The Project Manager uses the bidding process and the bidding module to:
Compose a list of potential bidders and receive approval on the bidder list (There is an option to bypass Bid List Approval)
Prepare the bid documents and assemble the bid package.
Release the bid package through the e-Builder Bidder Portal.
Answer and respond to questions about the bid from the bidders.
Tabulate and analyze the submitted bids.
Make an award recommendation.
Gain approval of the award recommendation.
Award the bid and notify the winning bidder.
Notify bidders not selected.
Note
Until all cost processes are released we will not kick off the commitment/purchase order process after awarding the bid.
Card
label
Process Map
This workflow displays in two images.
Card
label
Step Descriptions
Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division..
Deck of Cards
id
SDBid
history
false
Card
label
Bid List Approval
Toggle Cloak
1. Start Process (Complete Initial Bidding Form)
Cloak
The Bidding process is usually started by the Project Manager.
The OCP Planner, SPT Lead, SPT Commissioning Lead or VPF Strategic Sourcing may also start the process.
The initiator fills out the Contract Management, Potential Bidders, and if required the Sole Source sections of the process form. When finished, click the Submit button.
The next step is Skip Bid List Approval?
Bid list approval is always required except in the following cases involving a general contractor. (GC)
GC Bid following pre-construction bidding.
Subsequent LSW's or Exhibit A's following the first LSW.
Toggle Cloak
2. Furniture or AV Bid? (Decisional Step)
Cloak
The data field Based on the entry to the "Is this a furniture or AV bid?" question in the process this field is evaluated to determine routing for the process.
If True (Yes) the next step is PM Initiator Prepares Bid Documents.
If False (No) the next step is Vendor Manager Review.Skip Bid List Approval?
Toggle Cloak
3. Skip Bid List Approval (Decisional Step)
Cloak
The data field "Skip Bid List Approval?" conditional is evaluated.
If True (Yes) the process advances past the Bid List Approval part of the process and goes directly to Initiator Prepares Bid Documents. (Step #28 in this document)
If False (No) the next step is Vendor Manager ReviewBid List Approval.
Toggle Cloak
4. Vendor Manager ReviewBid List Approval
Cloak
The Vendor Manager completes reviews the proposed bidders list, completes any required fields and has the option to Submit or Revise.
If Submit is chosen the next step is Program Manager Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
5. Initiator Revise
Cloak
The initiator reviews the process, adds comments and makes adjustments as necessary. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
If To Vendor Manager is chosen the next step is Vendor Manager Review.
If To Program Manager is chosen the next step is Program Manager Review.
If Void is chosen the next step is Finish.
Toggle Cloak
6. Program Manager Review
Cloak
The Program Manager reads the comments and reviews the process fields and has Action options to Submit or Revise.
If Submit is chosen the next step is Sole SourceCampus Construction?
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
7. Sole Source? (Decisional Step)
Cloak
The data field "Sole Source?" is evaluated.
If True (Yes) the next step is VPF Procurement Reviews Bid Package
If False (No) the next step is Campus Construction?.
Toggle Cloak
8. Campus Construction? (Decisional Step)
Cloak
e-Builder uses information previously entered to determine if this is a Campus Construction project.
If Yes the next step is SP&T Program?
If No the next step is OCP?
Toggle Cloak
98. SP&T Program? (Decisional Step)
Cloak
e-Builder uses information previously entered to determine if this is an SP&T Program.
If True (Yes) the next step is SPT Director Review.
If False (No) the next step is CC Director Review.
Toggle Cloak
109. SPT Director Review
Cloak
The SPT Director reads the comments and reviews the process fields and has the option to Submit or Revise.
If Submit is chosen the next step is CC Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
1110. CC Director Review
Cloak
The CC Director reads the comments and reviews the process fields and has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
1211. OCP? (Decisional Step)
Cloak
e-Builder evaluates information previously entered to determine if this is an OCP Program.
If True (Yes) the next step is OCP Director Review.
If False (No) the next step is M&U?
Toggle Cloak
1312. OCP Director Review
Cloak
The OCP Director reads the comments and reviews the process fields. The OCP Director has options to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
1413. M&U? (Decisional Step)
Cloak
e-Builder evaluates information previously entered to determine if this is an M&U program?
If Yes the next step is Utilities Program?
If No the next step is Campus Services?
Toggle Cloak
1514. Utilities Program? (Decisional Step)
Cloak
e-Builder evaluates information previously entered to determine if this is a Utilities Program.
If True (Yes) the next step is Utilities Director Review.
If False (No) the next step is SEG Program?
Toggle Cloak
1615. Utilities Director Review
Cloak
The Utilities Director reads the comments and reviews the process fields. The Utilities Director has the option to Submit or Revise.
