Project Managers should use this process to:

  • move costs from one GL to another within a project
  • move costs from one project to another project

DoF Accounting will use this process to:

  • convert the project from a Capital to an Expense project
  • move asbestos/moving to a separate cost object
  • convert non-billable time to billable
  • split the project into multiple projects after project completion
Card
labelProcess Map

Card
labelStep Descriptions

Toggle Cloak
1. Initiation

Cloak
  • Started by the Accounting Manager or the Project Manager who fills out the required fields and attaches the associated documents before using the Submit option
  • The next step is Capital Expense

Toggle Cloak
2. Final Invoice?

Cloak

Multiple fields are evaluated to determine the reason for the Journal Voucher

If True the next step is Acct Change eB Info and Create JV

If False the next step is Correct Project GL?

Toggle Cloak
3. Acct Change eB Info and Create JV

Cloak

The Accounting Manager reads the comments and reviews the process fields and executes the Complete option

The next step is Finish

Toggle Cloak
4. Correct Project GL? (Decisional Step)

Cloak

The Reason for JV Request field is evaluated to determine if this JV request is "To correct the cost element to which a cost was changed within a project"

If True (Yes) the next step is PC Creates Budget Change Process

If False (No) the next step is Asbestos Move?

Toggle Cloak
5. PM Creates Budget Change Process

Cloak
  • The project manager reads the comments and reviews the process fields and takes the Complete action
  • The next step is POs on Project?

Toggle Cloak
6. POs on Project? (Decisional Step)

Cloak
  • The data field "Are there any purchase orders on the project" is evalulated
  • If True (Yes) the next step is PM Creates Commitment Change Process
  • If False (No) the next step is Account Creates GL Change JV

Toggle Cloak
7. PM Creates Commitment Change Process

Cloak
  • The project manager  reads the comments and reviews the process fields and takes the Complete action
  • The next step is POs on Project?

Toggle Cloak
8. Account Creates GL Change JV

Cloak
  • The accounting manager reads the comments, reviews the process and takes the Complete action
  • The next step is Finish

Toggle Cloak
9 Asbestos Move? (Decisional Field)

 

Cloak
  • The data field "Asbestos moving to separate cost object?" is evaluated
  • If True (Yes) the next step is Acct Updates eB & Creates Asbestos JV
  • If False (No) the next step is Nonbillable/Billable.