vendor executed contract, and fills out the PM Description of Change (Internal Only) field if necessary.
- The next step is Program Manager Reviews PO
| Program Manager Reviews PO Cloak |
---|
- The Program Manager reviews the Phased Purchase Order Release details.
- If Reviewed is chosen the next step is OCP?
- If Revise is chosen the next step is Initiator Revise PO Release
| OCP? Cloak |
---|
- The OCP? Conditional checks if the Program Type of the project is OCP
- If True (Yes) the next step is OCP Director Approval
- If False (No) the next step is CC Director Approval
| CC Director Approval Cloak |
---|
- The CC Director takes the appropriate action to approve the document.
- If Submit is chosen the next step is SAP Hold Step
- If Revise is chosen the next step is Initiator Revise PO Release
| OCP Director Approval Cloak |
---|
- The OCP Director takes the appropriate action to approve the document.
- If Submit is chosen the next step is SAP Hold Step
- If Revise is chosen the next step is Initiator Revise PO Release
| Initiator Revise PO Release Cloak |
---|
- The Initiator Revise PO Release step allows the Process Initiator to make changes and resubmit the process.
- If Resubmit is chosen the next step is MDA Release
- If Void is chosen the next step is Finish and the process is set to a Void status.
| PSA Mail Merge Cloak |
---|
- The PSA Mail Merge step is a mail merge automation step that completes the Standard PSA mail merge document.
- The next step is Project Manager Review
| PSA MM (for A/E man Cloak |
---|
- The PSA MM (for A/E man step is a mail merge automation step that completes the Standard PSA mail merge document to be sent to the A/E Lead or Consultant for a manual signature.
- The next step is PM Attaches Contract
| Project Manager Review Cloak |
---|
- The Project Manager reviews the PSA Details and fills out all required fields.
- If Submit is chosen the next step is Contracts Group Review PSA
- If Revise is chosen the next step is Initiator Revise PSA
| Contracts Group Review PSA Cloak |
---|
- The Contract Admin and Contract Admin Manager review the PSA Details and determine whether or not it meets the requirements for OGC Counsel Review.
- If Reviewed is chosen the next step is Vendor Signs
- If Send to OGC is chosen the next step is OGC Counsel Review
- If Revise is chosen the next step is Initiator Revise PSA
| OGC Counsel Review Cloak |
---|
- The DOF General Counsel reviews the PSA Details.
- If Reviewed is chosen the next step is Vendor Signs
- If Revise is chosen the next step is Contracts Group Review PSA
| Vendor Signs Cloak |
---|
- The Process Initiator takes the appropriate action to sign the document.
- If Submit is chosen the next step is Additional Funding?
- If Revise is chosen the next step is Initiator Revise PSA
| PM Review PSA - Manual Req Cloak |
---|
- The Project Manager fills out all required fields and sends the PSA Document to the Vendor for a manual signature.
- If Submit is chosen the next step is Hold for Signed PSA
- If Revise is chosen the next step is Initiator Revise PSA
- If Void is chosen the next step is Finish and the process is set to a Void status.
| Hold for Signed PSA Cloak |
---|
- The Project Manager and Contract Admin until they receive back the vendor manually signed PSA document and upload it to the process.
- The next step is Additional Funding?
| Additional Funding? Cloak |
---|
- The Additional Funding? Conditional checks if Yes was selected for the Additional Project Funding? field.
- If True (Yes) the next step is Spawn Budget Change (03.03)
- If False (No) the next step is Program Manager Review
| Spawn Budget Change (03.03) Cloak |
---|
- This step spawns a 03.03 - Contingency Request / True-Up Form / Additional Funding Request (BCHNG) process.
- The next step is CRSP Admin Mgr. Hold
| CRSP Admin Mgr. Hold Cloak |
---|
- The CRSP Admin holds the process in this step until additional funding has been applied to the project in both e-Builder and SAP.
- The next step is Program Manager Review
| Program Manager Review Cloak |
---|
- The Program Manager reviews the vendor signed document in the PSA/MDA for Signature field.
- If Submit is chosen the next step is Campus Construction?
- If Revise is chosen the next step is Initiator Revise PSA
| Initiator Revise PSA Cloak |
---|
- The Initiator Revise PSA step allows the Process Initiator to make changes and resubmit the process.
- If Resubmit is chosen the next step is MDA Release
- If Void is chosen the next step is Finish and the process is set to a Void status.
| Campus Construction? Cloak |
---|
- The Campus Construction? Conditional checks if the Program Type of the project is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
- If True (Yes) the next step is SP&T Program?
- If False (No) the next step is OCP?
| OCP? Cloak |
---|
- The OCP? Conditional checks if the Program Type of the project is OCP
- If True (Yes) the next step is EstFinCon> $500K
- If False (No) the next step is CSM?
| CSM? Cloak |
---|
- The CSM? Conditional checks if the Program Type of the project is CSG or R&M
- If True (Yes) the next step is EstFinCon> $5m?
