This test plan is intended to prescribe the scope, approach, types of performance testing, resources and high-level schedule of the testing activities to be performed in the Touchstone project. This plan will identify the use cases, data, and related systems to be included in the testing process.

1.0 Document identifiers

1.1 Document Author

The document author is:

Author

Title

Telephone

Email Address

Will Smithee

Senior Practice Manager

336-232-5208

will_smithee@questcon.com

1.2 Document Revisions

Issue

Date

Author

Reason for Change

0.1

01/27/2008

Will Smithee

Initial draft

 

 

 

 

1.3 References

The following documents were used as sources of information for this test plan:

...