SPRINT CYCLE - 6 weeks

  • Design: 1 Week
    • Sprint Planning happens at the beginning of this week
      • Available the thursday BEFORE sprint planning, Product Owner will produce Theme for sprint, and prioritized list of issues for review
    • Design meetings for any changes/new features that involve redesign. Only the key stakeholders for the given issue need attend. Out of that meeting should come a spec that QA can then use to write test plans from.

...

  • QA should review all issues in the Triage queue before the meeting.
    • Note: Suggest developers wait and review Triage list right before the meeting or save time and just listen at the meeting.
  • QA should run the Triage meeting.
  • QA person should take notes; it's helpful to have a printed issues list.
  • Triage meeting should run as:
    • QA person reads the issue number, the title and a brief description of the problem if needed - just enough info until the issue is understood.
    • Discuss if issue is related to another issue, a dupe, ask questions, request additional testing if needed, etc.
    • Team should:
      • Understand the issue to make sure change makes sense.
      • Think about possible ramifications of the requested change.
      • Make sure noted bug issue is really a bug (and not expected behavior).
    • Make issue decisions:
      • To be part of the current Sprint or which bucket it gets added to?
      • Assign resource.
      • If additional testing is needed, the issue could be reviewed again at the next Triage meeting or decided now.
  • QA should should update Triage issues soon after the meeting.
    • Assign resource, Fix Version bucket, etc.
    • Include any relevant notes, link issue, etc.
    • Updates should include a comment to detail what's being changed, i.e.: Changing to Robin, Codfish as per Triage meeting 12/21/07.

ROLES:Project Manager:

  • Tracking status
  • "The accountability piece": main artifact is the Burn-down chart
  • Red flags (ie: people are going beyond what they estimated, totals add up to more time than is allotted, etc) should be raised to Janet
  • Coordinate Biz issues
  • Include PM tasks in the chart, with estimates and dates
  • Collect information off-line, not in meetings

Product Owner - responsible for vision/priorities:

...

  • Estimates of tasks
  • Reporting exceptions in the scrum: task is taking longer than is expected, etc
  • Manage own bug queue
  • Do feature work, then bugs - we need to assign these in appropriate size chunks, so this is possible within a given sprint

...