1. Start/Initiation Cloak |
---|
- Started by the Contractor or the Project Manager.
Step No. | Step Name | Description |
---|
1 | Brief Description of Change | Enter a description of the change. | 2 | Ready for Owner Action | If the COR is ready for processing as part of a GCCO indicate by answering Yes. | 3 | A/E on Project | If an A/E is on the project indicate by answering Yes. | 4 | Time Extension Requested (in Days) | Indicate the time extension that is required for this GCO. You may indicate 0 if there is no impact to the schedule. | 5 | Vendor's Supporting Documentation | Add any documentation that supports the change request. | 6 | Commitment | You must select the commitment (PO) that is being changed. When the commitment is selected the process will display the commitment lines and allow for changes. | 7 | Date of Change | Indicate the date of the change. | 8 | Reason Code | Indicate the reason for the change. | 9 | Justification for the Change | Indicate the justification for the change. |
The next step is Ready for Owner?
| 2. Ready for Owner? Cloak |
---|
- The Ready for Owner? conditional step determines the path process will take based on if the Data Field “Ready for Owner Action?” has been marked “Yes” in a previous step.
- If True (Yes) the next step is Letter of Release?
- If False (No) the next step is Initiator Hold.
| 3. Initiator Hold Cloak |
---|
- The process initiator completes the Change Order Request and takes the Submit action.
- The next step is Letter of Release?
| 4. Letter of Release? Cloak |
---|
- The Letter of Release? conditional step determines the path process will take based on if the Data Field “Requesting Letter of Release?” has been marked “Yes” in a previous step.
- If True (Yes) the next step is PM Approves/Rejects & Verifies Funding.
- If False (No) the next step is A/E Review.
| 5. A/E Review Cloak |
---|
- A/E Lead reviews the process and takes the Submit action.
- The next step is PM Approves/Rejects & Verifies Funding.
| 6.Initiator Revise & Resubmit Cloak |
---|
- The initiator reviews the process, fills out the required fields and takes the Resubmit option.
- The next step is Letter of Release?
|
7. PM Approves/Rejects & Verifies Funding Cloak |
---|
- The Project Manager Reviews the process, verifies the available funding, and has the option to Submit, Revise, Reject, or Void.
- If Submit is chosen the next step is Budget Change Required.
- If Revise is chosen the next step is A/E Review.
- If Reject is chosen the next step is Initiator Revise and Resubmit.
- If Void is chosen the next step is Finish.
|
8. Budget Change Req'd Cloak |
---|
- The Budget Change Req’d? conditional step determines the path process takes based on if the Data Field “Budget Change” has been marked “Yes” in a previous step.
- If True (Yes) the next step is Program Manager Review and Approval.
- If False (No) the next step is COR Hold for GC-CO.
|
9. Program Manager Review and Approval Cloak |
---|
- The Program Manager reviews the process and takes an action to Void, Submit, or Revise.
- If Void is chosen the next step is Finish.
- If Submit is chosen the next step is COR Hold for GC
- If Revise is chosen the next step is PM Approves/Rejects & Verifies Funding
|
10. COR Hold for GC-CO Cloak |
---|
The COR Hold for GC-CO Step will hold all Change Order Requests until they are bundled with the Change Order Process and the process is approved. Once the Change Order process is approved the attached Change Order Request Processes will automatically take the Code Complete action. The next step is SAP Hold Step. |
11. SAP Hold Step Cloak |
---|
- Hold step for SAP Processing.
- The next step is Finish.
|
12. Finish
|