The Project Manager uses the bidding process and the bidding module to:
Compose a list of potential bidders and receive approval on the bidder list
Prepare the bid documents and assemble the bid package
Release the bid package through the e-Builder Bidder Portal
Answer and respond to questions about the bid from the bidders
Tabulate and analyze the submitted bids
Make an award recommendation
Gain approval of the award recommendation
Award the bid and notify the winning bidder
Notify bidders not selected
Awarding the bid in e-Builder kicks off the commitment/purchase order process
.
Card
label
Process Map
Card
label
Step Descriptions
Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division..
Deck of Cards
id
SDBid
history
false
Card
label
Bid List Approval
Toggle Cloak
1. Start
Cloak
The Bidding process is started by the Project Manager, OCP Planner, SPT Lead, SPT Commissioning Lead or VPF Strategic Sourcing. Regardless of who initiates the process the final step is Submit.
The next step is A133 Been Signed?
Toggle Cloak
2. Furniture or AV Bid? (Decisional Step)
Cloak
The data field "Is this a furniture or AV bid" is evaluated.
If True (Yes) the next step is PM Prepares Bid Documents.
If False (No) the next step is Vendor Manager Review.
Toggle Cloak
3. A133 Been Signed? (Decisional Step)
Cloak
The data field "Has the A133 Been Signed?" is evaluated.
If True (Yes) the next step is PM Prepares Bid Documents.
If False (No) the next step is Vendor Manager Review.
Toggle Cloak
4. Vendor Manager Review
Cloak
The Vendor Manager completes the required fields and has the option to Submit or Revise.
If Submit is chosen the next step is Program Manager Reviews.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
5. Initiator Revise
Cloak
The initiator reviews the process adds comments and makes adjustments as necessary. The options for the indicator are To Vendor Manager, To Program Manager or Void.
If To Vendor Manager is chosen the next step is Vendor Manager Review.
If To Program Manager is chosen the next step is Program Manager Review.
If Void is chosen the next step is Finish.
Toggle Cloak
6. Program Manager Review
Cloak
The Program Manager reads the comments and reviews the process fields. The Program Manager has options to Submit or Revise.
If Submit is chosen the next step is Sole Source?
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
7. Sole Source? (Decisional Step)
Cloak
The data field "Sole Source?" is evaluated.
If True (Yes) the next step is VPF Procurement Reviews Bid Package
If False (No) the next step is Campus Construction?.
Toggle Cloak
8. Campus Construction? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is a Campus Construction project.
If Yes the next step is SP&T Program?
If No the next step is OCP?
Toggle Cloak
9. SP&T Program? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an SP&T Program.
If True (Yes) the next step is VPF Strategic Sourcing Review.
If False (No) the next step is Projects Director Review.
Toggle Cloak
10. SPT Director Review
Cloak
The SPT Director reads the comments and reviews the process fields and has the option to Submit or Revise.
If Submit is chosen the next step is CC Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
11. Projects Director Review
Cloak
The Projects Director reads the comments and reviews the process fields and has the option to Submit or Revise.
If Submit is chosen the next step is CC Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
12. CC Director Review
Cloak
The CC Director reads the comments and reviews the process fields and has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
13. OCP? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an OCP Program.
If True (Yes) the next step is OCP Director Review.
If False (No) the next step is M&U?
Toggle Cloak
14. OCP Director Review
Cloak
The OCP Director reads the comments and reviews the process fields. The OCP Director has options to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
15. M&U? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an M&U program?
If Yes the next step is Utilities Program?
If No the next step is Campus Services?
Toggle Cloak
16. Utilities Program? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is a Utilities Program.
If True (Yes) the next step is Utilities Director Review.
If False (No) the next step is SEG Program?
Toggle Cloak
17. Utilities Director Review
Cloak
The Utilities Director reads the comments and reviews the process fields. The Utilities Director has the option to Submit or Revise.
If Submit is chosen the next step is M&U Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
18. SEG Program? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an SEG Program.
If True (Yes) the next step is SEG Director Review.
