This process can be started by the Administrative Assistant, CC Director, CC Planner, CC Planning Director, CC Planning Manager, Director of Finance and Administration, eB Admin, Furniture Designer, OCP Planner, Program Manager, Project Coordinator, Project Manager, SPT Commissioning Lead, SPT Lead, VPF Strategic Sourcing,
This process is also started when Send and Initialize is used as the notification option in the 4.0 Bidding Step
Card
label
Process Map
Card
label
Step Descriptions
Note that these step descriptions are in the process of being updated.
Toggle Cloak
Start
Cloak
The Project Coordinator or Project Manager fills out the required fields and executes the Submit action.
The next step is PM Initiate Process?
When asked to identify the type of contract being requested this document may be helpful.
Toggle Cloak
Total $ <= 0?
Cloak
The Total $ <=0? conditional checks if the amount for all commitment items entered is less than or equal to $ 0.
If True (Yes) the next step is Initiator Revise.
If False (No) the next step is PjFnAmt < ComAmt?
Toggle Cloak
PjFnAmt < ComAmt?
Cloak
The PjFnAmt < ComAmt? conditional checks if the Projected Final Contract Amount is less than the amount of the Commitment you are trying to establish.
If True (Yes) the next step is Initiator Revise.
If False (No) the next step is PjFnAmt < ComAmt?
Toggle Cloak
Initiator Revise
Cloak
The Initiator Revise step shares a page layout with the Start step and allows the Process Initiator to make changes and resubmit the process.
When the Initiator takes the Resubmit action the next step is the conditional question PM Initiate Process?
Toggle Cloak
PM Initiate Process?
Cloak
The PM Initiate Process? conditional step determines the path the process will take based on if the data field “Did the PM Initiate the Process?” has been marked “Yes” or "No" in the previous step.
If True (Yes) the next step is Contract Required?
If False (No) the next step is PM Review
Toggle Cloak
Contract Required?
Cloak
The Contract Required? conditional step determines the path the process will take based on if the data field “Contract Required?” has been marked “Yes” or "No" in the previous step.
NOTE: Contract is NOT Required if PO is for Material or Equipment ONLY purchase, Environmental Agreement < $5k, Consulting Agreement < $10k, or Construction Contract < $25k.
If True (Yes) the next step is Contract > $10K?
If False (No) the next step is Purch Req M.M.
Toggle Cloak
Contract >$10K?
Cloak
TheContract >$10K? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$10K) the next step is Vendor Manager Review of SoS.
If False (<=$10K) the next step isPurch Req M.M.
Toggle Cloak
PM Review
Cloak
The PM reviews the process and verifies the Contract or PO being added to the project and chooses the Submit action.
The next step is Contract Required?
Toggle Cloak
Vendor Manager Review of SoS
Cloak
The Vendor Manager reviews the Selection of Source information and confirms the vendor exists in SAP.
If Submit is chosen the next step is Contract Admin Assembles Contract.
If Revise is chosen the next step is Initiator Revise 1.
Toggle Cloak
Contract Admin Assembles Contract
Cloak
The Contract Admin reviews the process and uploads the assembled Contract Document to be executed.
As part of this step the Contract Admin associates a bid process to this PO/Contract process by using the Contract Number Lookup. (Instructions are in included on the process page)
If Submit is chosen the next step is Initiator Reviews Contract.
If Revise is chosen the next step is Initiator Revise 1.
Toggle Cloak
Initiator Reviews Contract
Cloak
The Process Initiator reviews the Contract Document.
If Submit is chosen the next step is CA Manager Reviews.
If Revise is chosen the next step is Contract Admin Assembles Contract.
Toggle Cloak
CA Manager Reviews
Cloak
The DoF Procurement Manager and the Contract Admin Manager reviews the Contract Document and determine whether or not it meets the requirements for OGC Counsel Review.
If Submit is chosen the next step is Contract Admin Releases Contract.
If Revise is chosen the next step is Initiator Revise 1.
