Hardware | O/S | Other |
TBD | TBD |
|
This information is an assumption and will be updated when MIT specifies what their production server configuration will be.
3.3.2 IdPi Server Configuration
Hardware | O/S | Other |
TBD | TBD |
|
This information is an assumption and will be updated when MIT specifies what their production server configuration will be.
3.3.4 Client Configuration
Hardware | O/S | Other |
PC | Windows XP Professional SP 2 |
|
Macintosh PowerPC | Mac OS X |
|
This information is an assumption and will be updated when MIT specifies what their desired client configuration will be for the purposes of this testing phase.
4.0 Schedule of Deliverables and Resources
...
Key Deliverables | Description | Expected Delivery Date | Resource |
Test Plan | This document. | After all needed data is delivered | Questcon |
Test Case Designs | List of objectives and priorities of the tests. | 4 business days after test plan is approved and necessary information and environmental needs met. | TBD Questcon or MIT designated resource |
Test Cases | Steps and expected results. | 6 business days after test case design completeion. | TBD Questcon or MIT designated resource |
Status Reports | Accomplishments, issues and plans. | Weekly TBD | Questcon or MIT designated resource |
Test Logs | Run logs. | Ongoing during test execution TBD | Questcon or MIT designated resource |
Defect Reports | Entered in Jira as they are discovered. | Ongoing during test execution TBD | Questcon or MIT designated resource |
Test Summary Report | Details the results of the testing effort. | 2 business days after test execution is completed. | TBD Questcon or MIT designated resource |
4.2 Test Schedule
The planned test schedule of the Touchstone project does not has an anticipated start date of //2008 and or completion date of //2008. The estimated completion date is based on set yet. All dates are subject to several assumptions, some of which have been identified in 2.3 Risks & Contingencies.
...