Card |
---|
| This process can be started by the Project Coordinator, Project Manager, Administrative Assistant, OCP Planner, SPT Commissioning Lead, SPT Lead, VPF Strategic Sourcing. |
Cloak |
---|
- The SEG Director reviews the process and contract, then takes the Submit action.
- The next step is Contract <$5m.
|
Card |
---|
| Image Added |
Card |
---|
| 1. Initiation Cloak |
---|
- The Project Coordinator or Project Manager fills out the required fields and executes the Submit action.
- The next step is PM Initiate Process?
| 2. PM Initiate Process (Decisional Step) Cloak |
---|
- The PM Initiate Process? conditional step determines the path the process will take based on if the Data Field “Did the PM Initiate the Process?” has a value of “Yes”.
- If the value is Yes the next step is Contract Required?
- If the value is False the next step is PM Review?
| 3. PM Review Cloak |
---|
- The PM reviews the process and verifies the Contract or PO being added to the project and chooses the Submit action.
- The next step is Contract Required?
| 4. Contract Required? (Decisional Step) Cloak |
---|
- Multiple fields are evaluated to determine the path that the process will take.
- If True the next step is Construction?
- If False the next step is Purch Req MM.
| 5. Construction? Cloak |
---|
- Multiple fields are evaluated to determine the path the process will take.
- If True the next step is eB Admin Updates CSI Codes.
- If False the next step is DoF Procurement Reviews.
| 6. eB Admin Uploads CSI Codes Cloak |
---|
- eB Admin runs the bid tabulation report and combines it with the process import template to do a quick upload into the processes to get the CSI and GL information on the commitment line item custom fields. Through the import the following Submit action is taken.
- The next step is DoF Procurement Review.
| 7. DoF Procurement Review Cloak |
---|
- DoF Procurement reviews the process and executes the Submit action.
- The next step is Contract Admin Assembles Contract.
| 8. Contract Admin Assembles Contract Cloak |
---|
- The Contact Admin reviews the process and uploads the assembled contract to be executed and has the option to take an acton to Submit or Revise.
- If Submit is chosen the next step is Initiator Reviews Contract.
- If Revise is chosen the next step is DoF Procurement Reviews.
| 9. Initiator Reviews Contract Cloak |
---|
- The initiator reviews the contract and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is DoF Procurement Releases Contract.
- If Revise is chosen the next step is Contract Admin Assembles Contract.
| 10. DoF Procurement Releases Contract Cloak |
---|
- DoF Procurement reviews the contract and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Vendor Executes Contract.
- If Revise is chosen the next step is Contact Admin Assembles Contract.
| 11. Vendor Executes Contract Cloak |
---|
- The Vendor reviews, signs and uploads the contract. The Vendor has the option to Submit or Revise. (Request Revision)
- If Submit is chosen the next step is Vendor Signature Step.
- If Revise is chosen the next step is DoF Procurement Releases Contract.
| 12. Vendor Signature Step Cloak |
---|
- The Vendor Signature Step finalizes the vendor's electronic signature with DocuSign allowing for the next person to sign the document. A Code Complete action is automatically taken.
- The next step is DoF Procurement Approves Contract.
| 13. DoF Procurement Approves Contract Cloak |
---|
- DoF Procurement reviews the process and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Campus Construction.
- If Revise is chosen the next step is Initiator Revise.
| 14. Campus Construction? Cloak |
---|
- The Campus Construction step determines the path the process will take based on the Program Type and if the contract is managed by a different program.
- If True (Yes) the next step is SP&T Program?
- If False (No) the next step is OCP?
| 15. SP&T Program? Cloak |
---|
- The SP&T Program? Step determines the path the process will take based on the Program Type or if the project is managed by a different program.
- If True (Yes) the next step is VPF Strategic Sourcing Review.
- If False (No) the next step is Projects Director Review.
| 16. VPF Strategic Sourcing Review Cloak |
---|
- The VPF Strategic Sourcing Director reviews the process and contract, then takes the Submit action.
- The next step is Contract <10M
| 17. Projects Director Review Cloak |
---|
- The Projects Director reviews the process and contract, then takes the Submit action.