If To DOF Counsel is chosen the next step is OGC Counsel Review.
Toggle Cloak
OGC Counsel Review
Cloak
The DOF General Counsel reviews the Contract Document.
If Submit is chosen the next step is Contract Admin Releases Contract.
If Revise is chosen the next step is Initiator Revise 1.
Toggle Cloak
Contract Admin Releases Contract
Cloak
The Contract Admin sends the contract to the vendor for review and signature, and records the date the contract was sent.
If Submit is chosen the Contract Document has been sent to the vendor. The next step is Vendor Executes Contract.
If Revise is chosen the next step is Contact Admin Assembles Contract.
Toggle Cloak
Initiator Revise 1
Cloak
The Initiator Revise1 step allows the Process Initiator to make changes and resubmit the process.
When the Initiator takes the Resubmit action the next step is Vendor Manager review of SoS.
Toggle Cloak
Hold for Vendor Contract Execution
Cloak
The Contract Admin reviews the signed contract received from the vendor, records the date they received the signed contract and then removes and replaces the unsigned contract with the received vendor signed contract into the Contract Document field.
If Submit is chosen the next step is Contract Admin Final Review.
If Revise is chosen the next step is Contract Admin Releases Contract.
Toggle Cloak
Contract Admin Final Review
Cloak
The Contract Admin Manager reviews the vendor signed contract for final review before going to directors steps.
If Submit is chosen the next step is Campus Construction?
If Revise is chosen the next step is Hold for Vendor Contract Execution.
Toggle Cloak
Campus Construction?
Cloak
This conditional routes the process based on what is entered
The next step is Contract <$10M
Toggle Cloak
SPT Program?
Cloak
The Contract <$10M conditional step The Campus Construction? conditional determines the path the process takes will take based on the Current Commitment Value being greater than or less than $10M.
If True (Yes) the next step is CC Director Executes Contract.
the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal.
If True (Yes) the next step is SP&T Program?
If FalseIf False(No) the next step isCC Director Review. OCP?
Toggle Cloak
SPT Director Review
Cloak
The CC Director reviews the process and executes the contact, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Proj. Contract>$10m?
Cloak
The CC Director reviews the process and the contract, then takes the Submit action.
The next step is Contract <$100M.
Toggle Cloak
CC Director Review
Cloak
The OCP? conditional step determines the path the takes based on Program Type or if the contract is managed by a different program.
If True (Yes) the next step is Contract <$500K.
If False (No) the next step is M&U?
Toggle Cloak
CC Director Executes Contract
Cloak
The Contract <$500K conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $500K.
If True (Yes) (<) the next step is OCP Director Executes.
If False (No) (>) the next step is OCP Director Review.
Toggle Cloak
CA Mgr & Dir. Finance
Cloak
The OCP Director reviews the process and executes the contract then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
OCP?
Cloak
The OCP Director reviews the process and contract then takes the Submit action.
The next step is Contract <$100m.
Toggle Cloak
Proj. Contract> $500k?
Program?
Cloak
The SPT Program? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is System Performance & Turn-over.
If True (Yes) the next step is SPT Director Review
If False (No) the next step isProj. Contract>$10m?
Toggle Cloak
SPT Director Review
Cloak
The SPT Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Proj. Contract>$10m?
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
Proj. Contract>$10m?
Cloak
TheProj. Contract>$10m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$10m) the next step is Vendor Manager Review of SoS.
If False (<=$10m) the next step isPurch Req M.M.
Toggle Cloak
CC Director Review
Cloak
The CC Director reviews the Contract Document attached to the process and if required attaches the CC Director Memo.
If Submit is chosen the next step is CA Mgr & Dir. Finance.
If Revise is chosen the next step is Initiator Revise 3.
If Send To OGC is chosen the next step is OGC Counsel Review.
Toggle Cloak
CC Director Executes Contract
Cloak
By taking the Submit action at this step the CC Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3.
