Card |
---|
| - The primary actor is the CC Planner who has responsibility for completing this process.
- The planner may work collaboratively with the Project Manager, SEG, Assessor or others while facilitating the addition of the PD form into e-Builder.
- This process spawns the 02.01 Team Assignment (TA) process.
|
Card |
---|
|  |
Card |
---|
| Wiki markup without migration |
---|
h1. Start {toggle-cloak:id=Start}
{cloak:id=My Cloak|visible=true}
Started by the CC Planner, CC Planning Manager, eB Admin, Project Manager, R&M Manager, UTLITIES-Program Manager. They will fill out the required field and take the following action:
Submit
Status of Process: Submitted
Causes Field Validation: Yes
If initiated by CC Planner, process routes to Project Manager Review
If not initiated by CC Planner, process routes to CC Planner Completes PD Form
.
{cloak} |
Started by the | Actor | Action |
---|
CC Planner, CC Planning Manager, eB Admin, PMProject Manager, R&M Manager, Utilities Program Manager Can initiate this process | UTLITIES-Program Manager. They will fill out the required field and take the following action: Submit Status of Process: Submitted Causes Field Validation: Yes If initiated by CC Planner, process routes to Project Manager Review If not initiated by CC Planner, process routes to CC Planner Completes PD Form
- CC Planner Completes PD Form
- CC Planner reviews the process and complete the required fields. One of the following actions will be taken:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Project Manager Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: Initiator Review
Void Status of Process: Void Causes Field Validation: No Add Comments: Yes, Required Next Step: Finish
- Project Manager Review
- Project Manager reviews the process and completes the required fields. They will take one of the following actions:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Planning Manager and Prog. Manager Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: CC Planner Revise
- Initiator Review
- Process Initiator reviews the process and completes the required fields. They will take the following action:
Reply Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: CC Planner Completes PD Form
- CC Planner Revise
- CC Planner reviews the process and completes the required fields. They will take the following action:
Resubmit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Project Manager Review
- Planning Manager and Prog. Manager Review
- Project Manager and Program Manager review the process and complete the required fields. They will take one of the following actions:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Number of Actors Required to Complete: All Next Step: Working Committee Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: CC Planner Revise
- Working Committee Review
- CC Planning Manager will review the process with working committee outside of e-Builder then complete the required fields. They will take one of the following actions:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Number of Actors Required to Complete: All Next Step: Utilities , O&M, and SEG Review
Put on Hold Status of Process: On Hold Causes Field Validation: Yes Add Comments: No Next Step: Finish
- Utilities , O&M, and SEG Review
- Utilities Director, O&M Director, and SEG Assignor will review the process, add their comments and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Number of Actors Required to Complete: All Next Step: CC Director, Ops, and M&U Review
- CC Director, Ops, and M&U Review
- CC Director, M&U Director, and IBO Director will review the process, add their comments and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Number of Actors Required to Complete: All Next Step: CRSP Screening Review
- DoF Planning Manager (Governance)
- CC Planning Manager will review the process, add their comments, prepare the Capital Renewal List for the RCRSP agenda, and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Next Step: Spawn Team Assignment
- Spawn Team Assignments
- When the Submit action is taken from the DoF Planning Manager step, the process will proceed to this spawn step. In the spawn step the 02.01 – Team Assignment process will be started and moved to the first step of that workflow. The following action will be automatically be taken after:
Spawn Complete Spawn Process: 02.01 – Team Assignment Spawn Process Initiator: Automatically Spawned Attach Process: Yes Copy Attached Files: Yes Next Step: Finance Office Issues IO Number
- Finance Officer Issues IO Number
- Financial Officer will review the process, add the Cost Object Number, and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comment: No Next Step: Apply Funding
- Apply Funding
- Financial Analyst will review the process, apply funding, and take the following action:
Submit Status of Process: Approved Causes Field Validation: Yes Add Comment: No Next Step: Finish
- Finish
CC Planner, CC Planning Manager, Project Manager | Can view drafts of this project | CC Planning Manager, CRSP Admin, eB Admin, Program Manager | Can view all process instances | All Users | Can report on this process, are notified as process moves through steps
|