This process can be used to generate the Change Order Request (COR). One or more CORs must be included in a General Conract Change Order process in order for commitments (POs) to be changed.

When you change a commitment (PO) you must also ensure that there is sufficient budget to cover the total of the changes.

Card
labelProcess Map

Card
labelStep Descriptions

Toggle Cloak
1. Start/Initiation

Cloak
  • Started by the Contractor or the Project Manager.

 

 

 

Step No.Step NameDescription
1Is this a user data entry ERROR fix ONLY?Please only select yes if you are using this process to fix a user data entry error that occurred while entering the original Commitment (Purchase Order schedule of values).
2Is this Change Request for a Purchase Order Only (NO Contract)?ONLY select yes if this change request is to a Purchase Order and there is no Contract for the Vendor. If the aggregate of the changes and original PO meet the thresholds for a Contract then the Issue Contract process will need to be started.
3Ready for Owner ActionIf the COR is ready for processing as part of a GCCO indicate by answering Yes.
4A/E on ProjectIf an A/E is on the project indicate by answering Yes.
5Brief Description of ChangeEnter a description of the change.
6Time Extension Requested (in Days)Indicate the time extension that is required for this GCO. You may indicate 0 if there is no impact to the schedule.
7Vendor's Supporting DocumentationAdd any documentation that supports the change request.
8CommitmentYou must select the commitment (PO) that is being changed. When the commitment is selected the process will display the commitment lines and allow for changes.
9Date of ChangeIndicate the date of the change.
10Reason CodeIndicate the reason for the change.
11Justification for the ChangeIndicate the justification for the change.
12Add All Existing ItemsImports the schedule of values for the chosen commitment.
13Edit the Change AmountEdit the change amounts for each Commitment line item you want to modify
14Add Additional Scope Commitment Item

Select the Cost Object for any new Scope Commitment Items you would like to add

15Select a Cost Object

Select a Cost Object


The next step is Data Entry Error?

Toggle Cloak
2. Data Entry Error?

Cloak
  • The Data Entry Error? conditional step determines the path process will take based on if the Data FieldIs this a user data entry ERROR fix ONLY?” has been marked “Yes” or "No" in the previous step.
  • If True (Yes) the next step is eB Admin Review.
  • If False (No) the next step is PO CO ONLY?

Toggle Cloak
3. PO CO ONLY?

Cloak
  • The PO CO ONLY? conditional step determines the path process will take based on if the Data FieldIs this Change Request for a Purchase Order Only (NO Contract)?” has been marked “Yes” or "No" in the previous step.
  • If True (Yes) the next step is Pm Enters Data.
  • If False (No) the next step is COR AMT <0>?

Toggle Cloak
4. Pm Enters Data

Cloak
 

 

Toggle Cloak
4. COR AMT <0>?

Cloak
  • The COR AMT <0>? conditional step determines if the data field Commitment Change Amount is a non-zero amount
  • If True (Yes) the next step is Ready for Owner?
  • If False (No) the next step is Comm Chng Items Mssng / Zero

Toggle Cloak
5. A/E Review

Cloak
  • A/E Lead reviews the process and takes the Submit action.
  • The next step is PM Approves/Rejects & Verifies Funding.

Toggle Cloak
6.Initiator Revise & Resubmit

Cloak
  • The initiator reviews the process, fills out the required fields and takes the Resubmit option.
  • The next step is Letter of Release?

Toggle Cloak
7. PM Approves/Rejects & Verifies Funding

Cloak
  • The Project Manager Reviews the process, verifies the available funding, and has the option to Submit, Revise, Reject, or Void.
  • If Submit is chosen the next step is Budget Change Required.
  • If Revise is chosen the next step is A/E Review.
  • If Reject is chosen the next step is Initiator Revise and Resubmit.
  • If Void is chosen the next step is Finish.

Toggle Cloak
8. Budget Change Req'd

Cloak
  • The Budget Change Req’d? conditional step determines the path process takes based on if the Data Field “Budget Change” has been marked “Yes” in a previous step.
  • If True (Yes) the next step is Program Manager Review and Approval.
  • If False (No) the next step is COR Hold for GC-CO.

Toggle Cloak
9. Program Manager Review and Approval

Cloak
  • The Program Manager reviews the process and takes an action to Void, Submit, or Revise.
  • If Void is chosen the next step is Finish.
  • If Submit is chosen the next step is COR Hold for GC
  • If Revise is chosen the next step is PM Approves/Rejects &  Verifies Funding

Toggle Cloak
10. COR Hold for GC-CO

Cloak

The COR Hold for GC-CO Step will hold all Change Order Requests until they are bundled with the Change Order Process and the process is approved.  Once the Change Order process is approved the attached Change Order Request Processes will automatically take the Code Complete action.

The next step is SAP Hold Step.

Toggle Cloak
11. SAP Hold Step

Cloak
  • Hold step for SAP Processing.
  • The next step is Finish.

12. Finish