This report is filtered to include only invoices paid the previous day that do not have a commitment number on projects where the field e-Builder Only? = Yes. Information is summarized by project. 

Components

This report shows General Invoices from the previous day that are imported to e-Builder as actual costs.

...

 Type of ChargeDefinition
ATime sheet chargesThis is calculated by taking the # of Hours x Billing rate for each workday.
BInvoices against a PO that originated on SAPAny invoice against that PO will be imported into eB as a general invoice from SAP.
CR&M chargesThese are charges from work orders, shut downs, etc.
DAccounting JV’sThese are costs that have moved between GL lines or between projects.

*The cost module shows the actual charges for your project, and can be broken into two simple types.

Sample Image

Image RemovedImage Added

(image taken 5/19/2020)