Toggle Cloak
CA Mgr & Dir. Finance
Cloak
The Contract Admin Manager and the Director of Finance and Administration review the attached CC Director Memo and upload the Executed Memo to the process.
If Submit is chosen the next step is VP, CSS Reviews
If Revise is chosen the next step is CC Director Review
Toggle Cloak
OCP?
Cloak
The OCP? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is OCP.
If True (Yes) the next step is Proj. Contract> $500k?
If False (No) the next step isCSM?
Toggle Cloak
Proj. Contract> $500k?
Cloak
TheProj. Contract> $500k? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$500K) the next step is CSM Director Executes
If False (<=$500K) the next step is CSM Director Reviews
Toggle Cloak
OCP Director Review
Cloak
The OCP Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Prj Contract > $10mil?
If Revise is chosen the next step is Initiator Revise 3
Cloak
The M & U? Conditional step will determine the path the process takes based on the Program Type or if the contract is managed by a different program
If True (Yes) the next step is Utilities Program.
If False (No) the next steep is Campus Services.
Toggle Cloak
OCP Director ReviewExecute
Cloak
By taking the Submit action at this step the OCP Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3
The Utilities Program? Conditional step will determine the path process takes based on the Program Type or if the contract is managed by a different program.
If True (Yes) the next step is Contract <$100K.
If False (No) the next step is SEG Program.
Toggle Cloak
OCP Director ExecuteCSM?
Cloak
The Contract < $100k conditional The CSM? step determines the path the process takes will take based on the Current Commitment Value being greater than or less than $100k.the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is CSG or R&M.
If TrueIf True(Yes) the next step is Utilities Director Execute.is Proj. Contract>$5m?
If FalseIf False(No) the next step isUtilities Director Review.Program?
Toggle Cloak
CSMProj. Contract>$5m?
Cloak
TheUtilities Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Proj. Contract>$5m?
Proj. Contract>$5m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$5m) the next step is CSM Director Review.
If False (<=$5m) the next step isCSM Director Executes
Cloak
The Utilities Director reviews the process and contract, then takes the Submit action.
The next step is Contract <$5m.
Toggle Cloak
CSM Director Executes
Cloak
By taking the Submit action at this step the O&M Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3
The SEG Program?conditionalstep determines the path the process takes based on the Program Type or if the contract is managed by a different program, Contract Program Type = SEG.
If True (Yes) the next step is Contract <$100k.
If False (No) the next step is Contract <$100k.
Toggle Cloak
CSM Director Review
Cloak
TheContract < $100k conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $100k.
If True (Yes) the next step is O&M Director Execute.
SPT Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Prj Contract > 10mil?
If Revise is chosen the next step is Initiator Revise 3If False (No) the next step is O&M Director Review.
Toggle Cloak
Utilities Program?
Cloak
The Utilities Program? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is CUP - OPS, or Utilities.
If True (Yes) the next step is Contract> $1M.
If False (No) the next step isFEG Program?
The O&M Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Contract> $1M
Cloak
TheProj. Contract>$10m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
If True (>$1m) the next step is Utilities Director Review.
If False (<=$1m) the next step is Utilities Director Executes.
tThe O&M Director reviews the process and contract, then takes the Submit action.
The next step is Contract <$5m
Toggle Cloak
Utilities Director Execute
Cloak
By taking the Submit action at this step the Utilities Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3
The Contract < $100k conditional step determines the path process takes based on the Current Commitment Value being greater than or less than $100k.
If True (Yes) the next step is SEG Director Execute.
If False (No) the next step is SEG Director Review.
Toggle Cloak
Utilities Director Review
Cloak
TheSEG SPT Director reviews the Contract Document attached to the processand executes the contract, then takes the Submit action..
If Submit is chosen the next step is Proj. Contract>$10mil?
If Revise is chosen the next step is Initiator Revise 3The next step is Contract Signature.
Toggle Cloak
FEG Program?
Cloak
The FEG Program? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is Energy, or SEG.