- The next step is Contract <$10M
| 18. Contract <$10M Cloak |
---|
- The Contract <$10M conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $10M.
- If True (Yes) the next step is CC Director Executes Contract.
- If False (No) the next step is CC Director Review.
| 19. CC Director Executes Contract Cloak |
---|
- The CC Director reviews the process and executes the contact, then takes the Submit action.
- The next step is Contract Signature.
| 20. CC Director Review Cloak |
---|
- The CC Director reviews the process and the contract, then takes the Submit action.
- The next step is Contract <$100M.
| 21. OCP? Cloak |
---|
- The OCP? conditional step determines the path the takes based on Program Type or if the contract is managed by a different program.
- If True (Yes) the next step is Contract <$500K.
- If False (No) the next step is M&U?
| 22. Contract <$500K Cloak |
---|
- The Contract <$500K conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $500K.
- If True (Yes) (<) the next step is OCP Director Executes.
- If False (No) (>) the next step is OCP Director Review.
| 23. OCP Director Executes Contract Cloak |
---|
- The OCP Director reviews the process and executes the contract then takes the Submit action.
- The next step is Contract Signature.
| 24. OCP Director Review Cloak |
---|
- The OCP Director reviews the process and contract then takes the Submit action.
- The next step is Contract <$100m.
| 25. M&U? Cloak |
---|
- The M & U? Conditional step will determine the path the process takes based on the Program Type or if the contract is managed by a different program
- If True (Yes) the next step is Utilities Program.
- If False (No) the next steep is Campus Services.
| 26. Utilities Program? Cloak |
---|
- The Utilities Program? Conditional step will determine the path process takes based on the Program Type or if the contract is managed by a different program.
- If True (Yes) the next step is Contract <$100K.
- If False (No) the next step is SEG Program.
| 27. Contract <$100K Cloak |
---|
- The Contract < $100k conditional step determines the path process takes based on the Current Commitment Value being greater than or less than $100k.
- If True (Yes) the next step is Utilities Director Execute.
- If False (No) the next step is Utilities Director Review.
| 28. Utilities Director Executes Contract Cloak |
---|
- The Utilities Director reviews the process and executes the contract, then takes the Submit action.
- The next step is Contract Signature.
| 29. Utilities Director Review Cloak |
---|
- The Utilities Director reviews the process and contract, then takes the Submit action.
- The next step is Contract <$5m.
| 30. SEG Program? Cloak |
---|
- The SEG Program? conditional step determines the path the process takes based on the Program Type or if the contract is managed by a different program, Contract Program Type = SEG.
- If True (Yes) the next step is Contract <$100k.
- If False (No) the next step is Contract <$100k.
| 31. Contract <$100k Cloak |
---|
- The Contract < $100k conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $100k.
- If True (Yes) the next step is O&M Director Execute.
- If False (No) the next step is O&M Director Review.
| 32. O&M Director Executes Contract Cloak |
---|
- The O&M Director reviews the process and executes the contract, then takes the Submit action.
- The next step is Contract Signature.
| 33. O&M Director Review Cloak |
---|
- tThe O&M Director reviews the process and contract, then takes the Submit action.
- The next step is Contract <$5m
| 34. Contract <$100k Cloak |
---|
- The Contract < $100k conditional step determines the path process takes based on the Current Commitment Value being greater than or less than $100k.
- If True (Yes) the next step is SEG Director Execute.
- If False (No) the next step is SEG Director Review.
| 35. SEG Director Executes Contract Cloak |
---|
- The SEG Director reviews the process and executes the contract, then takes the Submit action.
- The next step is Contract Signature.
| 36. SEG Director Review Cloak |
---|
- The SEG Director reviews the process and the contract, then takes the Submit action.
- The next step is Contract <$100m.
| 37. Contract < $5m Cloak |
---|
- The Contract < $5m conditional step will determine the path process takes based on the Current Commitment Value being greater than or less than $5m.
- If True (Yes) the next step is M&U Director Executes Contract.
- If False (No) the next step is M&U Director Review.
| 38. M&U Director Executes Contract Cloak |
---|
- The M&U Director reviews the process and executes the contract, then takes the Submit action.
