Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Deck of Cards
idBid
Card
labelSummary

The Project Initiator, usually the Project Manager, uses the bidding process and the bidding module to:

  • Compose a list of potential bidders and receive approval on the bidder list (There is an option to bypass Bid List Approval)
  • Prepare the bid documents and assemble the bid package.
  • Release the bid package through the e-Builder Bidder Portal.
  • Answer and respond to questions about the bid from the bidders.
  • Tabulate and analyze the submitted bids.
  • Make an award recommendation.
  • Gain approval of the award recommendation.
  • Award the bid and notify the winning bidder.
  • Notify bidders not selected.
Note

Until all cost processes are released we will not kick off the e-Builder commitment/purchase order process after awarding the bid.

Card
labelProcess Map


Card
labelStep Descriptions

To make the Step descriptions for Bidding easier to read they have been separated into the three parts (tabs). 

Deck of Cards
idSDBid
historyfalse
Card
labelBid List Approval

Toggle Cloak
1. Start Process (Complete Initial Bidding Form)

Cloak
  • The Bidding process is usually started by the Project Manager.
  • The OCP Planner, SPT Lead, SPT Commissioning Lead or VPF Strategic Sourcing may also start the process.
  • The initiator fills out the Contract Management, Potential Bidders, and if required the Sole Source sections of the process form. When finished, click the Submit button.
  • The next step is Skip Bid List Approval?

Bid list approval is always required except in the following cases involving a general contractor. (GC)

  • GC Bid following pre-construction bidding.
  • Subsequent LSW's or Exhibit A's following the first LSW.

Toggle Cloak
2. Furniture or AV Bid? (Decisional StepConditional)

Cloak
  • Based on the entry process initiator's answer to the "Is this a furniture or AV bid?" question in the process this field is evaluated to determine routing for the processis routed.
  • If True (Yes) the next step is Initiator Prepares Bid Documents.
  • If False (No) the next step is Skip Bid List Approval?

Toggle Cloak
3. Skip Bid List Approval (Decisional StepConditional)

Cloak
  • The data field Based on the process initiator's answer to the "Skip Bid List Approval?" conditional question the process is evaluatedrouted.
  • If True (Yes) the process advances past the Bid List Approval part of the process and goes directly to Initiator Prepares Bid Documents. (Step #28 in this document)
  • If False (No) the next step is Bid List Approval.

Toggle Cloak
4. Vendor Manager Reviews Bid List Approval

Cloak
  • The Vendor Manager completes reviews the proposed bidders bidder list, completes any required fields, and has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Program Manager Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
5. Initiator Revise

Cloak
  • The initiator reviews the process, adds comments and makes adjustments as necessary. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Manager Review.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void is chosen the next step is Finish.
 

Toggle Cloak
6. Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields and has Action options fields and has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
7. Campus Construction? (Decisional StepConditional)

Cloak
  • e-Builder uses information previously entered about the project to determine if this is a Campus Construction project.
  • If Yes the next step is SP&T Program?
  • If No the next step is OCP?

 

Toggle Cloak
8. SP&T Program? (Decisional StepConditional)

Cloak
  • e-Builder uses information previously entered to about the project to determine if this is an SP&T Program.
  • If True (Yes) the next step is SPT Director Review.
  • If False (No) the next step is CC Director Review.

Toggle Cloak
9. SPT Director Review

Cloak
  • The SPT Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is CC Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
10. CC Director Review

Cloak
  • The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
11. OCP? (Decisional StepConditional)

Cloak
  • e-Builder evaluates information previously entered to about the project to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review.
  • If False (No) the next step is M&U?

Toggle Cloak
12. OCP Director Review

Cloak
  • The OCP Director reads the comments and reviews the process fields. The OCP Director has options the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
13. M&U? (Decisional StepConditional)

Cloak
  • e-Builder evaluates information previously entered to about the project to determine if this is an M&U program?
  • If Yes the next step is Utilities Program?
  • If No the next step is Campus Services?

Toggle Cloak
14. Utilities Program? (Decisional StepConditional)

Cloak
  • e-Builder evaluates information previously entered to about the project to determine if this is a Utilities Program.
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?

Toggle Cloak
15. Utilities Director Review

Cloak
  • The Utilities Director reads the comments and reviews the process fields. The Utilities Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
16. SEG Program? (Decisional StepConditional)

Cloak
  • e-Builder evaluates information previously entered to about the project  to determine if this is an SEG Program.
  • If True (Yes) the next step is SEG Director Review.
  • If False (No) the next step is O&M Director Review?

Toggle Cloak
17. SEG Director Review

Cloak
  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
18. O&M Director Review

Cloak
  • The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
19. M&U Director Review

Cloak
  • The M&U Director reads the comments and reviews the process fields. The M&U Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge).
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
20. Campus Services? (Decisional StepConditional)

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an Campus Services Program.
  • If True (Yes) the next step is CS Director Review.
  • If False (No) the next step is IBO Director Review?

Toggle Cloak
21. CS Director Review

Cloak
  • The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
  • If If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
22. IBO Director Review

Cloak
  • The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
23. Initiator Revise

Cloak
  • The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • The next step is Sole Source?