If Submit is chosen the next step is M&U Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
1716. SEG Program? (Decisional Step)
Cloak
e-Builder evaluates information previously entered to determine if this is an SEG Program.
If True (Yes) the next step is SEG Director Review.
If False (No) the next step is O&M Director Review?
Toggle Cloak
1817. SEG Director Review
Cloak
The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
If Submit is chosen the next step is M&U Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
1918. O&M Director Review
Cloak
The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
If Submit is chosen the next step is M&U Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
2019. M&U Director Review
Cloak
The M&U Director reads the comments and reviews the process fields. The M&U Director has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (Mail Merge).
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
2120. Campus Services? (Decisional Step)
Cloak
e-Builder evaluates information previously entered to determine if this is an Campus Services Program.
If True (Yes) the next step is CS Director Review.
If False (No) the next step is IBO Director Review?
Toggle Cloak
2221. CS Director Review
Cloak
The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
2322. IBO Director Review
Cloak
The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
2423. Initiator Revise
Cloak
The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
The next step is Sole Source?
Toggle Cloak
2524. VPF Procurement Reviews Bid PackageApproved Bid List (Automatic Step)
Cloak
The VPF/Treasury reads the comments and reviews the process fields. The VPF/Treasury has the option to Submit or Revise.
If Submit is chosen the next step is Campus Construction.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
26. Approved Bid List (Automatic Step)
Automatic step generates the Approved Bid List document.
The next step is
Cloak
Automatic step generates the Approved Bid List document.
The next step is Initiator Prepares Bid Documents.
Card
label
Release to Bid
Toggle Cloak
2725. Initiator Prepares Bid Documents
Cloak
The initiator, usually the Project Manager, prepares the bid documents and completes the required fields. The Submit Action is taken when finished.
The next step is GC Previously Approved?
Toggle Cloak
2826. GC Previously Approved? (Decisional Step)
Cloak
e-Builder determines, based on information previously entered, if the GC has already been approved.
If True (Yes) the next step is Program Manager Reviews Package.
If False (No) the next step is DoF Procurement Assembles Assemble Bid Package.
The DOF ProcurementContract Admin reads the comments and reviews the process fieldsDoF Procurement may . The Contract Admin has the option to take an Action to Submit or Revise
If Submit is chosen the next step is Projects Director Program Manager Reviews Package
If Revise is chosen the next step is Initiator Prepares Bid Documents
Toggle Cloak
3028. Program Manager Reviews Package
Cloak
The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
If Submit is chosen the next step is Initiator Releases Bid.
If Revise is chosen the next step is Initiator Prepares Bid Documents.
Toggle Cloak
3129. Initiator Releases Bid (The initiator works in the Bidding Module prior to Submitting this step)Bi
Cloak
The initiator (usually the Project Manager) must, prior to releasing the Bid, work works within the Bidding module to complete the steps that enable the Bidding portal for the particular bid package.
Once the bid has been released the initiator Initiatorcompletes the required process fields, takes the SubmitAction.
The next step is Initiator Recommends Recommend Vendor.
Card
label
Bid Award Recommendation
Toggle Cloak
3230. Initiator Recommend Vendor
Cloak
The initiator receives all the bid documents, reviews them, and selects a vendor for recommendation. All project managers on the project receive a notification when this step is reached. They will fill out the required fields and Submit.
The next step is Selection of Source.
Toggle Cloak
3331. Selection of Source (Automatic Step)
Cloak
This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
The next step is DoF Procurement Reviews Selection.
Toggle Cloak
34. DoF Procurement Reviews Selection32. Vendor Manager Review of SoS
Cloak
DoF ProcurementVendor Manager reviews the selection and has the option to take the Action to Submit or Revise
If Submit is chosen the next step is Program Manager Review
If Revise is chosen the next step is Initiator Recommend Vendor
Toggle Cloak
3533. Program Manager Review
Cloak
The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
If Submit is chosen the next step is Campus Construction.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
3634. Initiator Revise
Cloak
The Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
If Submit is chosen the next step is Selection of Source.
If Void is chosen the next step is Finish.
Toggle Cloak
3735. Campus Construction (Decisional Step)
Cloak
e-Builder uses information previously entered to to determine "ownership" of the program.
If True (Yes) the next step is SP&T Program.
If False (No) the next step is M&U.
Toggle Cloak
3836. SP&T Program? (Decisional Step)
Cloak
The "Contract managed by a different program" field is evaluated.
If True (Yes) the next step is SPT Director Review.
If False (No) the next step is DoF Procurement Review.
Toggle Cloak
3937. SPT Director Review
Cloak
The SPT Director reads the comments and reviews the process fields. The SPT Director has the option to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
4038. M&U (Decisional Step)
Cloak
e-Builder uses information previously entered to determine "ownership" of the program.
If True (Yes) the next step is Utilities Program?
If False the next step is DoF Procurement Review.
