...
Deck of Cards |
---|
|
Card |
---|
| - This process is spawned by the 02.03 CRSP Screening Kickoff (CRSPK) or initiated by the e-B admin for non-CRSP projects. A project manager may initiate this process.
- The process can be reviewed by the e-B admin, Project Manager, and the Program Manager.
- No other processes are spawned by Team Assignment.
|
Card |
---|
| ![](/confluence/download/attachments/117319720/TA%202.01%20Final.jpg?version=1&modificationDate=1474034149000&api=v2) |
Card |
---|
label | Training: Actors and Actions |
---|
| Initiation Cloak |
---|
The process is started by the eB Admin, Project Manager or automatically spawned by the CRSP Screening Process. The initiator fills out the required fields take the following action: Submit - Status of Process: Submitted
- If Project Manager has already been assigned, process moves to Team Assignments w/o Program Manager
- If Project Manager has not been assigned, process moves to Team Assignments
| Team Assignments w/o Program Manager Cloak |
---|
Each actor in this step assigns their respective team members and takes the following action: Submit - Status of Process: Pending
- Next Step: eB Admin
| Team AssignmentsEach actor in this step assigns their respective team members and takes the following action: Submit - Status of Process: Pending
- Next Step: eB Admin
eB Admin eB Admin assigns all team members selected to the project and takes the following action: Complete
- Status of Process: Approved
- Next Step: Finished
| Finished Cloak |
---|
The process is complete |
|
e-Builder Instructions
The names of eligible individuals, as determined by their e-Builder role(s), are displayed in a dropdown menu for each position being filled.
...