Design fin can Approx. Time Required# People RequiredNotes
Fin Design & Manufacturing36 hoursThe more the merrier.Manufacturing procedure and detailed breakdown described in "Hermes 2 Fin Design & Manufacturing"
Design/make jigs
   
Root bond jig 3 Allow for tolerance so fins fit, but don't make slots too loose. Make sure you have a top plate.
Fillet jig 3  
Tube preparation
   
Sand tube 2 Sand inside with flapper wheel so that it fits over the motor case
Tube layup 62-4Rough up the outside of the tube before layup.
Root bond 1 5-minute is ok, but if you have time, use a stronger epoxy.
Root fillets   

Need 4 sets of fillets but it takes 8 rounds cause you gotta do the ends of each side separately (read below for more detail).

You'll have to backtrack from when you want to do the layup to when each fillet has to be done by (can speed up using heat gun)

Layup preparation
   
Laser-cut CF cutouts   
Spray-glue to wax paper   
Sand fillets   
Prep vacuum materials   
Layup   
Wet plies/weight   
Layup   
Put on vacuum bagging   
Vacuuming   
Oven Cure   
Set up oven/vacuum materials   
Follow epoxy cure cycle   
Remove vacuum materials   
Clean up edges   
Static load test   
Design/build jig   
Determine testing loads   
Static load test   
Analyze data   
Post-processing   
Sand fillets/outside   
Outer fillets on low spots   
Paint   
Total manufacturing time   

...