If False (No) the next step is O&M Director Review?
Toggle Cloak
19. SEG Director Review
Cloak
The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
If Submit is chosen the next step is M&U Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
20. O&M Director Review
Cloak
The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
If Submit is chosen the next step is M&U Director Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
21. M&U Director Review
Cloak
The M&U Director reads the comments and reviews the process fields. The M&U Director has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (Mail Merge).
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
22. Campus Services? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an Campus Services Program.
If True (Yes) the next step is CS Director Review.
If False (No) the next step is IBO Director Review?
Toggle Cloak
23. CS Director Review
Cloak
The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
24. IBO Director Review
Cloak
The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
25. Initiator Revise
Cloak
The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
The next step is Sole Source?
Toggle Cloak
26. VPF Procurement Reviews Bid Package
Cloak
The VPF/Treasury reads the comments and reviews the process fields. The following are the possible actions.
If Submit is chosen the next step is Campus Construction.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
27. Approved Bid List (Automatic Step)
Cloak
Automatic step generates the Approved Bid List document.
The next step is Initiator Prepares Bid Documents.
Card
label
Release to Bid
Toggle Cloak
28. Initiator Prepares Bid Documents
Cloak
The initiator prepares the bid documents, completes the required fields and Submits when finished.
The next step is DOF Procurement Assembles Bid Package.
Toggle Cloak
29. Has A133 Been Signed? (Decisional Step)
Cloak
The data field "Has the A133 been signed?" is evaluated.
If True (Yes) the next step is Program Manager Reviews Package.
If False (No) the next step is DoF Procurement Assembles Bid Package.
Toggle Cloak
30. DoF Procurement Assembles Bid Package
Cloak
The DOF Procurement reads the comments and reviews the process fields DoF Procurement may Submit or Revise
If Submit is chosen the next step is Projects Director Reviews Package
If Revise is chosen the next step is PM Prepares Bid Documents
Toggle Cloak
31. Program Manager Reviews Package
Cloak
The program manager reads the comments and reviews the process fields. The program manager has the option to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Assembles Bid Package.
If Revise is chosen the next step is PM Prepares Bid Documents.
Toggle Cloak
32. Projects Director Reviews Package
Cloak
The Projects Director reads the comments and reviews the process fields The Projects Director may Submit of Revise.
If Submit is chosen the next step is Release to Bid (Mail Merge).
If Revise is chosen the next step is PM Prepares Bid Documents.
Toggle Cloak
33. Initiator Releases Bid
Cloak
The initiator completes the required process fields, Submits and uses the e-Builder Bidding module to send the bids to the approved bid list.
The next step is Initiator Recommends Vendor.
Card
label
Bid Award Recommendation
Toggle Cloak
34. Initiator Recommend Vendor
Cloak
The initiator receives all the bid documents, reviews them, and selects a vendor for recommendation. All project managers on the project receive a notification when this step is reached. They will fill out the required fields and Submit.
The next step is Selection of Source.
Toggle Cloak
35. Selection of Source (Automatic Step)
Cloak
This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
The next step is Program Manager Review.
Toggle Cloak
36. DoF Procurement Reviews Selection
Cloak
DoF Procurement reviews the selection and has the option to Submit or Revise
If Submit is chosen the next step is Program Manager Review
If Revise is chosen the next step is Initiator Recommend Vendor
Toggle Cloak
37. Program Manager Review
Cloak
The program manager reads the comments and reviews the process fields. The program manager has the option to Submit or Revise.
If Submit is chosen the next step is Campus Construction.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
38. Initiator Revise
Cloak
The initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
If Submit is chosen the next step is Selection of Source.
If Void is chosen the next step is Finish.
Toggle Cloak
39. Campus Construction (Decisional Step)
Cloak
Multiple fields are evaluated to determine "ownership of the program".
If True (Yes) the next step is SP&T Program.
If False (No) the next step is M&U.
Toggle Cloak
40. SP&T Program? (Decisional Step)
Cloak
The "Contract managed by a different program" field is evaluated.
If True (Yes) the next step is VPF Strategic Sourcing Review.