Toggle Cloak
24. Approved Bid List (Automatic StepAutomation)

Cloak
  • Automatic step This step generates the Approved Bid List document .from a template
  • The bid list document is placed into the Documents\05 Procurement\0505 Bid Lists (I) folder
  • The next step is Initiator Prepares Bid Documents.
Card
labelRelease to Bid

Toggle Cloak
25. Initiator Prepares Bid Documents

Cloak
  • The initiatorprocess initiator, usually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit Action is taken when finished.
  • The next step is GC Previously Approved?

Toggle Cloak
26. GC Previously Approved? (Decisional Step)

Cloak
  • e-Builder determines, based on information previously entered, if the GC has already been approved.
  • If True (Yes) the next step is Program Manager Reviews Package.
  • If False (No) the next step is Assemble Bid Package.

Toggle Cloak
27. Assemble Bid Package

Cloak
  • The Contract Admin reads the comments and reviews the process fields. The Contract Admin has the option to take an Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Reviews Package
  • If Revise is chosen the next step is Initiator Prepares Bid Documents

Toggle Cloak
28. Program Manager Reviews Package

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Initiator Releases Bid.
  • If Revise is chosen the next step is Initiator Prepares Bid Documents.

Toggle Cloak
29. Initiator Releases Bid

Cloak
  • The initiator (usually the Project Manager) works within the Bidding module to complete the steps that enable the Bidding portal for the bid package.
  • Once the bid has been released the Initiator completes the required process fields, takes the Submit Action.
  • The next step is Initiator Recommend Vendor.
Card
labelBid Award Recommendation

Toggle Cloak
30. Initiator Recommend Vendor

Cloak
  • The initiator receives all the bid documents, reviews them, and selects a vendor for recommendation. All project managers on the project receive a notification when this step is reached. They will fill out the required fields and Submit.
  • The next step is Selection of Source.

Toggle Cloak
31. Selection of Source (Automatic Step)

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
32. Vendor Manager Review of SoS

Cloak
  • The Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Review
  • If Revise is chosen the next step is Initiator Recommend Vendor

Toggle Cloak
33. Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
34. Initiator Revise

Cloak
  • The Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
  • If Submit is chosen the next step is Selection of Source.
  • If Void is chosen the next step is Finish.

Toggle Cloak
35. Campus Construction (Decisional Step)

Cloak
  • e-Builder uses information previously entered to to determine "ownership" of the program.
  • If True (Yes) the next step is SP&T Program.
  • If False (No) the next step is M&U.

Toggle Cloak
36. SP&T Program? (Decisional Step)

Cloak
  • The "Contract managed by a different program" field is evaluated.
  • If True (Yes) the next step is SPT Director Review.
  • If False (No) the next step is Vendor Manager Review of SoS

Toggle Cloak
37. SPT Director Review

Cloak
  • The SPT Director reads the comments and reviews the process fields. The SPT Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
38. M&U (Decisional Step)

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Program?
  • If False the next step is Vendor Manager Review of SoS.

Toggle Cloak
39. Utilities Program (Decisional Step)

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?.

Toggle Cloak
40. Utilities Director Review

Cloak
  • The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
    If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Review.

Toggle Cloak
41. SEG Program

Cloak
  • e-Builder uses information previously entered to determine if this is an SEG Program.
  • If True (Yes) the nest step is SEG Director Review
  • If False (No) the next step is O&M Director Review.

Toggle Cloak
42. SEG Director Review

Cloak
  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
43. O&M Director Review

Cloak

 

  • The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
44. Vendor Manager Review of SoS

Cloak
  • Vendor Manager reads the comments and reviews the process fields. Vendor Manager has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
45. Campus Construction (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is a Campus Construction program.
  • If True (Yes) the next step is CC Director Review.
  • If False (No) the next step is OCP?

Toggle Cloak
46. CC Director Review

Cloak
  • The CC Director reads the comments and reviews the process fields. CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
47. OCP? (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review.
  • If False (No) the next step is M&U?.

Toggle Cloak
48. OCP Director Review

Cloak
  • The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
49. M&U? (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is an M&U program
  • If True (Yes) the next step is M&U Director Review
  • If False (No) the next step is Campus Services?

Toggle Cloak
50. M&U Director Review

Cloak
  • The M&U Director reads the comments and reviews the process fields and has the option to Submit or Revise
  • If Submit is chosen the next step is Initiator Awards Bid
  • If Revise is chosen the next step is Initiator Revise

Toggle Cloak
51. Campus Services? (Decisional Field)

Cloak
  • Multiple fields are evaluated to determine if this is an Campus Services program?
  • If True (Yes) the next step is CS Director Review.
  • If False (No) the next step is IBO Director Review.

Toggle Cloak
52. CS Director Review

Cloak
  • The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
53. IBO Director Review

Cloak

The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.

  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
54. Initiator Award Bid

Cloak
  • The Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
  • The next step is Finish.

64. Finish

Card
idPFI
labelProcess Form Instructions

Contract Management

Potential Bidders

Use the Lookup link to display a menu that allows potential bidders to be added.

Sole Source

Indicate if this is a Sole Source procurement. If it is Sole Source, provide a reason.