| Workflow Task | Actors |
---|
Who can start this process? | CC Planner, CC Planning Manager, eB Admin, Project Manager, R&M Manager, UTLITIES-Program Manager | Who can view drafts of this process? | CC Planner, CC Planning Manager, Project Manager | Who can view all process instances? | CC Planning Manager, CRSP Admin, eB Admin, Program Manager | Who can report on this process? | All Users | Who is notified as the process moves between steps? | All Users | Who can view/add private comments to this process? | No Users |
|
Card |
---|
| Click > to reveal additional content. Start (Usually by CC Planner) Cloak |
---|
Though usually started by the CC Planner, any of the following may start the process: - CC Planning Manager
- eB Admin
- Project Manager
- R&M Manager
- Utilities - Program Manager
Once required fields are completed the form is submitted. If the process was initiated by CC Planner, the next step is Project Manager Review. If not initiated by CC Planner, the next step is CC Planner Completes PD Form | CC Planner Completes PD Form Cloak |
---|
CC Planner reviews the process, complete the required fields and chooses one of the actions below:One of the following actions will be takenthese actions: Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Project Manager Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: VoidInitiator Review
Status of Process:
Void Causes Field Validation: No Add Comments: Yes, Required Next Step: Finish
|
Project Manager Review Cloak |
---|
Project Manager reviews the process and , completes the required fields . They will take and chooses one of the following actionsthe these actions: - Submit
Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Planning Manager and Prog. Manager Review
- Revise
Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: CC Planner Revise
|
Initiator Review Cloak |
---|
Process Initiator reviews the process and , completes the required fields . They will take the following action: Reply Status of Process: Leave Status Unchanged Causes Field Validation: Yesand clicks Reply.
Next Step: CC Planner Completes PD Form |
CC Planner Revise Cloak |
---|
CC Planner reviews the process and , completes the required fields. They will take the following action: Resubmit Status of Process: Leave Status Unchanged Causes Field Validation: Yes, and clicks Resubmit.
Next Step: Project Manager Review |
Planning Manager and Prog. Manager Review Cloak |
---|
Project Manager and Program Manager review the process and , complete the required fields : They will take and choose one of the following these actions: - Submit
- Status of Process: Leave status unchanged
- Causes Field Validation: Yes
Number of Actors Required to Complete: All Next Step: Working Committee Review
- Revise
- Status of Process: Leave Status Unchanged
- Causes Field Validation: Yes
Add Comments: Yes, Required Next Step: CC Planner Revise
| Working Committee Review Cloak |
---|
CC Planning Manager will review reviews the process with the working committee outside of e-Builder and then complete , completes the required fields . They will take and chooses one of the following these actions: - Submit
- Status of Process: Leave status unchanged
- Causes field Validation: Yes
Number of Actors Required to Complete: All Next Step: Utilities, O&M and SEG Review- Put On HoldStatus of Process: On HoldCauses Field Validation: Yes
- Add Comments: No
Next Step: Finish
| Utilities, O&M and SEG Review Cloak |
---|
Utilities Director, O&M Director, and SEG Assignor will review the process, add their comments and take the following action: Submit Status of Process: Leave Status UnchangedCauses Field Validation: NoAdd Comment: NoNumber of Actors Required to Complete: Allclick Submit. Next Step: CC Director, Ops, and M&U Review | CC Director, Ops, and M&U Review Cloak |
---|
CC Director, M&U Director and IBO Director will review the process, add their comments and take the following action: Submit Status of Process: Leave Status UnchangedCauses Field Validation: NoAdd Comment: NoNumber of Actors Required to Complete: Allclick Submit. Next Step: CRSP Planning Review | DoF Planning Manager (Governance) Cloak |
---|
CC Planning Manager will review reviews the process, add their adds comments, prepare prepares the Capital Renewal List for the RCRSP agenda and take the following action: Submit Status of Process: Leave Status UnchangedCauses Field Validation: NoAdd Comment: Noclicks Submit: Next Step: Spawn Team Assignment | Spawn Team Assignments Cloak |
---|
When a Submit action is taken from the DoF Planning Manager step, the process proceeds to this spawned step. In the spawn step the 2.01 - Team Assignment process starts and is moved to the first step of that workflow. The following action is automatically taken after: Spawn Complete Spawn Process: 02:01 - Team AssignmentSpawn Process Initiator: Automatically SpawnedAttach Process: YesCopy Attached Files: YesNext Step: Finance Office Issues IO Number | Finance Officer Issues IO Number Cloak |
---|
Financial Officer reviews the process, adds the Cost Object Number, and take the following action:clicks Submit. Submit - Status of Process: Leave Status Unchanged
- Causes Field Validation: Yes
- Add Comment: No
- Next Step: Apply Funding
| Apply Funding Cloak |
---|
Financial Analyst reviews the process, applies funding, and takes the following action: Submit - Status of Process: Approved
- Causes Field Validation: Yes
- Add Comment: No
- Next Step: Finish
| Finish Cloak |
---|
This is the terminal step in this process. No instructions are provided. |
|
|