If False (No) the next step is Project Director Review.
Toggle Cloak
41. SPT Director Review
Cloak
The SPT Director reads the comments and reviews the process fields. The SPT Director has the option to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
42. Projects Director Review
Cloak
The projects director reads the comments and reviews the process fields. The Projects Director has the option to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
43. M&U (Decisional Step)
Cloak
Multiple fields are evaluated to determine ownership of the program.
If True (Yes) the next step is Utilities Program?
If False the next step is DoF Procurement Review.
Toggle Cloak
44. Utilities Program (Decisional Step)
Cloak
Multiple fields are evaluated to determine "ownership of the program".
If True (Yes) the next step is Utilities Director Review.
If False (No) the next step is SEG Program?.
Toggle Cloak
45. Utilities Director Review
Cloak
The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Review.
Toggle Cloak
46. SEG Program
Cloak
Multiple fields are evaluated to determine if this is an SEG Program.
If True (Yes) the nest step is SEG Director Review
If False (No) the next step is O&M Director Review.
Toggle Cloak
47. SEG Director Review
Cloak
The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
48. O&M Director Review
Cloak
The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
If Submit is chosen the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
49. DoF Procurement Review
Cloak
DoF Procurement reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
If Submit is chosen the next step is A133 Been Signed?.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
50. A133 Been Signed? (Decisional Step}
Cloak
The data field "Has the A133 Been Signed" is evaluated.
If True (Yes) the next step is Campus Construction.
If False (No) the next step is >10M
Toggle Cloak
51. >10M (Decisional Step)
Cloak
The data field ">10M" is evaluated.
If True (Yes) the next step is VPF Procurement Review.
If False (No) the next step is One Bid?
Toggle Cloak
52. One Bid? (Decisional Step)
Cloak
The data field Reason Vendor Selected is evaluated to determine If the reason selected is "2.5 Multiple Bidders Selected - Only One Bidder Responded".
If True the next step is VPF Procurement Review.
If False the next step is Lowest Bid?
Toggle Cloak
53. Lowest Bid? (Decisional Step)
Cloak
The data field Reason Vendor Selected is evaluated to determine if the reason selected is "2.2 Adequate price competition (at least 2 quotes): Lowest Bidder Selected. No further explanation required.".
If True the next step is Campus Construction.
If False the next step is VPF Procurement Review.
Toggle Cloak
54. VPF Procurement Review
Cloak
The VPF/Treasury reads the comments and reviews the process fields. The VPF/Treasury has the option to Submit or Revise.
If Submit is chosen the next step is Campus Construction.
If Revise is chosen the next step is DoF Procurement Review.
Toggle Cloak
55. Campus Construction (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is a Campus Construction program.
If True (Yes) the next step is CC Director Review.
If False (No) the next step is OCP?
Toggle Cloak
56. CC Director Review
Cloak
The CC Director reads the comments and reviews the process fields. CC Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
57. OCP? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an OCP Program.
If True (Yes) the next step is OCP Director Review.
If False (No) the next step is M&U?.
Toggle Cloak
58. OCP Director Review
Cloak
The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
59. M&U? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an M&U program
If True (Yes) the next step is M&U Director Review
If False (No) the next step is Campus Services?
Toggle Cloak
60. M&U Director Review
Cloak
The M&U Director reads the comments and reviews the process fields and has the option to Submit or Revise
If Submit is chosen the next step is Initiator Awards Bid
If Revise is chosen the next step is Initiator Revise
Toggle Cloak
61. Campus Services? (Decisional Field)
Cloak
Multiple fields are evaluated to determine if this is an Campus Services program?
If True (Yes) the next step is CS Director Review.
If False (No) the next step is IBO Director Review.
Toggle Cloak
62. CS Director Review
Cloak
The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
63. IBO Director Review
Cloak
The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
If Submit is chosen the next step is Initiator Awards Bid.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
64. Initiator Award Bid
Cloak
The initiator reviews the process and awards the bid using the e-Builder Bidding module. The initiator Submits.