The planned test schedule of the Touchstone project has an anticipated start date of 04/25/2007 and completion date of 07/17/2007. The estimated completion date is based on several assumptions, some of which have been identified in 2.3 Risks & Contingencies.
Milestone | Target Timeframe | Summation of Activities |
Develop test strategy / plan | 04/25/2007 2008 - 05/07/2007 2008 | - Analyze existing design documents, notes, and other available materials
|
...
- Develop test plan document
|
...
...
...
...
...
...
...
...
- Review, clarify, correct, and update the test plan
|
Perform test analysis |
...
...
...
...
...
...
...
...
- Develop test case design document
|
...
|
Review FTT & test case design |
...
...
...
...
...
...
...
- Review, clarify, correct, and update the test case design
|
Build functional test cases / scenarios |
...
...
...
...
...
...
...
- Combine test objectives into test cases
|
...
- Document data, procedures, and results
|
...
...
- Determine which test cases will be executed in different browser/OS configurations
|
...
...
...
...
...
...
...
...
- Setup web server and database server
|
...
- Load application under test
|
...
- Setup logins and authorizations
|
...
...
...
...
...
...
...
...
- Review & analyze test cases to target data to load in test environment
|
...
- Load initial test data set
|
...
|
Execute functional & exploratory tests |
...
...
...
...
...
...
...
- Execute documented test cases, as well as exploratory tests
|
...
- Communicate with the development team when issues are found
|
...
...
...
|
Investigate / correct defects |
...
...
...
...
...
...
...
- Investigate and validate that a defect has been found
|
...
...
- Work with the development team, as necessary, to identify the cause of the defect
|
...
- Accept and retest defect corrections from the development team
|
...
...
...
...
...
...
...
...
- Execute a prioritized subset of test cases as regression of the system once all functional and exploratory testing is complete
|
...
- Validate that no new errors have been introduced as a result of correcting known defects or configuration management / version control issues
|
...
- Investigate and validate that a defect has been found
|
...
...
- Work with the development team, as necessary, to identify the cause of the defect
|
...
- Accept and retest defect corrections from the development team
|
...
...
...
...
...
...
...
...
- Work with the user community to identify and manage the execution of user acceptance tests
|
...
- Communicate with the development team when issues are found
|
...
- Investigate and validate that a defect has been found
|
...
...
- Work with the development team, as necessary, to identify the cause of the defect
|
...
- Accept and retest defect corrections from the development team
|
...
...
...
...
...
...
...
...
- Create and deliver a test summary report to include:
|
...
- Summation of planned/actual test activities
|
...
- Deviation from planned activities
|
...
- Summary of defects (open defects)
|
...