This process replaces the 3.01 Milestone Project Estimate and Budget request process and the budget template/Excel spreadsheet.

All projects will now have a budget template added when the project is created. Users will run the 03.01a Project Budget Request process to create the project budget. All work is done within the process, no external document is required.

Once the budget is created the process is routed for approval depending on project type.

This process also results in the assignment of a cost object to the project.

Card
labelProcess Map

Card
labelPM Instructions for - Creating a Budget

These are general instrucitons

Column

  This is column 1

Column

  This is column 2

Card
labelStep Descriptions

Toggle Cloak
1. Initiation by Project Manager

Cloak
  • Based on how the process is started a conditional is evaluated to determine if the project manager needs to complete their fields.

Toggle Cloak
2. Started by Spawn

Cloak
  • The Started by Spawn? conditional determines if the process was spawned.
  • If the conditional is True the next step is Project Manager Submit Estimate.
  • If the conditional is False the next step is Program Manager Review.

Toggle Cloak
3. Project Manager Estimate

Cloak
  • The project manager navigates to the Estimate Worksheet, clicks Edit, completes the spreadsheet, and then checks the edited spreadsheet back into e-Builder.
  • The project manager attaches the newly edited spreadsheet to the process, completes the form by selecting from the Create Budget Type and Estimate Type dropdown menus and by indicating that the project schedule has been updated if necessary and also indicates if the review includes a funding request.
  • Once the form is completed and ready to be reviewed the project manager clicks Submit.
  • Next Step: Program Manager Review

Toggle Cloak
4. Program Manager Review

Cloak
  • The Program Manager reviews the process and adds comments if necessary. The program manager can download the estimate worksheet, make changes and then upload. This will result in a separate document from the one submitted by the PM.
  • The program manager has the option of either submitting or asking for revisions.
  • If the program manager clicks Submit a series of decisions is evaluated to determine routing to one of the CC Director and Director of Projects, M&U Director, OCP Director, Campus Services Director or IBO Director.
  • If the program manager clicks Revise the next step is Initiator Revise and Resubmit

Toggle Cloak
5. Initiator Revise and Resubmit

Cloak
  • The process initiator reads the comments and fills out the required fields and has the option to Resubmit or Void.
  • If the initiator chooses Resubmit the next step is Program Manager Review
  • If the initiator chooses Void the next step is Finish

Toggle Cloak
6. CC Director and Director of Projects or M&U Director or OCP Director or Campus Services Director or IBO Director Review

Cloak
  • One of the above reviews the process and takes an action to Submit or to Revise
  • If Submitis chosen the process passes through several decision steps to determine if it contains a funding request and if it is a capital or academic project
    • If the process is determined to be for a capital project the next step is Governance Review.
    • If the process is determined to be for an academic project the next step is CRSP Admin Distributes
    • If the process is determined not to be for Capital or Academic the next step is R-CRSP Committee Review/Approval.
  • If Revise is chosen the next step is Initiator Revise and Resubmit.

Toggle Cloak
7. Funding Request? (Conditional)

Cloak
  • The funding request step is a conditional that determines if additional funding is needed with the budget request by evaluating the "Does this review include a request for funding" field.
  • If True (Yes) the next step is Capital Project? (F)
  • If False (No) the next step is Capital Project?

Toggle Cloak
8.  Capital Project? (F) (Conditional)

Cloak

The capital project (F) conditional determines if the Program type equals Capital Group based on the Project Custom Field "Program Type" entry being Capital Group.

  • If True the next step is Governance Review
  • If False the next step is Provost Review.

Toggle Cloak
9. Capital Project? (Conditional)

Cloak
  • The Capital Project? Conditional determines if the program type equals Capital Group based on the Project Custom Field "Program Type".
  • If True the next step is  Cost Object Assigned.
  • If False the next step is CRSP Admin Distributes

Toggle Cloak
10. CRSP Admin Distributes

Cloak
  • The CRSP Admin reviews the process and distributes to Associate Provost, DLC & School and has the option of sending to RCRSP or Put on Hold.
  • If RCRSP is chosen the next step is R-CRSP Committee Review / Approval
  • If Put on Hold is chosen the next step is Project on Hold

Toggle Cloak
11. R-CRSP Committee Review Approval

Cloak
  • The CRSP Admin reviews the process, completes the required fields and has the option to Approve, Revise or Reject
  • If Approve is selected the next step is Financial Officeer Office Obtain Cost Objects.
  • If Revise is selected the next step is CRSP Admin Distributes.
  • If Reject is selected the next step is Finish.

Toggle Cloak
12. Governance Review

Cloak
  • The CRSP Admin reviews the process, completes the required fields and has the option to Approve, Put On Hold, or Revise.
  • If Approve is selected the next step is Cost Object Assigned?
  • If Put On Hold is selected the next step is Project On Hold
  • If Revise is selected the next step is Initiator Revise and Resubmit

Toggle Cloak
13. Project On Hold

Cloak
  • The e-B Admin reviews the process, completes the required fields and clicks Submit
  • The next step is Governance Review

Toggle Cloak
14. Cost Object Assigned?

Cloak
  • This step determines if a cost object is assigned to the process
  • If True (no) the next step is Financial Officer Obtain Cost Object
  • If False (yes) the next step is Financial Analyst Imports Data

Toggle Cloak
15. Financial Officer Obtain Cost Object

Cloak
  • The Financial Officer obtains the cost object number, updates the process and takes the Receive action.
  • The next step is Finish

 

Toggle Cloak
16. Financial Analyst Imports Data

Cloak
  • The Financial Analyst imports data, applies funding (as needed) and clicks Submit
  • The next step is Finish

Toggle Cloak
17. Finish

...