Scheduling gives program managers, Schedules give program/project managers and project participants a single system to coordinate people resources and their project tasks and milestones.

The following activities usually apply to a schedule:

...

Actors Responsibilities

WhoEvent
e-B adminWhen the project is added to e-Builder, applies an MIT-specific template to the project

...

to establish consistent high level tasks across all e-Builder projects. The use of a template at the highest

...

task level also promotes ease of use.
Schedule/Project

...

Managers
  • Update tasks for the new schedule by adjusting dates

...

  • or adding

...

  • tasks below the high level template tasks.

...

  • Change the status of the schedule

...

  • from Draft to Active

...

  • Save a Baseline
  • Save a Snapshot of the baseline
  • Approve changes made to the schedule
Project Resources (participants)Update the schedule for their individual tasks

...

Opening a Project Schedule

Open the Schedule from an open project by clicking the Schedule link in the left- side Project menu or click on the Schedule tab to open the module and then select a project using the Project drop down menu.

Either of these choices opens the Schedule The Schedule Details page appears.

Schedule Details Page

Project Details

...