Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Deck of Cards
idMOU
Card
labelSummary

This process starts:

Card
labelProcess Map

Card
labelStep Descriptions

Toggle Cloak
1. Process Start

Cloak
  • The process is started by the spawn step in CRSP Screening Kickoff or by the eB Admin.
  • If initiated by the eB Admin, the eB Admin must complete the Department, Project Description, 100% CRSP Funding and Stage 1 Budget fields.
  • If started by the spawn process those fields will be automatically filled out
  • Next step: PIT Meeting Required

Toggle Cloak
2. PIT Meeting Required? Conditional Step

Cloak
  • The PIT Meeting Required conditional step determines the path the process will take based on if the data field "PIT Meeting Required" has been marked "Yes" in a previous step. It will automatically take one of the following paths:
  • If True (Yes) the next step is PM schedules PIT meeting
  • If False (No) the next step is Provost Office Draft MOU

Toggle Cloak
3. PIT Meeting Occurs

Cloak
  • The Project Manager reviews the process and completes the required fields in the form. When finished the Project Manager clicks SUBMIT.
  • Next Step: Provost Office Draft MOU

Toggle Cloak
4. PM Verifies Team Assignments

Cloak
  • The Project Manager reviews the process, completes the required fields and clicks SUBMIT.
  • Next Step: Provost Office Draft MOU

Toggle Cloak
5. Provost Office Draft MOU

Cloak
  • The Provost Office reviews the process, completes the required fields and clicks SUBMIT to send to the team.
  • Next Step: Team Review

Toggle Cloak
6. Team Review

Cloak
  • IS&T Lead, Project Manager, CC Sustainability, CC Planning Manager, EHS Project Liaison, CR Admin and OCP Planner review the process and then Submit. All actors must complete their tasks and SUBMIT.
  • If a team member has not been assigned the process will continue without input from that person.
  • Next Step: Provost Office Reviews MOU Comments

Toggle Cloak
7. Provost Office Review MOU Comments

Cloak
  • The Provost Office reviews the process, fills out the required fields and clicks SUBMIT.
  • Next Step:  Program Manager MOU Review

Toggle Cloak
8. Program Manager MOU Review

Cloak
  • The Program Manager reviews the process and has the option of either submitting or asking for revisions.
  • If the program manager clicks Submit the next step is PM Final MOU Review
  • If the program manager clicks Revise the next Step: is Provost Office Reviews MOU Comments

Toggle Cloak
9. Project Manager Final MOU Review

Cloak
  • The Project Manager reviews the process and has the option to submit or to request revisions.
  • If the Project Manager chooses Submit then the next step is DRAFT MOU.
  • If the Project Manager chooses Revise then the next step is Provost Office Reviews MOU Comments

Toggle Cloak
10. Draft MOU (Mail Merge Automation Step)

Cloak
  • System performs Draft MOU Mail Merge
  • Next Step: Provost Distributes to DLC for Review

Toggle Cloak
11. Provost Distributes to DLC for Review

Cloak
  • The Provost Office reviews the process, fills out the required fields and clicks SUBMIT.
  • Next Step: PM Enters Benchmark and 51 Estimate

Toggle Cloak
12. Project Manager EBenchmark and S1 Estimate

Cloak
  • The Project Manager reviews the process, fills out the benchmark and Stage 1 data, prints the Stage 1 mail merge and attaches and clicks SUBMIT.
  • Next Step: Program Manager Review

Toggle Cloak
13. Program Manager Review

Cloak
  • The Program Manager reviews the process and had the option to submit or revise.
  • If the program manager clicks Submit the next step is MOU /Stage 1 MM
  • If the program manager clicks Revise the next step is PM Enters Benchmark and 51 Estimate

Toggle Cloak
14. MOU Stage 1 Mail Merge

Cloak
  • The MOU Stage 1 MM step is a mail merge automation step that completes the below items and automatically takes the following action:
  • Next Step: Provost Distributes to DLC for Review

Toggle Cloak
15. CC Dir and Dir of Projects Review

Cloak
  • The CRSP Admin reviews the process, adds comments, and has the option to either Submit or Revise.
  • If Submit is chosen the Next Step is Provost Office Reviews.
  • If Revise is chosen the next step is PM Revises Benchmark or S1 Estimate

Toggle Cloak
16. PM Revises Benchmark or S1 Estimate

Cloak
  • The Project Manager reviews the process, fills out the required fields and sends to the Program Manager.
  • Next Step: Program Manager Review

Toggle Cloak
17. Provost Office Review

Cloak
  • The Provost Office reviews the process, fills out the required fields, and has the option to Submit or to Revise.
  • If Submit is chosen the next step is Start 03.01 Milestone Project Estimate
  • If Revise is chosen the next step is PM Revises Benchmark or S1 Estimate

Toggle Cloak
18. Start Milestone Project Estimate (Spawn Step)

Cloak
  • The Start Milestone Project Estimate spawn step creates a process instance for 03.01 Milestone Project Estimate process.
  •  Next Step: Finish

19. Finish

...