The planned test schedule of the Touchstone project has an anticipated start date of 04/25/2007 and completion date of 07/17/2007.  The estimated completion date is based on several assumptions, some of which have been identified in 2.3 Risks & Contingencies

Milestone

Target Timeframe

Summation of Activities

Develop test strategy / plan

04/25/2007 2008 - 05/07/2007 2008

        
  • Analyze existing design documents, notes, and other available materials

...

  • Develop test plan document

...


Review test plan

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Review, clarify, correct, and update the test plan

Perform test analysis

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Develop FTT

...

  • Develop test case design document

...

Review FTT & test case design

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  •  Review, clarify, correct, and update the test case design

Build functional test cases / scenarios

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Combine test objectives into test cases

...

  • Document data, procedures, and results

...

  • Prioritize test cases

...

  • Determine which test cases will be executed in different browser/OS configurations

...

Setup test environment

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Setup web server and database server

...

  • Load application under test

...

  • Setup logins and authorizations

...

Setup test data

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Review & analyze test cases to target data to load in test environment

...

  • Load initial test data set

...

Execute functional & exploratory tests

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Execute documented test cases, as well as exploratory tests

...

  • Communicate with the development team when issues are found

...

  • Maintain a test run log

...

  • Track test metrics

...

Investigate / correct defects

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Investigate and validate that a defect has been found

...

  • Log defects in Jira

...

  • Work with the development team, as necessary, to identify the cause of the defect

...

  • Accept and retest defect corrections from the development team

...



Execute regression tests

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Execute a prioritized subset of test cases as regression of the system once all functional and exploratory testing is complete

...

  • Validate that no new errors have been introduced as a result of correcting known defects or configuration management / version control issues

...

  • Investigate and validate that a defect has been found

...

  • Log defects in Jira

...

  • Work with the development team, as necessary, to identify the cause of the defect

...

  • Accept and retest defect corrections from the development team

...

Execute UAT

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Work with the user community to identify and manage the execution of user acceptance tests

...

  • Communicate with the development team when issues are found

...

  • Investigate and validate that a defect has been found

...

  • Log defects in Jira

...

  • Work with the development team, as necessary, to identify the cause of the defect

...

  • Accept and retest defect corrections from the development team

...

Create test summary

...

/

...

/

...

2008 -

...

/

...

/

...

2008

...

  • Create and deliver a test summary report to include:

    ...

      • Summation of planned/actual test activities

    ...

      • Deviation from planned activities

    ...

      • Summary of defects (open defects)

    ...

      • Summary of test metrics