This process is used to submit pay requisitions and invoices. It can started by the A/E Lead, Consultant or Contractor. It can also be initiated by the Administrative Assistant when the A/E, Consultant or Contractor is unable to do so.

This process integrates with SAP. The process includes a step to ensure that invoice numbers submitted by vendors comply with SAP requirements. (11 alphanumeric characters are allowed)

Card
labelProcess Map
 
Card
labelStep Descriptions

Toggle Cloak
1. Start

Cloak
  • The process is started by the A/E Lead, Administrative Assistant, Contractor or Consultant who fills out the required fields and attaches the associated documents before taking the Submit action.
  • The next step is Final Invoice?.

Toggle Cloak
2. Valid Invoice Number#?

Cloak

The invoice number is checked evaluated to ensure that it complies with SAP requirements.

  • If True (Compliant) the next step is Final Invoice?
  • If False (Not compliant) the next step is Fix Invoice Number.

Toggle Cloak
3.

 

Fix Invoice Number

Cloak

If the invoice number is not compliant the Project Manager or eB Admin must modify the invoice number in this step.

The next step is Valid Invoice Number?

Toggle Cloak
24. Final Invoice?

Cloak
  • This is a decision step to determine if the final invoice is being processed. (The If it is the final invoice is handled differently than others)
  • If True the next step is Contractor or CM?
  • If False the next step is Contractor or CM?

Note: Though the next steps share a common name they are on separate processing paths. See the process map for clarity.

Toggle Cloak
3. Contractor or CM (Final Invoice True)

Cloak
  • This step determines if A/E Review is Yes.
  • If True the next step is A/E Review Final.
  • If False the next step is PM Reviews Final.
  • the project manager is prompted with a list of requirements with which the vendor should comply before the invoice is processed. Both the final invoice and not final invoice paths have the same steps taken by the same actors.
  • The next step is Requires A/E Review?

Toggle Cloak
3. Requires A/E Review?
Toggle Cloak
4. Contractor or CM (Final Invoice False)

Cloak
  • This step determines if A/E Review is Yesrequired.
  • If True (required) the next step is A/E Review Final.
  • If False (A/E review not required) the next step is PM ReviewReviews Final.


Toggle Cloak
5. A/E Review Final

Cloak
  • The A/E Lead reads the comments and reviews the process fields and has the option to take the Submit or Don't Sign action.
  • If Submit is chosen the next step is PM Reviews Final.
  • If Don't Sign is chosen the next step is PM Reviews Final.

Toggle Cloak
6. Initiator Submit and Revise

Cloak
  • The Process Initiator reads the comments and reviews the process fields and updates as necessary and has the option to take the Resubmit or Void action.
  • If Resubmit is chosen the next step is Final Invoice?
  • If Void is chosen the next step is Finish.A/E

Toggle Cloak
7. PM Reviews Final

Cloak
  • The Project Manager reads the comments and reviews the process fields and has the option to take an action to Approve, Reject or Void.
  • If Approve is chosen the next step is Waiting for Payment.
  • If Reject is chosen the next step is Initiator Revise and Resubmit.
  • If Void is chosen the next step is Finish.

Toggle Cloak
8. A/E Review

Cloak
  • The A/E Lead reads the comments and reviews the process fields and has the option to take an action to Submit or Don't Sign.
  • If Submit is chosen the next step is PM Review.
  • If Don't Sign is chosen the next step is PM Review.

Toggle Cloak
9. PM Review

Cloak
  • The Project Manager reads the comments and reviews the process fields and has the option to take an action to Approve or Reject or Void.
  • If Approve is chosen the next step is Waiting for Payment.
  • If Reject is chosen the next step is Initiator Revise & Resubmit.
  • If Void is chosen the next step is Finish.

Toggle Cloak
10. Waiting for Payment

Cloak
  • The process will hold for the SAP integration to automatically update the process once payment has been made. The automation will cause the Paid action.
  • The next step is Finish.

11. Finish