Risk | Contingency |
QA environment not available | Utilize development or production environment |
Insufficient time to fully test the Touchstone application with all major web browsers | Execute ~80% of application functionality with MIT's standard browser (Mozilla Firefox 2.0) and ~20% of the functionality with other browsers. |
Test time increases due to changes in scope requiring additional test analysis and/or test case creation | If test time cannot be increased, reduce/cut overlap in multi-browser testing and execute highest priority test cases initially followed by lower priority tests until test time runs out. |
Excessive defect rate or defect correction time | Execute test cases in unrelated/unblocked functional areas of the application based on designated priority |
Use cases not complete or available | Parts of the application will not be tested, or Questcon will require additional time to assist MIT in authoring the necessary use cases. |
Server or client hardware or software specifications not available | Assumptions will be made which may be incorrect. This may lead to inaccurate testing and possible missed defects in the production system. |
...
The following table outlines the various types of testing considered for this test effort, any additional comments about the testing, and the individual or group responsible for completing the testing.
Type of Testing | Included | Comments | Team Responsible |
Automation | N | MIT personnel will utilize jMeter to automate portions of the backend testing; no test automation tools will be used for the UI testing (use of Flash prevents this). | N/A |
Conversion | N | There is no pre-existing system; therefore no data conversion is necessary. | N/A |
Exploratory | Y | Some level of exploratory testing will be conducted based on heuristics related to typical rich-content internet applications. | Questcon |
Functional | Y | Functional testing will be performed based on test cases derived on the documented use cases and front-end functional design. | Questcon |
Installation / Upgrade | N | Because this is a web application no installation testing is necessary. | N/A |
Integration | Y | Some integration testing will naturally occur as the front-end of the Touchstone application interfaces with and utilizes the back-end APIs. | Questcon |
Parallel | N | There is no existing system that Touchstone is replacing. | N/A |
Performance | N | Performance testing is coved by a separate Test Plan. | N/A |
Regression | Y | Questcon expects to run at least a minimum regression test set prior to release to production. | Questcon |
Security | Y | Backend security testing will be done by MIT. Questcon will execute basic security/login testing on the front-end | MIT - Tester (backend) |
UAT | Y | The user community will be tasked with performing ad-hoc user acceptance testing, domain specific metadata testing (metadata titles, tag lists, etc.), as well as previously designated documented functional test cases for multiple browser/OS configurations (primarily Safari or Firefox/Mac configurations). | MIT - User Community |
Unit | Y | Questcon expects the MIT developers to perform unit testing prior to releasing code to the test environment. | MIT - Developers |
...
Key Deliverables | Description | Expected Delivery Date | Resource |
Test Plan | This document. | After all needed data is delivered | Questcon |
Test Case Designs | List of objectives and priorities of the tests. | 4 business days after test plan is approved and necessary information and environmental needs met. | Questcon or MIT designated resource |
Test Cases | Steps and expected results. | 6 business days after test case design completeion. | Questcon or MIT designated resource |
Status Reports | Accomplishments, issues and plans. | Weekly | Questcon or MIT designated resource |
Test Logs | Run logs Test execution data that indicates test run status, number of test runs and test metrics summaries. | Ongoing during test execution | Questcon or MIT designated resource |
Defect Reports | Entered in Jira as they are discovered. | Ongoing during test execution | Questcon or MIT designated resource |
Test Summary Report | Details the results of the testing effort. | 2 business days after test execution is completed. | Questcon or MIT designated resource |
...
Milestone | Target Timeframe | Summation of Activities |
Develop test strategy / plan | 01/15/2008 - 02/05/2008 |
|
Review test plan | 02/05/2008 - 02/11/2008 |
|
Perform test analysis | //2008 - //2008 |
|
Review test case design | //2008 - //2008 |
|
Build functional test cases / scenarios | //2008 - //2008 |
|
Setup test environment | //2008 - //2008 |
|
Setup test data | //2008 - //2008 |
|
Execute functional & exploratory tests | //2008 - //2008 |
|
Investigate / correct defects | //2008 - //2008 |
|
Execute regression tests | //2008 - //2008 |
|
Execute UAT | //2008 - //2008 |
|
Create test summary | //2008 - //2008 |
|
Total: | 65 business days | _ ** This estimate could change depending on the actual number of test cases, complexity of test cases, or items we are not aware of at this time._ |