- If False (No) the next step is Utilities Program?
| Utilities Program? Cloak |
---|
- The Utilities Program? Conditional checks if the Program Type of the project is CUP - OPS or Utilities
- If True (Yes) the next step is Est Fin Cont>$1M
- If False (No) the next step is FEG Program
| FEG Program? Cloak |
---|
- The FEG Program? Conditional checks if the Program Type of the project is Energy or SEG
- If True (Yes) the next step is FEG Director Review
- If False (No) the next step is EstFinCon >$1M
| EstFinCon > $1M Cloak |
---|
- The EstFinCon > $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is EstFinCon>$10M
- If False (No) the next step is Dir. Finance Execute
| SP&T Program? Cloak |
---|
- The SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
- If True (Yes) the next step is SPT Director Review
- If False (No) the next step is EstFinCon >$10m
| EstFinCon> $500K Cloak |
---|
- The EstFinCon> $500K Conditional checks if >$500,000<=$1,000,000, >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is OCP Director Review
- If False (No) the next step is OCP Director Execute
| EstFinCon>$5m? Cloak |
---|
- The EstFinCon>$5m? Conditional checks if >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is CSM Director Review
- If False (No) the next step is CSM Director Execute
| Est Fin cont> $1M Cloak |
---|
- The Est Fin cont> $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is Utilities Director Review
- If False (No) the next step is Utilities Director Execute
| SPT Director Review Cloak |
---|
- The SPT Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is EstFinCon>$10M
- If Revise is chosen the next step is Initiator Revise 2
| OCP Director Review Cloak |
---|
- The OCP Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is EstFinCon>$10M
- If Revise is chosen the next step is Initiator Revise 2
| CSM Director Review Cloak |
---|
- The M&U Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is EstFinCon>$10M
- If Revise is chosen the next step is Initiator Revise 2
| FEG Director Review Cloak |
---|
- The SEG Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is EstFinCon>$10M
- If Revise is chosen the next step is Initiator Revise 2
| Utilities Director Review Cloak |
---|
- The Utilities Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is EstFinCon>$10M
- If Revise is chosen the next step is Initiator Revise 2
| Dir. Finance Execute Cloak |
---|
- By taking the Approved action at this step the Director of Finance and Administration is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
- If Send CC Director is chosen the next step is CC Director Review.
| EstFinCon>$10m Cloak |
---|
- The EstFinCon>$10m Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is CC Director Review
- If False (No) the next step is CC Director Execute
| CC Director Review Cloak |
---|
- The CC Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is EstFinCon>10<=100mil
- If Revise is chosen the next step is Initiator Revise 2
| CC Director Execute Cloak |
---|
- By taking the Approved action at this step the CC Director is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
| OCP Director Execute Cloak |
---|
- By taking the Approved action at this step the OCP Director is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
| CSM Director Execute Cloak |
---|
- By taking the Approved action at this step the M&U Director is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
| Utilitites Director Execute Cloak |
---|
- By taking the Approved action at this step the Utilities Director is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
| EstFinCon>$10M Cloak |
---|
- The EstFinCon>$10M Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is Dir of Fin & Adm Review 2.
- If False (No) the next step is Dir of Fin & Adm Review 1.
| Dir of Fin & Adm Review 1 Cloak |
---|
- The Director of Finance and Administration reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is VP, CSS ExecutesExecute.
- If Revise is chosen the next step is Initiator Revise 2.
- If Send CC Director is chosen the next step is CC Director Review.
| Dir of Fin & Adm Review 2 Cloak |
---|
- The Director of Finance and Administration reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is VP, CSS ReviewsReview.
- If Revise is chosen the next step is Initiator Revise 2.
- If Send CC Director is chosen the next step is CC Director Review.
| VP, CSS Review Cloak |
---|
- The VP for Campus Services and Stewardship reviews the Process Details and the appropriate file in the Change Order Document Details section.
- If Submit is chosen the next step is EstFinCon>10<=100mil
- If Revise is chosen the next step is Initiator Revise 2
| VP, CSS Execute Cloak |
---|
- By taking the Approved action at this step the Deputy EVP is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
| EstFinCon>10<=100mil Cloak |
---|
- The EstFinCon>10<=100mil Conditional checks if >$10,000,000<=$100,000,000 was selected for the Estimated Final Contract Amount field.
- If True (Yes) the next step is VP Finance Execute
- If False (No) the next step is EVPT Execute
| VP Finance Execute Cloak |
---|
- By taking the Approved action at this step the VP for Finance is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
| EVPT Execute Cloak |
---|
- By taking the Approved action at this step the EVP&T Office is Approving the process.
- If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
- If Revise is chosen the next step is Initiator Revise 2
| Initiator Revise 2 Cloak |
---|
- The Initiator Revise 2 step allows the Process Initiator to make changes and resubmit the process.
- If Resubmit is chosen the next step is MDA Release
- If Void is chosen the next step is Finish and the process is set to a Void status.
| Amendment SignatureSAP Hold Step Cloak |
---|
- Hold step for SAP Processing.
- Once processed the next step is the PO MM step.
| PO MM Cloak |
---|
- The PO MM step is a mail merge automation step that completes the PSA PO CO MM mail merge document.
- The next step is Project Manager Review
| AA/Contracts Sends Exec-PSA to Vendor Cloak |
---|
- The Administrative Assistant and Contract Admin should review the documents attached to the process, and send the executed documents to the vendor.
- The next step is Finish.
| Finish |
|