- The next step is Contract Signature.
| 39. M&U Director Review Cloak |
---|
- The M&U Director reviews the process and the contract, then takes the Submit action.
- The next step is Contract <$100m.
| 40. Campus Services? Cloak |
---|
- The Campus Services? Conditional step determines the path the process takes based on the Program Type or if the contract is managed by a different program, Contract Program Type = Campus Services..
- If True (Yes) the next step is Contract <$5m.
- If False (No) the next step is Contract <$10m.
| 41. Contract <$5m Cloak |
---|
The Contract < $5m conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $5m. If True (Yes) the next step is CS Director Execute. If False (No) the next step is CS Director Review. | 42. CS Director Executes Contract Cloak |
---|
- The CS Director reviews the process and executes the contract, then takes the Submit action.
- The next step is Contract Signature.
| 43. CS Director Reviews Contract Cloak |
---|
- The CS Director reviews the process and the contract, then takes the Submit action.
- The next step is Contract < $100m .
| 44. Contact < $10m Cloak |
---|
- The Contract <$10m conditional step determines the path the process takes based on the Current Commitment value being greater than or less than $10m.
- If True (Yes) the next step is IBO Director Executes Contract.
- If False (No) the next step is IBO Director Reviews Contract.
| 45. IBO Director Executes Contract Cloak |
---|
- The IBO Director reviews the process and executes the contract, then takes the Submit action.
- The next step is Contract Signature.
| 46. IBO Director Reviews Contract Cloak |
---|
- The IBO Director reviews the process and the contract, then takes the Submit action.
- The next step is Contract <100m.
| 47. Contract <$100m Cloak |
---|
- The Contract <$100m conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $100m.
- If True (Yes) the next step is Deputy EVP Executes Contract.
- If False (No) the next step is Deputy EVPT Review.
| 48. Deputy EVPT Executes Contract Cloak |
---|
- The Deputy EVPT reviews the process, signs the contract and takes the Submit action.
- The next step is Contract Signature.
| 49. Deputy EVPT Reviews Contract Cloak |
---|
- The Deputy EVPT reviews the process and the contract and takes the Submit action.
- The next step is Contract Signature.
| 50. EVPT Office Executes Contract Cloak |
---|
- The EVPT Office reviews the process and the contract and takes the Submit action.
- The next step is Contract Signature.
| 51. Contract Signature Cloak |
---|
- Contract Signature will finalize the director's electronic signatures using DocuSign. Once complete it will automatically take the Code Complete action. (Signifies that e-Builder has completed a task}
- The next step is SAP PO/Contract Hold Step.
| 52. Purchase Req MM Cloak |
---|
- The Purchase req MM step is a mail merge automation that completes the purchase requisition from the purchase requisition template.
- The next step is DoF Procurement Review.
| 53. DoF Procurement Review Cloak |
---|
- DoF Procuremenact - Finance reviews the process and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Vendor Reviews PO.
- If Revise is chosen the next step is Initiator Revise and Resubmit.
| 54. Initiator Revise and Resubmit Cloak |
---|
- The initiator reviews the process, makes all the necessary changes and has the option to Resubmit or Void.
- If Resubmit is chosen the next step is Contract Required?
- If Void is chosen the next step is Finish.
| 55. Vendor Reviews PO Cloak |
---|
- The Vendor reviews the process, signs the PO, and takes the Submit action.
- The next step is DOF Procurement Executes PO.
| 56. DOF Procurement Executes PO Cloak |
---|
- The DoF Procurement reviews the process, signs the PO then takes the Approve action.
- The next step is PO Signature.
| 57. PO Signature Cloak |
---|
- PO Signature will finalize the DoF's electronic signatures using DocuSign. Once complete it will automatically take the Code Complete action. (Signifies that e-Builder has completed a task}
- The next step is SAP PO/Contract Hold Step.
| 58. SAP PO/Contract Hold Step Cloak |
---|
The Admin Assistant reviews the process, adds the PO Number from SAP, then takes the Finish action. The next step is Finish. |
59. Finish |
|