If True (Yes) the next step is FEG Director Review.
If False (No) the next step is VP, CSS Executes
The SEG Director reviews the process and the contract, then takes the Submit action.
The next step is Contract <$100m.
Toggle Cloak
FEG Director Review
Cloak
TheContract < $5m conditional step will determine the path process takes based on the Current Commitment Value being greater than or less than $5m.
If True (Yes) the next step is M&U Director Executes Contract.
FEG Director reviews the Contract Document attached to the process.
If Submit is chosen the next step is Proj. Contract>$10mil?
If Revise is chosen the next step is Initiator Revise 3If False (No) the next step is M&U Director Review.
Toggle Cloak
Prj Contract > 10mil?
Cloak
TheM&U Director reviews the process and executes the contract, then takes the Submit action.Prj. Contract > 10mil? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount
If True (>$10m) the next step is VP, CSS Reviews.
If False (<=$10m) the next step isThe next step is Contract SignatureVP, CSS Executes.
Toggle Cloak
VP, CSS Reviews
Cloak
TheM&U DirectorVP for Campus Services and Stewardshipreviews the process and the contract, then takes the Submit action.Contract Document attached to the process.
If Submit is chosen the next step is Campus Construction?
If Revise is chosen the next step is Initiator Revise 3The next step is Contract <$100m.
Toggle Cloak
CP, CSS Executes
Cloak
By taking the Submit action at this step the CC Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3
The Campus Services? Conditional step determines the path the process takes based on the Program Type or if the contract is managed by a different program, Contract Program Type = Campus Services..
If True (Yes) the next step is Contract <$5m.
If False (No) the next step is Contract <$10m.
Toggle Cloak
>$10mil <$100mil?
Cloak
The
Contract < $5m
Proj. Contract>$10m?conditional step determines the path the process
takes
will take based on the
Current Commitment Value being greater than or less than $5m.If True (Yes
amount entered for the data field Projected Final Contract Amount.
If True (>$10m) the next step
is CS Director Execute
is Vendor Manager Review of SoS.
If
If False(
No
<=$10m) the next step is
CS Director Review
Purch Req M.M.
Toggle Cloak
VP Finance Executes
Cloak
By taking the Submit action at this step the CC Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3
The CS Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
EVPT Executes
Cloak
By taking the Submit action at this step the CC Director is Executing the contract.
If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
If Revise is chosen the next step is Initiator Revise 3
The CS Director reviews the process and the contract, then takes the Submit action.
The next step is Contract < $100m.
Toggle Cloak
Initiator Revise 3
Cloak
The Contract <$10m conditional step determines the path the process takes based on the Current Commitment value being greater than or less than $10m.
If True (Yes) the next step is IBO Director Executes Contract.
If False (No) the next step is IBO Director Reviews Contract.
Toggle Cloak
Contract Signature
Cloak
The IBO Director reviews the process and executes the contract, then takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Purch Req M.M.
Cloak
The IBO Director reviews the process and the contract, then takes the Submit action.
The next step is Contract <100m.
Toggle Cloak
CRSP Admin & Procurement Review
Cloak
The Contract <$100m conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $100m.
If True (Yes) the next step is Deputy EVP Executes Contract.
If False (No) the next step is Deputy EVPT Review.
Toggle Cloak
>$25K?
Cloak
The Deputy EVPT reviews the process, signs the contract and takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
Initiator Revise 2
Cloak
The Deputy EVPT reviews the process and the contract and takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
SAP PO Hold Step
Cloak
The EVPT Office reviews the process and the contract and takes the Submit action.
The next step is Contract Signature.
Toggle Cloak
PO M.M
Cloak
Contract Signature will finalize the director's electronic signatures using DocuSign. Once complete it will automatically take the Code Complete action. (Signifies that e-Builder has completed a task}
The next step is SAP PO/Contract Hold Step.
Toggle Cloak
AA sends Exec. PO\Contract to vendor
Cloak
The Purchase req MM step is a mail merge automation that completes the purchase requisition from the purchase requisition template.
