Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

The objective of this scenario is to stress only the internal IDP. We plan to push it gradually up to its breaking point and then beyond to determine how and at what load it fails.

5.

...

2.3.1 Load Model

Desired Transaction Rate: OPEN

...

The objective of this scenario is to stress only the external IDP. We plan to push it gradually up to its breaking point and then beyond to determine how and at what load it fails.

5.

...

2.3.1 Load Model

Desired Transaction Rate: OPEN

...

The objective of this scenario is to stress both IdPs concurrently. We plan to push it gradually up to its breaking point and then beyond to determine how and at what load it fails.

5.

...

2.3.1 Load Model

Desired Transaction Rate: OPEN

...

Key Deliverables

Description

Expected Delivery Date

Resource

Performance Test Plan

This document.

After all non-functional requirements and other needed data is delivered

Questcon

Performance Test Scripts

Automated scripts used to deliver load.

36 30 business days after test plan finalization and environmental needs are met.
(3 2.5 days for each script)

Questcon

Performance Test Scenarios

Automated execution designs used to conduct performance tests.

5 business days after scripts are developed.
(1 day ~.75 days for each scenario)

Questcon

Status Reports

Accomplishments, issues and plans.

Weekly

Questcon

Defect Reports

Entered in Jira as they are discovered.

Ongoing during test execution

Questcon

Performance Test Summary Report

Details the results of the testing effort.

3 business days after the last performance test is completed.

Questcon

...

9.2 Test Schedule

The planned test schedule of the Touchstone project has an anticipated start date of //2008 and completion date of //2008. The estimated completion date is based on several assumptions, some of which have been identified in 2.3 Risks & Contingencies.

Milestone

Target Timeframe

Summation of Activities

Develop performance test plan

01/15/2008 - 02/05/2008
15 Business Days 

  • Analyze existing design documents, notes, and other available materials
  • Develop test plan document

Review performance test plan

02/05/2008 - 02/11/2008
3 Business Days

  • Review, clarify, correct, and update the test plan
  • Client approval of test plan

Build Performance test scripts

//2008 - //2008
30 Business Days

  • Author test scripts in automated tool

Build Performance test scenarios

//2008 - //2008
5 Business Days

  • Setup web server and database server
  • Load application under test
  • Setup logins and authorizations

Setup test data

//2008 - //2008
1 Business Day

  • Review & analyze test cases to target data to load in test environment
  • Load initial test data set

Execute performance tests

//2008 - //2008
10 Business Days

  • Execute documented performance test scenarios
  • Communicate with the development team when issues are found
  • Maintain a test run log
  • Track test metrics

Create test summary

//2008 - //2008
3 Business Days

  • Create and deliver a test summary report to include:
    • Summation of planned/actual test activities
    • Deviation from planned activities
    • Summary of defects (open defects)
    • Summary of test metrics

TOTAL:

73 Business Days