1. Start Cloak |
---|
- The process is started by the Architect Lead who completes the required fields and takes the Submit action.
- The next step is PSA Mail Merge.
| 2. PSA Mail Merge (System Step) Cloak |
---|
- The e-Builder system creates a mail merge document using the PSA template and ads it to ...
- The next step is Vendor Signs
| 3. Vendor Signs Cloak |
---|
- The vendor reviews the generated mail merge document and has the option to take action to Submit or Revise
- If Submit is chosen the next step is Project Manager Review
- If Revise is chosen the next step is Initiator Revise
| 4. Project Manager Review Cloak |
---|
- The Project Manager reviews the process, adds comments if necessary and takes one of the following actions, Submit, Revise or Void
- If Submit is chosen the next step is Financial Analyst Adjusts Funding
- If Revise is chosen the next step is Initiator Revise
- If Void is chosen the next step is Finish,
| 5. Initiator Revise Cloak |
---|
- The Project Manager reads the comments and reviews the process fields and updates as necessary, then takes the Resubmit action.
- The next step is Project Manager Review.
| 6. Additional Funding? (Decisional Step) Cloak |
---|
- The Additional Funding Required field is evaluated to determine if the value is Yes.
- If the value is Yes (True) then the next step is Spawn Budget Change (03.03).
- If the value is No (False) then the next step is Program Manager Reviews.
| 7. Program Manager Reviews Cloak |
---|
- The Program Manager reads the comments, reviews the process fields and has the option to Submit or Revise.
- If Submit is chosen the next step is
- If Revise is chosen the next step is Initiator Revise.
| 8. Program Type Util? (Decisional Step) Cloak |
---|
- This is a decisional step that evaluates the Project Type field to determine if this is a Util Program Type.
- If True the next step is Director of Utilities Review.
- If False the next step is Director of Projects Review.
|
9. Director of Utilities Review
Cloak |
---|
- The Director of Utilities reads the comments and reviews the process fields and has the option to choose between the actions Reviewed and Revise.
- If Reviewed is chosen, the next step is DoF Procurement Review.
- If Revise is chosen the next step is Initiator Revise.
| 10. Director of Projects Review Cloak |
---|
- The Director of Projects reads the comments and reviews the process fields and has the option to choose between the actions Reviewed and Revise.
- If Reviewed is chosen, the next step is DoF Procurement Review.
- If Revise is chosen the next step is Initiator Revise.
| 11. DoF Procurement Review Cloak |
---|
- The DoF Procurement reads the comments and reviews the process fields and chooses between actions to Submit or Revise.
- If Submit is chosen the next step is Contract > $100M?
- If Revise is chosen the next step is Initiator Revise.
| 12. Campus Construction? (Decisional Step) Cloak |
---|
- Multiple process fields are evaluated to determine if this is a Campus Construction project and to determine the next step.
- When True is evaluated the next step is SP&T Program.
- When False is determined the next step is OCP?
| 13. SP&T Program (Decisional Step) Cloak |
---|
- Multiple fields are evaluated to determine if this is an SP&T program and to determine the next step.
- When True is evaluated the next step is VPF Strategic Sourcing Review.
- When False is evaluated the next step is Projects Director Review.
| 14. VPF Strategic Sourcing Review Cloak |
---|
- The VPF Strategic Sourcing reads the comments, reviews the process fields and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Contract < $10M
- If Revise is chosen the next step is Initiator Revise.
|
15. Projects Director Review Cloak |
---|
- The Projects Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Contract <$10M
- If Revise is chosen the next step is Initiator Revise.
| 16. Contract <$10M (Decisional Step) Cloak |
---|
- The date field Project Type is evaluated to determine if it is "Capital Renewal".
- If True the next step is CC Director Executes Contract.
- If False the next step is CC Director Review.
| 17. CC Director Review Cloak |
---|
- The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Contract < $100M
- If Revise is chosen the next step is Initiator Revise.
| 18. CC Director Executes Cloak |
---|
- The CC Director reads the comments and reviews the process and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Administrative Assistant Final Review.
- If Revise is chosen the next step is Initiator Revise.
| 19. Contract <$100M (Decisional Step) Cloak |
---|
- The Cost Commitment/Contract Value is evaluated to see if it is < $100,000,000.
- If True the next step is Deputy EVP Executes Contract.
- If False the next step is Deputy EVP Review.
|
|