The next step is DoF Procurement Review.
Toggle Cloak
Finish
Cloak
Card
label
Commitment Line Intructions
Enter information for each commitment item.
Item Number - a sequential number denoting each line.
Budget Line Item - Associate each entry with a Budget Line Item.
Current Budget - Displays the current budget.
Description - editable field for a description.
Retainage Percent - enter the retainage percent when applicable.
Amount - the amount of the the commitment line
Allowance Item - Check if it is an allowance item.
Custom Fields - used to enter the cost object.
Pay particulate attention to the Retainage percentage as that determines how retainage is calculated when invoices are submitted.
A Retainage of five percent should be expressed as 5.00 (as in the example)
The following list of items, though part of the budget template, cannot be used to generate a commitment. You cannot place internal charges on a PO.
If you are issuing a PO to cover vendor expenses use the reimbursable line item for that vendor type. For example, for A/E expenses use B-30-125 A/E Reimbursables.
Do Not Use list is below:
A15-005
A15-005 DoF Project Administration
A15-010
A15-010 OCP Project Administration
A15-015
A15-015 Utilities Project Administration
A15-020
A15-020 SEG Project Administration
A15-025
A15-025 EHS Project Administration
A15-035
A15-035 Service and Support-Staff
A15-045
A15-045 Employee Benefit Charges (EB) - General
A20-050
A20-050 Travel Expenses
C50-685
C50-685 Other MIT Internal Charges
C55-730
C55-730 Steam
C55-745
C55-745 Chilled Water
F95-835
F95-835 EVPT Contingency
F96-840
F96-840 DoF Contingency
Card
label
Output - The Purchase Order Document
This process will print a Purchase Order document that can be sent to the vendor.
Purchase Order
This process is used for both signed contracts and purchase orders and it will display the desired document in the AA Sends Exec. PO/Contract to Vendor ... step.
When a contract is displayed the supporting purchase order is still generated. To print the purchase order:
Click the Print button.
Click the Merge Templates radio button.
Choose Purchase Order from the drop down menu.
Click the Print Button on the Mail Merge Templates menu.
Sample Purchase Order Document
PO Mail Merge Field
Notes/Description
Purchase Order Number
The Purchase Order Number in the top right hand corner of the PO (highlighted in yellow on this example) will only appear when the process has progressed through the SAP PO/Contract Hold step. Prior to that step it is possible to preview the Purchase Order, but the PO number will not appear on the form.
Date
The date field is the date that the purchase order mail merge is generated. If you reprint the purchase order the date will update.
Vendor and Vendor Address
The Vendor and vendor addresss information is derived from the Contacts module in e-Builder. If address information is missing from that module the PO fields for this information will be blank. If you update the Contacts information in e-Builder you may reprint the PO and the information will appear as updated.
Ship To
This information is derived from the building information that is part of the e-Builder project information. If room information has been added to e-Builder the room information will also print on the purchase order.
Delivery Date
This information is hardcoded. Each purchase order will have "Per Previous Agreement" in this field. Changing this field requires the assistance of an e-B admin.
Shipping Method
This information is hardcoded. Each purchase order will have "N/A" in this field. Changing this field requires the assistance of an e-B admin.
Shipping Terms
This information is hardcoded. Each purchase order will have "N/A" in this field. Changing this field requires the assistance of an e-B admin.
Payment Terms
This information is hardcoded. Each purchase order will have "Net 30" in this field. Changing this field requires the assistance of an e-B admin.
Items
Each commitment line will use the dollar figure and commitment description for the corresponding commitment in e-Builder. Each line will be sequentially numbered beginning with 001.
Project Number
The project number from e-Builder.
Project Name
The project name from e-Builder. The project name may contain the room number.
Project Contact
The proect contact is derived from Project Manager 1 in e-Builder. The phone number is hard coded and is the general switchboard number for MIT DoF.