Toggle Cloak
41. Utilities Program U (Decisional Step)
Cloak
e-Builder uses information previously entered to determine "ownership" of the program.
If True(Yes) the next step is Utilities Director Review.
If False (No) the next step is SEG Program?.
Toggle Cloak
42. Utilities Director Review
Cloak
The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
If Submit is chosen (Yes) the next step is DoF Procurement Review.Utilities Program?
If Revise is chosen Falsethe next step is Initiator DoF Procurement Review.
Toggle Cloak
4339. SEG Utilities Program (Decisional Step)
Cloak
e-Builder uses information previously entered to determine if this is an SEG Program"ownership" of the program.
If True (Yes) the nest next step is SEG Utilities Director Review.
If False (No) the next step is O&M Director ReviewSEG Program?.
Toggle Cloak
4440. SEG Utilities Director Review
Cloak
The SEG Directorutilities director reads the comments and reviews the process fields. The SEG Director utilities director has the option to take an Action to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revisethe next step is Initiator Review.
Toggle Cloak
41. SEG Program
Cloak
e-Builder uses information previously entered to determine if this is an SEG Program.
If True (Yes) the nest step is SEG Director Review
If False (No) the next step is O&M Director Review.
Toggle Cloak
4542. O&M SEG Director Review
Cloak
The O&M SEG Director reads the comments and reviews the process fields. DoF Procurement The SEG Director has the option to take an Action to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
46. DoF Procurement 43. O&M Director Review
Cloak
DoF ProcurementThe O&M Directorreads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
If Submit is chosen the next step is GC Previously Approved?DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
47. GC Previously Approved? (Decisional Step}44. Vendor Manager Review of SoS
Cloak
Vendor Manager reads the comments and reviews the process fields. Vendor Manager has the option to Submit or Revise.
If Submit is chosen
Cloak
The data field "GC Previously Approved" is evaluated.
If True (Yes) the next step is Campus Construction.
If False (No) Revise is chosen the next step is One Bid?Initiator Revise.
Toggle Cloak
48. One Bid? (Decisional Step)
Cloak
The data field "One Bid" is evaluated.
If True (Yes) the next step is VPF Procurement Review.
If False (No) the next step is Lowest Bid?
Toggle Cloak
49. Lowest Bid? (Decisional Step)
Cloak
The data field Reason Vendor Selected is evaluated to determine If the reason selected is "2.5 Multiple Bidders Selected - Only One Bidder Responded".
If True the next step is VPF Procurement Review.
If False the next step is Lowest Bid?
Toggle Cloak
50. Lowest Bid? (Decisional Step)
Cloak
The data field Reason Vendor Selected is evaluated to determine if the reason selected is "2.2 Adequate price competition (at least 2 quotes): Lowest Bidder Selected. No further explanation required.".
If True (Yes) the next step is Campus Construction.
If False(No) the next step is VPF Procurement Review.
Toggle Cloak
53. VPF Procurement Review
Cloak
The VPF/Treasury reads the comments and reviews the process fields. The VPF/Treasury has the option to Submit or Revise.
If Submit is chosen the next step is Campus Construction.
If Revise is chosen the next step is DoF Procurement Review.
Toggle Cloak
54. Campus Construction (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is a Campus Construction program.
If True (Yes) the next step is CC Director Review.
If False (No) the next step is OCP?
Toggle Cloak
55. CC Director Review
Cloak
The CC Director reads the comments and reviews the process fields. CC Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
56. OCP? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an OCP Program.
If True (Yes) the next step is OCP Director Review.
If False (No) the next step is M&U?.
Toggle Cloak
57. OCP Director Review
Cloak
The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
58. M&U? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an M&U program
If True (Yes) the next step is M&U Director Review
If False (No) the next step is Campus Services?
Toggle Cloak
59. M&U Director Review
Cloak
The M&U Director reads the comments and reviews the process fields and has the option to Submit or Revise
If Submit is chosen the next step is Initiator Awards Bid
If Revise is chosen the next step is Initiator Revise
Toggle Cloak
60. Campus Services? (Decisional Field)
Cloak
Multiple fields are evaluated to determine if this is an Campus Services program?
If True (Yes) the next step is CS Director Review.
If False (No) the next step is IBO Director Review.
Toggle Cloak
61. CS Director Review
Cloak
The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
62. IBO Director Review
Cloak
The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
63. Initiator Award Bid
Cloak
The initiator reviews the process and awards the bid using the e-Builder Bidding module. The initiator Submits.
The next step is Finish.
64. Finish
Card
id
PFI
label
Process Form Instructions
Contract Management
Potential Bidders
Use the Lookup link to display a menu that allows potential bidders to be added.
Sole Source
Indicate if this is a Sole Source procurement. If it is Sole Source, provide a reason.